National Bridge Inventory (NBI) Statistics
Number of bridges: 13
Total length: 16 meters (52ft)
Total costs: $4,715,000
Total average daily traffic: 33,120
Total average daily truck traffic: 3,001
Total future (year 2027) average daily traffic: 52,307
National Bridge Inventory (NBI) Registered Bridges for Cheshire

New bridges - Historical Statistics

  • 1900-1909: 1
  • 1910-1919: 0
  • 1920-1929: 2
  • 1930-1939: 6
  • 1940-1949: 1
  • 1950-1959: 0
  • 1960-1969: 0
  • 1970-1979: 1
  • 1980-1989: 2

Reconstructed bridges - Historical Statistics

  • 1920-1929: 1
  • 1930-1939: 0
  • 1940-1949: 0
  • 1950-1959: 1
  • 1960-1969: 0
  • 1970-1979: 0
  • 1980-1989: 3
  • 1990-1999: 3

Average Daily Traffic

Bridge Condition - Deck

Bridge Condition - Superstructure

Bridge Condition - Substructure

Bridge Condition - Channel

Bridge Condition - Culverts

Find on map >>

Structure Number: C100010CUMHDNBI,  Location: 2.1 MI W OF SAVOY TL (Lat: 42.589167,  Lng: -73.113333),  Route carried "on" structure: State highway 116,  Year Built: 1940,  Year Reconstructed: 1993,  Status: Open,  Structure Length: 1.25m (4.10ft),  Average Daily Traffic: 2,900 (year 2004),  Truck Traffic: 7%,  Average Future Daily Traffic: 4,580 (year 2029),  Design Load: HS 20,  Features Intersected: WATER DRY BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 105.538,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 8.8m (28.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 11.0m (36.1ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 11.7m (38.4ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Very good,  Operating Rating: 44.2 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.30m (4.27ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2008,  Bridge Improvement Cost: $240,000,  Roadway Improvement Cost: $25,000,  Total Project Cost: $361,000 ( Estimate for 2006),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: C1000203GMUNNBI,  Location: SE OF JCT RT116&WELLS RD (Lat: 42.585833,  Lng: -73.110278),  Route carried "on" structure: City street ,  Year Built: 1939,  Status: Posted for load,  Structure Length: 1.46m (4.79ft),  Average Daily Traffic: 100 (year 1997),  Truck Traffic: 6%,  Average Future Daily Traffic: 158 (year 2027),  Design Load: H 15,  Features Intersected: WATER DRY BROOK,  Facility Carried by Structure: HWY SAND MILL RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.009,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Skew: 3 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 12.8m (42.0ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 6.1m (20.0ft),  Out-to-Out Width: 7.0m (23.0ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 37.0 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 21.7 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.50m (4.92ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2006,  Bridge Improvement Cost: $188,000,  Roadway Improvement Cost: $19,000,  Total Project Cost: $283,000 ( Estimate for 2006),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: C1000303HMUNNBI,  Location: S OF JCT RT116&WELLS RD (Lat: 42.583056,  Lng: -73.107222),  Route carried "on" structure: City street ,  Year Built: 1939,  Status: Open,  Structure Length: 1.31m (4.30ft),  Average Daily Traffic: 300 (year 1997),  Truck Traffic: 6%,  Average Future Daily Traffic: 474 (year 2027),  Design Load: H 15,  Features Intersected: WATER DRY BROOK,  Facility Carried by Structure: HWY SAND MILL RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 2.527,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 5.2m (17.1ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 11.6m (38.1ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 6.1m (20.0ft),  Out-to-Out Width: 7.0m (23.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 58.0 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 38.8 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 1.40m (4.59ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2006,  Bridge Improvement Cost: $294,000,  Roadway Improvement Cost: $30,000,  Total Project Cost: $442,000 ( Estimate for 2006),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: C1000400MMUNNBI,  Location: AT JCT OF MAIN ST (Lat: 42.562778,  Lng: -73.151667),  Route carried "on" structure: City street ,  Year Built: 1931,  Status: Open,  Structure Length: 0.85m (2.79ft),  Average Daily Traffic: 1,000 (year 2007),  Truck Traffic: 6%,  Average Future Daily Traffic: 1,579 (year 2028),  Features Intersected: WATER SOUTH BROOK,  Facility Carried by Structure: HWY WELLS RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.016,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.6m (24.9ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 9.0m (29.5ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 58.5 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 36.5 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 0.90m (2.95ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2007,  Bridge Improvement Cost: $166,000,  Roadway Improvement Cost: $17,000,  Total Project Cost: $250,000 ( Estimate for 2006),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: C1000503JMUNNBI,  Location: S OF JCT MAIN ST&WELLS RD (Lat: 42.561111,  Lng: -73.151389),  Route carried "on" structure: City street ,  Year Built: 1939,  Year Reconstructed: 1997,  Status: Open,  Structure Length: 1.25m (4.10ft),  Average Daily Traffic: 500 (year 2007),  Truck Traffic: 6%,  Average Future Daily Traffic: 790 (year 2028),  Design Load: HS 20,  Features Intersected: WATER SOUTH BROOK,  Facility Carried by Structure: HWY E MAIN ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.223,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.0m (23.0ft),  Skew: 3 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 11.3m (37.1ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 1.8m (5.9ft),  Curb-To-Curb Width: 8.1m (26.6ft),  Out-to-Out Width: 11.0m (36.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 72.9 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 35.1 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 1.30m (4.27ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2007,  Bridge Improvement Cost: $162,000,  Roadway Improvement Cost: $17,000,  Total Project Cost: $244,000 ( Estimate for 2006),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Epoxy Overlay,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: C1000600LMUNNBI,  Location: .5 MI E OF RTE 8 (Lat: 42.561944,  Lng: -73.156111),  Route carried "on" structure: City street ,  Year Built: 1938,  Year Reconstructed: 1997,  Status: Open,  Structure Length: 1.32m (4.33ft),  Average Daily Traffic: 900 (year 1997),  Truck Traffic: 6%,  Average Future Daily Traffic: 1,421 (year 2028),  Design Load: HS 20,  Features Intersected: WATER HOOSIC RIVER,  Facility Carried by Structure: HWY CHURCH ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.789,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.0m (23.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 12.1m (39.7ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 0.1m (0.3ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 11.0m (36.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Very good,  Operating Rating: 67.6 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 40.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 1.40m (4.59ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2007,  Bridge Improvement Cost: $222,000,  Roadway Improvement Cost: $23,000,  Total Project Cost: $334,000 ( Estimate for 2006),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: C1000703KMUNNBI,  Location: E OF RT8 NR ADAMS (Lat: 42.593611,  Lng: -73.141389),  Route carried "on" structure: City street ,  Year Built: 1976,  Year Reconstructed: 1994,  Status: Posted for load,  Structure Length: 1.83m (6.00ft),  Average Daily Traffic: 100 (year 2007),  Average Future Daily Traffic: 158 (year 2027),  Features Intersected: WATER HOOSIC RIVER,  Facility Carried by Structure: HWY HARBOR RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.338,  Lanes on structure: 1,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 4.6m (15.1ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 17.3m (56.8ft),  Curb or Sidewalk Widths: Left: 0.9m (3.0ft),  Right: 0.9m (3.0ft),  Curb-To-Curb Width: 3.0m (9.8ft),  Out-to-Out Width: 5.1m (16.7ft)

