National Bridge Inventory (NBI) Statistics
Number of bridges: 19
Total length: 42 meters (138ft)
Total costs: $7,817,000
Total average daily traffic: 9,558
Total average daily truck traffic: 938
Total future (year 2026) average daily traffic: 13,874
National Bridge Inventory (NBI) Registered Bridges for Loachapoka-Roxana

New bridges - Historical Statistics

  • 1940-1949: 2
  • 1950-1959: 7
  • 1960-1969: 6
  • 1970-1979: 3
  • 1980-1989: 1

Bridge Condition - Deck

Bridge Condition - Superstructure

Bridge Condition - Substructure

Bridge Condition - Channel

Bridge Condition - Culverts

Find on map >>

Structure Number: 2382,  Location: 0.2 MI S W LEE RD 57 (Lat: 32.566667,  Lng: -85.550000),  Route carried "on" structure: County highway 1137,  Year Built: 1940,  Status: Open,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 1,300 (year 2006),  Truck Traffic: 11%,  Average Future Daily Traffic: 1,950 (year 2026),  Design Load: H 15,  Features Intersected: CHOCLAFAULA BRANCH,  Facility Carried by Structure: LEE RD 137
Minimum Vertical Clearance: 99.00m (324.80ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.4m (21.0ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 22.7 metric tons,  Inventory Rating: 17.1 metric tons,  Structural Evaluation: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.26m (4.13ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2006,  Bridge Improvement Cost: $122,000,  Roadway Improvement Cost: $12,000,  Total Project Cost: $183,000 ( Estimate for 2008)
Find on map >>

Structure Number: 3094,  Location: 1.2 MI S W BEEHIVE (Lat: 32.533333,  Lng: -85.583333),  Route carried "on" structure: County highway 1137,  Year Built: 1947,  Status: Posted for load,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 1,158 (year 2006),  Truck Traffic: 11%,  Average Future Daily Traffic: 1,736 (year 2026),  Features Intersected: BRANCH,  Facility Carried by Structure: LEE RD 137
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.4m (21.0ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 8.1m (26.6ft)

