National Bridge Inventory (NBI) Statistics
Number of bridges: 12
Total length: 41 meters (135ft)
Total costs: $12,253,000
Total average daily traffic: 10,366
Total average daily truck traffic: 734
Total future (year 2016) average daily traffic: 13,374
National Bridge Inventory (NBI) Registered Bridges for Brasher

New bridges - Historical Statistics

  • 1900-1909: 1
  • 1910-1919: 0
  • 1920-1929: 0
  • 1930-1939: 4
  • 1940-1949: 1
  • 1950-1959: 1
  • 1960-1969: 2
  • 1970-1979: 0
  • 1980-1989: 2
  • 1990-1999: 1

Reconstructed bridges - Historical Statistics

  • 1970-1979: 2
  • 1980-1989: 2
  • 1990-1999: 1

Bridge Condition - Deck

Bridge Condition - Superstructure

Bridge Condition - Substructure

Bridge Condition - Channel

Find on map >>

Structure Number: 100886,  Location: 1.4 MI NE JCT US11C & SH4 (Lat: 44.807978,  Lng: -74.772081),  Route carried "on" structure: State highway 11C,  Year Built: 1933,  Year Reconstructed: 1994,  Status: Open,  Structure Length: 1.21m (3.97ft),  Average Daily Traffic: 1,256 (year 2005),  Truck Traffic: 11%,  Average Future Daily Traffic: 1,476 (year 2025),  Design Load: HS 25,  Features Intersected: ST REGIS RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 7.282,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 11.5m (37.7ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 0.0m,  Curb-To-Curb Width: 9.2m (30.2ft),  Out-to-Out Width: 11.3m (37.1ft)

Condition: Deck: Satisfactory,  Superstructure: Excellent,  Substructure: Good,  Channel: Good,  Operating Rating: 81.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 40.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.21m (3.97ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2006,  Bridge Improvement Cost: $1,512,000,  Roadway Improvement Cost: $899,000,  Total Project Cost: $2,411,000 ( Estimate for 2007),  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 100887,  Location: 1.4 MI NE JCT 11C & 420 (Lat: 44.807953,  Lng: -74.772275),  Route carried "on" structure: State highway 11C,  Year Built: 1933,  Year Reconstructed: 1994,  Status: Open,  Structure Length: 4.72m (15.49ft),  Average Daily Traffic: 1,256 (year 2005),  Truck Traffic: 11%,  Average Future Daily Traffic: 1,476 (year 2025),  Design Load: HS 20,  Features Intersected: ST REGIS RIVER
Minimum Vertical Clearance: 0.00m,  Kilometerpoint: 7.266,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 45.7m (149.9ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 0.0m,  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 8.3m (27.2ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 64.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 35.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.72m (15.49ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: August 2006,  Critical Feature Inspection Date: August 2006,  Bridge Improvement Cost: $846,000,  Roadway Improvement Cost: $503,000,  Total Project Cost: $1,349,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 102403,  Location: JCT RTE 37C + ST.REGIS R (Lat: 44.924150,  Lng: -74.722353),  Route carried "on" structure: State highway 37C,  Year Built: 1959,  Year Reconstructed: 1981,  Status: Open,  Structure Length: 9.26m (30.38ft),  Average Daily Traffic: 1,977 (year 2007),  Truck Traffic: 6%,  Average Future Daily Traffic: 2,638 (year 2027),  Design Load: HS 20,  Features Intersected: ST REGIS RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 8.417,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 10.6m (34.8ft),  Material/Design: Prestressed concrete continuous,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 22.5m (73.8ft),  Curb-To-Curb Width: 10.6m (34.8ft),  Out-to-Out Width: 11.3m (37.1ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 70.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 41.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 9.26m (30.38ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2007,  Bridge Improvement Cost: $2,268,000,  Roadway Improvement Cost: $1,316,000,  Total Project Cost: $3,584,000 ( Estimate for 2007),  Wearing Surface/Protective System: Wearing Surface: Integral Concrete
Find on map >>

Structure Number: 22208,  Location: 3 MILES EAST OF HELENA (Lat: 44.924222,  Lng: -74.676642),  Route carried "on" structure: City street ,  Year Built: 1902,  Status: Open,  Structure Length: 0.79m (2.59ft),  Average Daily Traffic: 56 (year 2000),  Truck Traffic: 4%,  Average Future Daily Traffic: 67 (year 2020),  Features Intersected: HUNKINS MARSH,  Facility Carried by Structure: KEENAN ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 4.5m (14.8ft),  Material/Design: Steel,  Design/Construction: Arch - Deck,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.6m (24.9ft)

