National Bridge Inventory (NBI) Statistics
Number of bridges: 88
Total length: 345 meters (1,132ft)
Total costs: $113,837,000
Total average daily traffic: 2,038,552
Total average daily truck traffic: 126,393
National Bridge Inventory (NBI) Registered Bridges for Mount Pleasant

New bridges - Historical Statistics

  • 1920-1929: 5
  • 1930-1939: 24
  • 1940-1949: 1
  • 1950-1959: 3
  • 1960-1969: 4
  • 1970-1979: 36
  • 1980-1989: 4
  • 1990-1999: 9
  • 2000-2009: 2

Reconstructed bridges - Historical Statistics

  • 1960-1969: 2
  • 1970-1979: 1
  • 1980-1989: 2
  • 1990-1999: 4

Average Daily Traffic

Average Truck Traffic (%)

Bridge Condition - Deck

Bridge Condition - Superstructure

Bridge Condition - Substructure

Bridge Condition - Channel

Bridge Condition - Culverts

Find on map >>

Structure Number: 1006129,  Location: JCT RTS 9A + 100 + 41 (Lat: 41.107303,  Lng: -73.806744),  Route carried "on" structure: State highway 9A,  Year Built: 1972,  Status: Open,  Structure Length: 1.61m (5.28ft),  Average Daily Traffic: 29,276 (year 2005),  Truck Traffic: 6%,  Average Future Daily Traffic: 40,986 (year 2025),  Design Load: HS 20,  Features Intersected: SAW MILL RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 16.404,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 16.4m (53.8ft),  Skew: 23 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 6.0m (19.7ft),  Curb-To-Curb Width: 42.6m (139.8ft),  Out-to-Out Width: 50.9m (167.0ft)

Condition: Channel: Fair,  Culverts: Fair,  Operating Rating: 76.4 metric tons,  Inventory Rating: 29.3 metric tons,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.61m (5.28ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2006,  Bridge Improvement Cost: $1,814,000,  Roadway Improvement Cost: $1,080,000,  Total Project Cost: $2,894,000 ( Estimate for 2007),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 100614,  Location: JCT RTS 117+9A+TSP (Lat: 41.123672,  Lng: -73.809569),  Route carried "on" structure: State highway 117,  Year Built: 1936,  Year Reconstructed: 1995,  Status: Open,  Structure Length: 2.59m (8.50ft),  Average Daily Traffic: 18,782 (year 2006),  Truck Traffic: 6%,  Average Future Daily Traffic: 26,295 (year 2026),  Design Load: HS 25,  Features Intersected: RTE 9A, RTE 987G
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.846,  Lanes on structure: 5,  Lanes under structure: 5,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 23.1m (75.8ft),  Material/Design: Concrete continuous,  Design/Construction: Frame,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 14.3m (46.9ft),  Curb or Sidewalk Widths: Left: 3.0m (9.8ft),  Right: 6.0m (19.7ft),  Curb-To-Curb Width: 19.6m (64.3ft),  Out-to-Out Width: 30.2m (99.1ft)

Condition: Superstructure: Good,  Substructure: Good,  Operating Rating: 53.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.59m (8.50ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2006,  Bridge Improvement Cost: $1,727,000,  Roadway Improvement Cost: $1,028,000,  Total Project Cost: $2,755,000 ( Estimate for 2007),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 100615,  Location: 0.8 MI N JCT RTS 9A+117 (Lat: 41.133356,  Lng: -73.818150),  Route carried "on" structure: State highway 9A,  Year Built: 1929,  Year Reconstructed: 1975,  Status: Open,  Structure Length: 0.79m (2.59ft),  Average Daily Traffic: 36,700 (year 2005),  Truck Traffic: 6%,  Average Future Daily Traffic: 51,380 (year 2025),  Design Load: HS 20,  Features Intersected: POCANTICO RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 19.466,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 15.5m (50.9ft),  Skew: 21 degrees,  Material/Design: Concrete,  Design/Construction: Arch - Deck,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.0m (19.7ft),  Curb-To-Curb Width: 15.6m (51.2ft),  Out-to-Out Width: 17.8m (58.4ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Channel: Fair,  Operating Rating: 76.4 metric tons,  Inventory Rating: 29.3 metric tons,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Meets minimum limits,  Length Of Structure Improvement: 0.79m (2.59ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2006,  Bridge Improvement Cost: $313,000,  Roadway Improvement Cost: $186,000,  Total Project Cost: $499,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 100617,  Location: 1.9 MI N JCT RTS 9A+117 (Lat: 41.148117,  Lng: -73.824167),  Route carried "on" structure: State highway 9A,  Year Built: 1928,  Status: Open,  Structure Length: 1.18m (3.87ft),  Average Daily Traffic: 40,707 (year 1999),  Truck Traffic: 6%,  Average Future Daily Traffic: 56,990 (year 2019),  Design Load: HS 20,  Features Intersected: POCANTICO RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 21.234,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 15.8m (51.8ft),  Skew: 20 degrees,  Material/Design: Concrete,  Design/Construction: Arch - Deck,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.0m (19.7ft),  Curb or Sidewalk Widths: Left: 0.0m,  Right: 1.2m (3.9ft),  Curb-To-Curb Width: 14.4m (47.2ft),  Out-to-Out Width: 17.6m (57.7ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 76.9 metric tons,  Inventory Rating: 32.6 metric tons,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.18m (3.87ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2006,  Bridge Improvement Cost: $564,000,  Roadway Improvement Cost: $336,000,  Total Project Cost: $900,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>