Condition: Deck: Good,  Superstructure: Poor,  Substructure: Satisfactory,  Channel: Fair,  Operating Rating: 16.1 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 8.7 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: High priority of replacement,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Meets minimum limits,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 2.60m (8.53ft),  Designated Inspection Frequency: Every 12 months,  Critical Feature Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: September 2006,  Critical Feature Inspection Date: September 2006,  Other Special Inspection Date: August 2007,  Bridge Improvement Cost: $434,000,  Roadway Improvement Cost: $44,000,  Total Project Cost: $652,000 ( Estimate for 2006),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>

Structure Number: C100080BNMHDNBI,  Location: 3.1 MI N OF LANSBORO TL (Lat: 42.553611,  Lng: -73.165278),  Route carried "on" structure: State highway 8,  Year Built: 1927,  Year Reconstructed: 1962,  Status: Open,  Structure Length: 1.62m (5.31ft),  Average Daily Traffic: 12,000 (year 2004),  Truck Traffic: 10%,  Average Future Daily Traffic: 18,952 (year 2028),  Features Intersected: WATER HOOSIC RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 81.849,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.6m (38.1ft),  Skew: 2 degrees,  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 13.7m (44.9ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 11.6m (38.1ft),  Out-to-Out Width: 13.1m (43.0ft)