Condition: Superstructure: Poor,  Substructure: Poor,  Channel: Satisfactory,  Operating Rating: 48.9 metric tons,  Inventory Rating: 14.1 metric tons,  Structural Evaluation: Meets minimum limits,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.79m (2.59ft),  Designated Inspection Frequency: Every 12 months,  Inspection Date: October 2007,  Bridge Improvement Cost: $334,000,  Roadway Improvement Cost: $213,000,  Total Project Cost: $547,000 ( Estimate for 2007),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 226642,  Location: 3.5 MI NE BRASHER FALLS (Lat: 44.835961,  Lng: -74.717667),  Route carried "on" structure: City street ,  Year Built: 1980,  Status: Open,  Structure Length: 1.00m (3.28ft),  Average Daily Traffic: 38 (year 2003),  Truck Traffic: 4%,  Average Future Daily Traffic: 46 (year 2023),  Features Intersected: TROUT BROOK,  Facility Carried by Structure: MURRAY ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 5.4m (17.7ft),  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.5m (14.8ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 75.5 metric tons,  Inventory Rating: 29.3 metric tons,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.00m (3.28ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2007,  Bridge Improvement Cost: $172,000,  Roadway Improvement Cost: $102,000,  Total Project Cost: $274,000 ( Estimate for 2007),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 322085,  Location: LOCATED IN HELENA (Lat: 44.919517,  Lng: -74.722289),  Route carried "on" structure: City street ,  Year Built: 1931,  Status: Open,  Structure Length: 4.54m (14.90ft),  Average Daily Traffic: 2,369 (year 2006),  Truck Traffic: 6%,  Average Future Daily Traffic: 3,161 (year 2026),  Design Load: HS 25,  Features Intersected: DEER RIVER,  Facility Carried by Structure: DEPOT STREET
Minimum Vertical Clearance: 4.52m (14.83ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 44.1m (144.7ft),  Curb or Sidewalk Widths: Left: 1.7m (5.6ft),  Right: 0.0m,  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 7.8m (25.6ft)

Condition: Deck: Good,  Superstructure: Serious,  Substructure: Fair,  Channel: Excellent,  Operating Rating: 59.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: High priority of corrective action,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.54m (14.90ft),  Designated Inspection Frequency: Every 12 months,  Critical Feature Inspection Frequency: Every 12 months,  Inspection Date: October 2007,  Critical Feature Inspection Date: October 2007,  Bridge Improvement Cost: $769,000,  Roadway Improvement Cost: $457,000,  Total Project Cost: $1,226,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 334053,  Location: 2.0 MI E OF HELENA (Lat: 44.929314,  Lng: -74.682167),  Route carried "on" structure: County highway ,  Year Built: 1934,  Year Reconstructed: 1983,  Status: Open,  Structure Length: 1.21m (3.97ft),  Average Daily Traffic: 1,137 (year 2001),  Truck Traffic: 6%,  Average Future Daily Traffic: 1,517 (year 2021),  Features Intersected: HUNKINS MARSH,  Facility Carried by Structure: HELENA-BOMBAY RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.6m (24.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 12.8m (42.0ft),  Curb-To-Curb Width: 10.6m (34.8ft),  Out-to-Out Width: 11.8m (38.7ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 78.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 47.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.21m (3.97ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2007,  Bridge Improvement Cost: $167,000,  Roadway Improvement Cost: $100,000,  Total Project Cost: $267,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 334054,  Location: 2 MILES SW OF HELENA (Lat: 44.896917,  Lng: -74.757506),  Route carried "on" structure: County highway ,  Year Built: 1999,  Status: Open,  Structure Length: 8.19m (26.87ft),  Average Daily Traffic: 617 (year 2000),  Truck Traffic: 6%,  Average Future Daily Traffic: 823 (year 2020),  Design Load: HS 25,  Features Intersected: ST REGIS RIVER,  Facility Carried by Structure: BRASHER FLS-HL RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Skew: 3 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 40.2m (131.9ft),  Curb-To-Curb Width: 8.4m (27.6ft),  Out-to-Out Width: 9.3m (30.5ft)