Condition: Deck: Good,  Superstructure: Fair,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 19.9 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 11.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: High priority of replacement,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 1.26m (4.13ft),  Designated Inspection Frequency: Every 12 months,  Inspection Date: November 2006,  Bridge Improvement Cost: $133,000,  Roadway Improvement Cost: $13,000,  Total Project Cost: $199,000 ( Estimate for 2008),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 3604,  Location: 3.0 MI N MACON CO (Lat: 32.616667,  Lng: -85.683333),  Route carried "on" structure: County highway 1217,  Year Built: 1950,  Status: Open,  Structure Length: 1.46m (4.79ft),  Average Daily Traffic: 102 (year 2006),  Truck Traffic: 1%,  Average Future Daily Traffic: 145 (year 2026),  Features Intersected: ROPES BRANCH,  Facility Carried by Structure: LEE RD 217
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 7.3m (24.0ft),  Curb-To-Curb Width: 3.7m (12.1ft),  Out-to-Out Width: 4.1m (13.5ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 63.9 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 44.0 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 2.12m (6.96ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2006,  Bridge Improvement Cost: $114,000,  Roadway Improvement Cost: $11,000,  Total Project Cost: $171,000 ( Estimate for 2008),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 3728,  Location: 0.7 MI N JCT LEE RD 72 (Lat: 32.683333,  Lng: -85.550000),  Route carried "on" structure: County highway 1086,  Year Built: 1950,  Status: Posted for load,  Structure Length: 1.22m (4.00ft),  Average Daily Traffic: 88 (year 2006),  Average Future Daily Traffic: 126 (year 2026),  Features Intersected: LITTLE LOBLOCKEE CREEK,  Facility Carried by Structure: LEE RD 86
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 12.2m (40.0ft),  Curb-To-Curb Width: 5.3m (17.4ft),  Out-to-Out Width: 5.7m (18.7ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 37.6 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 24.5 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 10.0 - 19.9% below),  Length Of Structure Improvement: 1.88m (6.17ft),  Designated Inspection Frequency: Every 12 months,  Inspection Date: October 2006,  Bridge Improvement Cost: $140,000,  Roadway Improvement Cost: $14,000,  Total Project Cost: $210,000 ( Estimate for 2008),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 3783,  Location: 2.5 MI SE WAVERLY (Lat: 32.700000,  Lng: -85.550000),  Route carried "on" structure: County highway 1088,  Year Built: 1950,  Status: Posted for load,  Structure Length: 1.22m (4.00ft),  Average Daily Traffic: 249 (year 2006),  Truck Traffic: 3%,  Average Future Daily Traffic: 353 (year 2026),  Features Intersected: LOBLOCKEE CREEK,  Facility Carried by Structure: LEE RD 88
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 12.2m (40.0ft),  Curb-To-Curb Width: 7.4m (24.3ft),  Out-to-Out Width: 7.5m (24.6ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 35.2 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 23.0 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 10.0 - 19.9% below),  Length Of Structure Improvement: 1.88m (6.17ft),  Designated Inspection Frequency: Every 12 months,  Inspection Date: October 2006,  Bridge Improvement Cost: $184,000,  Roadway Improvement Cost: $18,000,  Total Project Cost: $276,000 ( Estimate for 2008),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 4031,  Location: 1 MI N OF JAMES (Lat: 32.650000,  Lng: -85.566667),  Route carried "on" structure: County highway 1188,  Year Built: 1951,  Status: Open,  Structure Length: 1.22m (4.00ft),  Average Daily Traffic: 354 (year 2006),  Truck Traffic: 9%,  Average Future Daily Traffic: 531 (year 2026),  Features Intersected: LITTLE LOBLOCKEE,  Facility Carried by Structure: LEE RD 188
Minimum Vertical Clearance: 99.00m (324.80ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 6.1m (20.0ft)

Condition: Channel: Fair,  Culverts: Poor,  Operating Rating: 14.5 metric tons,  Inventory Rating: 10.9 metric tons,  Structural Evaluation: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.88m (6.17ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2006,  Bridge Improvement Cost: $245,000,  Roadway Improvement Cost: $25,000,  Total Project Cost: $368,000 ( Estimate for 2008)
Find on map >>

Structure Number: 5048,  Location: 1.0 MI N W S 267 (Lat: 32.633333,  Lng: -85.500000),  Route carried "on" structure: County highway 1082,  Year Built: 1955,  Status: Posted for load,  Structure Length: 6.16m (20.21ft),  Average Daily Traffic: 1,385 (year 2006),  Truck Traffic: 15%,  Average Future Daily Traffic: 2,009 (year 2026),  Features Intersected: SOUGAHATCHEE CREEK,  Facility Carried by Structure: LEE RD 82
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 12.2m (40.0ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 7.6m (24.9ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 29.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 17.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 20.0 - 29.9% below),  Length Of Structure Improvement: 7.20m (23.62ft),  Designated Inspection Frequency: Every 12 months,  Inspection Date: October 2006,  Bridge Improvement Cost: $712,000,  Roadway Improvement Cost: $71,000,  Total Project Cost: $1,068,000 ( Estimate for 2008),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 5502,  Location: 0.3 MI N ROXANA (Lat: 32.683333,  Lng: -85.666667),  Route carried "on" structure: County highway 1651,  Year Built: 1956,  Status: Posted for load,  Structure Length: 0.61m (2.00ft),  Average Daily Traffic: 245 (year 2006),  Truck Traffic: 3%,  Average Future Daily Traffic: 346 (year 2026),  Features Intersected: WIND CREEK,  Facility Carried by Structure: LEE RD 651
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.1m (20.0ft),  Curb-To-Curb Width: 6.1m (20.0ft),  Out-to-Out Width: 6.1m (20.0ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 42.5 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 30.7 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 0.1 - 9.9% below),  Length Of Structure Improvement: 1.20m (3.94ft),  Designated Inspection Frequency: Every 12 months,  Inspection Date: October 2006,  Bridge Improvement Cost: $96,000,  Roadway Improvement Cost: $10,000,  Total Project Cost: $144,000 ( Estimate for 2008),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 6517,  Location: 1.7 MI N MACON CO (Lat: 32.600000,  Lng: -85.683333),  Route carried "on" structure: County highway 1217,  Year Built: 1959,  Status: Posted for load,  Structure Length: 11.28m (37.01ft),  Average Daily Traffic: 75 (year 2006),  Average Future Daily Traffic: 105 (year 2026),  Features Intersected: ROPES CREEK,  Facility Carried by Structure: LEE RD 217
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 4.9m (16.1ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Number Of Approach Spans: 10,  Length of Maximum Span: 26.2m (86.0ft),  Curb-To-Curb Width: 3.7m (12.1ft),  Out-to-Out Width: 4.4m (14.4ft)