Condition: Deck: Fair,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Very good,  Operating Rating: 56.5 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 30.4 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.70m (5.58ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2007,  Bridge Improvement Cost: $398,000,  Roadway Improvement Cost: $40,000,  Total Project Cost: $598,000 ( Estimate for 2006),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: C100090BPMHDNBI,  Location: 3.5 MI N OF LANSBORO TL (Lat: 42.558889,  Lng: -73.167500),  Route carried "on" structure: State highway 8,  Year Built: 1901,  Year Reconstructed: 1926,  Status: Open,  Structure Length: 0.94m (3.08ft),  Average Daily Traffic: 12,200 (year 2004),  Truck Traffic: 10%,  Average Future Daily Traffic: 19,267 (year 2028),  Features Intersected: WATER KITCHEN BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 82.456,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.8m (42.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.6m (24.9ft),  Curb or Sidewalk Widths: Left: 2.0m (6.6ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 11.2m (36.7ft),  Out-to-Out Width: 14.4m (47.2ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Channel: Fair,  Operating Rating: 54.4 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 22.0 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 1.00m (3.28ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2007,  Bridge Improvement Cost: $258,000,  Roadway Improvement Cost: $26,000,  Total Project Cost: $388,000 ( Estimate for 2006),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: C100100CVMHDNBI,  Location: 2.2 MI W OF SAVOY TL (Lat: 42.590000,  Lng: -73.114167),  Route carried "on" structure: State highway 116,  Year Built: 1929,  Year Reconstructed: 1995,  Status: Open,  Structure Length: 1.83m (6.00ft),  Average Daily Traffic: 2,900 (year 2004),  Truck Traffic: 7%,  Average Future Daily Traffic: 4,580 (year 2029),  Design Load: HS 20,  Features Intersected: WATER DRY BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 105.694,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 16.5m (54.1ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 0.0m,  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 11.6m (38.1ft)

Condition: Deck: Very good,  Superstructure: Good,  Substructure: Good,  Channel: Very good,  Operating Rating: 32.5 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 34.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.90m (6.23ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2008,  Bridge Improvement Cost: $351,000,  Roadway Improvement Cost: $36,000,  Total Project Cost: $527,000 ( Estimate for 2006),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: C1001603LMUNNBI,  Location: S OF WINDSOR RD NR CENTER (Lat: 42.556389,  Lng: -73.144722),  Route carried "on" structure: City street ,  Year Built: 1939,  Year Reconstructed: 1986,  Status: Open,  Structure Length: 1.13m (3.71ft),  Average Daily Traffic: 100 (year 1997),  Truck Traffic: 6%,  Average Future Daily Traffic: 158 (year 2027),  Features Intersected: WATER SOUTH BROOK,  Facility Carried by Structure: HWY NOTCH RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.064,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 6.4m (21.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.7m (31.8ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 6.1m (20.0ft),  Out-to-Out Width: 6.8m (22.3ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 67.1 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 48.5 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.20m (3.94ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2006,  Bridge Improvement Cost: $146,000,  Roadway Improvement Cost: $15,000,  Total Project Cost: $220,000 ( Estimate for 2006),  Deck Structure Type: Open Grating
Find on map >>

Structure Number: C1001853XMUNNBI,  Location: 0.6 KM EAST OF WINDSOR RD (Lat: 42.553611,  Lng: -73.139722),  Route carried "on" structure: City street ,  Year Built: 1982,  Status: Open,  Structure Length: 0.92m (3.02ft),  Average Daily Traffic: 20 (year 2000),  Average Future Daily Traffic: 32 (year 2028),  Design Load: H 20,  Features Intersected: WATER SOUTH BROOK,  Facility Carried by Structure: HWY NOTCH RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 6.0m (19.7ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.3m (14.1ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 44.1 metric tons,  Inventory Rating: 32.4 metric tons,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 0.60m (1.97ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2007,  Bridge Improvement Cost: $168,000,  Roadway Improvement Cost: $17,000,  Total Project Cost: $253,000 ( Estimate for 2006)
Find on map >>

Structure Number: C10023AV3MUNNBI,  Location: EAST OF RICHMONH HILL RD (Lat: 42.560833,  Lng: -73.094167),  Route carried "on" structure: City street ,  Year Built: 1988,  Status: Open,  Structure Length: 0.65m (2.13ft),  Average Daily Traffic: 100 (year 2000),  Truck Traffic: 1%,  Average Future Daily Traffic: 158 (year 2028),  Design Load: H 20,  Features Intersected: WATER DRY BROOK,  Facility Carried by Structure: HWY WINDSOR RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 6.0m (19.7ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.5m (21.3ft)

Condition: Channel: Good,  Culverts: Very good,  Operating Rating: 44.1 metric tons,  Inventory Rating: 32.4 metric tons,  Structural Evaluation: Equal to present desirable criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 0.40m (1.31ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2007,  Bridge Improvement Cost: $108,000,  Roadway Improvement Cost: $11,000,  Total Project Cost: $163,000 ( Estimate for 2006)

Discuss this city on our hugely popular Massachusetts forum

Back to: Cheshire, MA, Massachusetts, All US cities.


City-data.com does not guarantee the accuracy or timeliness of any information on this site.  Use at your own risk.
Some parts © 2009 Advameg, Inc.