Condition: Deck: Satisfactory,  Superstructure: Excellent,  Substructure: Good,  Channel: Very good,  Operating Rating: 70.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 41.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 8.19m (26.87ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2007,  Bridge Improvement Cost: $167,000,  Roadway Improvement Cost: $100,000,  Total Project Cost: $267,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 334055,  Location: 1 MI N OF NORTH LAWRENCE (Lat: 44.819961,  Lng: -74.681686),  Route carried "on" structure: County highway ,  Year Built: 1960,  Status: Open,  Structure Length: 1.88m (6.17ft),  Average Daily Traffic: 682 (year 2003),  Truck Traffic: 6%,  Average Future Daily Traffic: 910 (year 2023),  Features Intersected: DEER RIVER,  Facility Carried by Structure: YOUMMELL ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 5.7m (18.7ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 18.2m (59.7ft),  Curb-To-Curb Width: 6.6m (21.7ft),  Out-to-Out Width: 7.2m (23.6ft)

Condition: Deck: Poor,  Superstructure: Poor,  Substructure: Good,  Channel: Good,  Operating Rating: 39.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 22.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.88m (6.17ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2007,  Bridge Improvement Cost: $296,000,  Roadway Improvement Cost: $176,000,  Total Project Cost: $472,000 ( Estimate for 2007),  Deck Structure Type: Open Grating
Find on map >>

Structure Number: 334056,  Location: 3 MI N OF NORTH LAWRENCE (Lat: 44.844397,  Lng: -74.686903),  Route carried "on" structure: County highway ,  Year Built: 1962,  Status: Open,  Structure Length: 2.92m (9.58ft),  Average Daily Traffic: 643 (year 2001),  Truck Traffic: 6%,  Average Future Daily Traffic: 858 (year 2021),  Features Intersected: DEER RIVER,  Facility Carried by Structure: YOUMMELL ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 5.7m (18.7ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 28.0m (91.9ft),  Curb-To-Curb Width: 7.2m (23.6ft),  Out-to-Out Width: 7.2m (23.6ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 35.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 20.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 2.92m (9.58ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2006,  Bridge Improvement Cost: $296,000,  Roadway Improvement Cost: $176,000,  Total Project Cost: $472,000 ( Estimate for 2007),  Deck Structure Type: Open Grating
Find on map >>

Structure Number: 334058,  Location: LOCATED IN BRASHER IRON W (Lat: 44.892339,  Lng: -74.693217),  Route carried "on" structure: City street ,  Year Built: 1947,  Status: Open,  Structure Length: 2.92m (9.58ft),  Average Daily Traffic: 244 (year 2003),  Truck Traffic: 4%,  Average Future Daily Traffic: 293 (year 2023),  Features Intersected: DEER RIVER,  Facility Carried by Structure: SMITH ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 4.5m (14.8ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 14.0m (45.9ft),  Curb-To-Curb Width: 6.1m (20.0ft),  Out-to-Out Width: 6.8m (22.3ft)

Condition: Deck: Fair,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Very good,  Operating Rating: 32.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 20.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Meets minimum limits,  Length Of Structure Improvement: 2.92m (9.58ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2007,  Bridge Improvement Cost: $434,000,  Roadway Improvement Cost: $258,000,  Total Project Cost: $692,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 33406,  Location: 2.5 MI N OF NO LAWRENCE (Lat: 44.857936,  Lng: -74.673425),  Route carried "on" structure: City street ,  Year Built: 1989,  Year Reconstructed: 2001,  Status: Open,  Structure Length: 3.01m (9.88ft),  Average Daily Traffic: 91 (year 1996),  Truck Traffic: 4%,  Average Future Daily Traffic: 109 (year 2016),  Design Load: HS 20,  Features Intersected: DEER RIVER,  Facility Carried by Structure: HURLEY ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 4.5m (14.8ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 29.2m (95.8ft),  Curb-To-Curb Width: 4.5m (14.8ft),  Out-to-Out Width: 5.4m (17.7ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Very good,  Channel: Very good,  Operating Rating: 43.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 27.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.01m (9.88ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2007,  Bridge Improvement Cost: $434,000,  Roadway Improvement Cost: $258,000,  Total Project Cost: $692,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing

Discuss this city on our hugely popular New York forum

Back to: Brasher, NY, New York, All US cities.


City-data.com does not guarantee the accuracy or timeliness of any information on this site.  Use at your own risk.
Some parts © 2009 Advameg, Inc.