Condition: Deck: Good,  Superstructure: Poor,  Substructure: Poor,  Channel: Satisfactory,  Operating Rating: 18.6 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 13.0 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Meets minimum limits,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 12.16m (39.90ft),  Designated Inspection Frequency: Every 12 months,  Critical Feature Inspection Frequency: Every 12 months,  Inspection Date: October 2006,  Critical Feature Inspection Date: October 2007,  Bridge Improvement Cost: $695,000,  Roadway Improvement Cost: $70,000,  Total Project Cost: $1,043,000 ( Estimate for 2008),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>

Structure Number: 6946,  Location: 0.5 MI S ROWELLS X RD (Lat: 32.666667,  Lng: -85.583333),  Route carried "on" structure: County highway 1188,  Year Built: 1960,  Status: Posted for load,  Structure Length: 1.22m (4.00ft),  Average Daily Traffic: 381 (year 2006),  Truck Traffic: 10%,  Average Future Daily Traffic: 542 (year 2026),  Features Intersected: WEBB CREEK,  Facility Carried by Structure: LEE RD 188
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 12.2m (40.0ft),  Curb-To-Curb Width: 6.6m (21.7ft),  Out-to-Out Width: 7.7m (25.3ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 19.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 11.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 20.0 - 29.9% below),  Length Of Structure Improvement: 1.88m (6.17ft),  Designated Inspection Frequency: Every 12 months,  Inspection Date: October 2006,  Bridge Improvement Cost: $189,000,  Roadway Improvement Cost: $19,000,  Total Project Cost: $284,000 ( Estimate for 2008),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 7069,  Location: 0.8 MI E JCT LEE RD 188 (Lat: 32.566667,  Lng: -85.583333),  Route carried "on" structure: County highway 1393,  Year Built: 1960,  Status: Posted for load,  Structure Length: 2.44m (8.01ft),  Average Daily Traffic: 285 (year 2006),  Truck Traffic: 1%,  Average Future Daily Traffic: 405 (year 2026),  Features Intersected: MILES CREEK,  Facility Carried by Structure: LEE RD 393
Minimum Vertical Clearance: 99.00m (324.80ft),  Kilometerpoint: 0.010,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 5.2m (17.1ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 24.4m (80.1ft),  Curb-To-Curb Width: 3.7m (12.1ft),  Out-to-Out Width: 4.2m (13.8ft)

Condition: Deck: Satisfactory,  Superstructure: Poor,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 5.4 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 3.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: High priority of replacement,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 3.31m (10.86ft),  Designated Inspection Frequency: Every 12 months,  Critical Feature Inspection Frequency: Every 12 months,  Inspection Date: October 2006,  Critical Feature Inspection Date: October 2007,  Bridge Improvement Cost: $181,000,  Roadway Improvement Cost: $18,000,  Total Project Cost: $271,000 ( Estimate for 2008),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 8227,  Location: 2.2 MI S ROXANA (Lat: 32.650000,  Lng: -85.650000),  Route carried "on" structure: County highway 1066,  Year Built: 1964,  Status: Posted for load,  Structure Length: 0.61m (2.00ft),  Average Daily Traffic: 102 (year 2006),  Truck Traffic: 1%,  Average Future Daily Traffic: 145 (year 2026),  Features Intersected: ROPES CREEK,  Facility Carried by Structure: LEE RD 66
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.1m (20.0ft),  Curb-To-Curb Width: 5.5m (18.0ft),  Out-to-Out Width: 6.2m (20.3ft)

Condition: Deck: Good,  Superstructure: Fair,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 42.7 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 29.0 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 0.1 - 9.9% below),  Length Of Structure Improvement: 1.20m (3.94ft),  Designated Inspection Frequency: Every 12 months,  Inspection Date: October 2006,  Bridge Improvement Cost: $97,000,  Roadway Improvement Cost: $10,000,  Total Project Cost: $146,000 ( Estimate for 2008),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 939,  Location: 0.5 MI W JCT LEE RD 188 (Lat: 32.683333,  Lng: -85.583333),  Route carried "on" structure: County highway 1072,  Year Built: 1967,  Status: Open,  Structure Length: 1.74m (5.71ft),  Average Daily Traffic: 1,496 (year 2006),  Truck Traffic: 11%,  Average Future Daily Traffic: 2,127 (year 2026),  Design Load: H 15,  Features Intersected: WEBB CREEK,  Facility Carried by Structure: LEE RD 72
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 5.8m (19.0ft),  Curb-To-Curb Width: 6.6m (21.7ft),  Out-to-Out Width: 7.7m (25.3ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 46.3 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 30.0 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Meets minimum limits,  Length Of Structure Improvement: 2.44m (8.01ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2006,  Bridge Improvement Cost: $245,000,  Roadway Improvement Cost: $25,000,  Total Project Cost: $368,000 ( Estimate for 2008),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 9397,  Location: 0.2 MI W JCT LEE RD 137 (Lat: 32.566667,  Lng: -85.566667),  Route carried "on" structure: County highway 1058,  Year Built: 1967,  Status: Open,  Structure Length: 0.61m (2.00ft),  Average Daily Traffic: 180 (year 2006),  Truck Traffic: 1%,  Average Future Daily Traffic: 255 (year 2026),  Features Intersected: CHOCLAFAULA CREEK,  Facility Carried by Structure: LEE RD 58
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Masonry,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 14.5 metric tons,  Inventory Rating: 10.9 metric tons,  Structural Evaluation: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.20m (3.94ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2006,  Bridge Improvement Cost: $147,000,  Roadway Improvement Cost: $15,000,  Total Project Cost: $221,000 ( Estimate for 2008)
Find on map >>

Structure Number: 9566,  Location: 1.1 MI N RIDGE GROVE (Lat: 32.666667,  Lng: -85.516667),  Route carried "on" structure: County highway 1085,  Year Built: 1968,  Status: Open,  Structure Length: 0.61m (2.00ft),  Average Daily Traffic: 109 (year 2006),  Truck Traffic: 1%,  Average Future Daily Traffic: 155 (year 2026),  Features Intersected: BRANCH,  Facility Carried by Structure: LEE CO 85
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.4m (21.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.1m (20.0ft),  Curb-To-Curb Width: 5.5m (18.0ft),  Out-to-Out Width: 6.5m (21.3ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 79.0 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 55.4 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.20m (3.94ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2006,  Bridge Improvement Cost: $102,000,  Roadway Improvement Cost: $10,000,  Total Project Cost: $153,000 ( Estimate for 2008),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 10292,  Location: MACONS MILL (Lat: 32.650000,  Lng: -85.566667),  Route carried "on" structure: County highway 1188,  Year Built: 1970,  Status: Open,  Structure Length: 8.02m (26.31ft),  Average Daily Traffic: 381 (year 2006),  Truck Traffic: 10%,  Average Future Daily Traffic: 572 (year 2026),  Design Load: HS 20,  Features Intersected: LOBLOCKEE CREEK,  Facility Carried by Structure: LEE RD 188
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 30.5m (100.1ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 10.1m (33.1ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 60.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 36.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 9.02m (29.59ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2006,  Bridge Improvement Cost: $1,185,000,  Roadway Improvement Cost: $119,000,  Total Project Cost: $1,778,000 ( Estimate for 2008),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 10727,  Location: 2.0 MI S JCT LEE RD 72 (Lat: 32.666667,  Lng: -85.616667),  Route carried "on" structure: County highway 1070,  Year Built: 1972,  Status: Posted for load,  Structure Length: 0.73m (2.40ft),  Average Daily Traffic: 17 (year 2006),  Average Future Daily Traffic: 25 (year 2026),  Features Intersected: BIRD CREEK,  Facility Carried by Structure: LEE RD 70
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 6.4m (21.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.3m (24.0ft),  Curb-To-Curb Width: 4.5m (14.8ft),  Out-to-Out Width: 4.9m (16.1ft)

Condition: Deck: Poor,  Superstructure: Fair,  Substructure: Poor,  Channel: Satisfactory,  Operating Rating: 5.4 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 3.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: High priority of replacement,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Meets minimum limits,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 1.37m (4.49ft),  Designated Inspection Frequency: Every 12 months,  Inspection Date: October 2006,  Bridge Improvement Cost: $88,000,  Roadway Improvement Cost: $9,000,  Total Project Cost: $132,000 ( Estimate for 2008),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>

Structure Number: 11224,  Location: 0.2 MI E JCT LEE RD 188 (Lat: 32.650000,  Lng: -85.566667),  Route carried "on" structure: County highway 1080,  Year Built: 1974,  Status: Open,  Structure Length: 0.61m (2.00ft),  Average Daily Traffic: 155 (year 2006),  Truck Traffic: 4%,  Average Future Daily Traffic: 220 (year 2026),  Design Load: H 15,  Features Intersected: BRANCH,  Facility Carried by Structure: LEE RD 84
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.1m (20.0ft),  Curb-To-Curb Width: 7.4m (24.3ft),  Out-to-Out Width: 7.9m (25.9ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 49.3 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 34.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Meets minimum limits,  Length Of Structure Improvement: 1.20m (3.94ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2006,  Bridge Improvement Cost: $124,000,  Roadway Improvement Cost: $12,000,  Total Project Cost: $186,000 ( Estimate for 2008),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 14246,  Location: 0.5 MI E ROWELLS X RD (Lat: 32.683333,  Lng: -85.566667),  Route carried "on" structure: County highway 1072,  Year Built: 1987,  Status: Open,  Structure Length: 1.83m (6.00ft),  Average Daily Traffic: 1,496 (year 2006),  Truck Traffic: 11%,  Average Future Daily Traffic: 2,127 (year 2026),  Design Load: HS 20,  Features Intersected: LOBLOCKEE CREEK,  Facility Carried by Structure: LEE RD 72
Minimum Vertical Clearance: 99.00m (324.80ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 4.3m (14.1ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 43.5 metric tons,  Inventory Rating: 32.7 metric tons,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.53m (8.30ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2006,  Bridge Improvement Cost: $411,000,  Roadway Improvement Cost: $41,000,  Total Project Cost: $616,000 ( Estimate for 2008)

Discuss this city on our hugely popular Alabama forum

Back to: Loachapoka-Roxana, AL, Alabama, All US cities.


City-data.com does not guarantee the accuracy or timeliness of any information on this site.  Use at your own risk.
Some parts © 2009 Advameg, Inc.