Structure Number: 100618,  Location: 2.1 MI N JCT RTS 9A+117 (Lat: 41.150092,  Lng: -73.826311),  Route carried "on" structure: State highway 9A,  Year Built: 1931,  Year Reconstructed: 1974,  Status: Open,  Structure Length: 0.85m (2.79ft),  Average Daily Traffic: 33,834 (year 1999),  Truck Traffic: 6%,  Average Future Daily Traffic: 47,368 (year 2019),  Design Load: HS 20,  Features Intersected: POCANTICO RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 21.396,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 16.1m (52.8ft),  Skew: 21 degrees,  Material/Design: Concrete,  Design/Construction: Arch - Deck,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.0m (23.0ft),  Curb-To-Curb Width: 21.7m (71.2ft),  Out-to-Out Width: 24.8m (81.4ft)

Condition: Superstructure: Fair,  Substructure: Satisfactory,  Channel: Fair,  Operating Rating: 77.5 metric tons,  Inventory Rating: 32.6 metric tons,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Meets minimum limits,  Length Of Structure Improvement: 0.85m (2.79ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2006,  Bridge Improvement Cost: $468,000,  Roadway Improvement Cost: $278,000,  Total Project Cost: $746,000 ( Estimate for 2007),  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>

Structure Number: 103714,  Location: 1.1 MI E JCT SH 448 & US9 (Lat: 41.094886,  Lng: -73.842417),  Route carried "on" structure: State highway 448,  Year Built: 1931,  Status: Open,  Structure Length: 2.71m (8.89ft),  Average Daily Traffic: 4,091 (year 2005),  Truck Traffic: 6%,  Average Future Daily Traffic: 5,727 (year 2025),  Design Load: H 20,  Features Intersected: UNNAMED ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.773,  Lanes on structure: 2,  Lanes under structure: 1,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Concrete,  Design/Construction: Arch - Deck,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.4m (30.8ft),  Curb or Sidewalk Widths: Left: 2.1m (6.9ft),  Right: 2.1m (6.9ft),  Curb-To-Curb Width: 12.1m (39.7ft),  Out-to-Out Width: 13.4m (44.0ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Operating Rating: 65.8 metric tons,  Inventory Rating: 28.1 metric tons,  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Meets minimum limits,  Length Of Structure Improvement: 2.71m (8.89ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2006,  Bridge Improvement Cost: $647,000,  Roadway Improvement Cost: $385,000,  Total Project Cost: $1,032,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 103715,  Location: 2.9 MI E JCT US 9 & SH448 (Lat: 41.109281,  Lng: -73.820192),  Route carried "on" structure: State highway 448,  Year Built: 1931,  Status: Open,  Structure Length: 3.87m (12.70ft),  Average Daily Traffic: 4,091 (year 2005),  Truck Traffic: 6%,  Average Future Daily Traffic: 5,727 (year 2025),  Design Load: H 20,  Features Intersected: UNNAMED ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.679,  Lanes on structure: 2,  Lanes under structure: 1,  Base Highway Network: Yes,  Owner: State Highway Agency,  Maintenance Responsibility: Private,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Concrete,  Design/Construction: Arch - Deck,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.4m (30.8ft),  Curb or Sidewalk Widths: Left: 1.8m (5.9ft),  Right: 1.7m (5.6ft),  Curb-To-Curb Width: 12.1m (39.7ft),  Out-to-Out Width: 17.2m (56.4ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Satisfactory,  Operating Rating: 65.8 metric tons,  Inventory Rating: 28.1 metric tons,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Meets minimum limits,  Length Of Structure Improvement: 3.87m (12.70ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2006,  Bridge Improvement Cost: $1,471,000,  Roadway Improvement Cost: $875,000,  Total Project Cost: $2,346,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 103716,  Location: JCT RTS 117+9A (Lat: 41.123653,  Lng: -73.810367),  Route carried "on" structure: State highway 117,  Year Built: 1931,  Year Reconstructed: 1995,  Status: Open,  Structure Length: 1.46m (4.79ft),  Average Daily Traffic: 18,782 (year 2006),  Truck Traffic: 6%,  Average Future Daily Traffic: 26,295 (year 2026),  Design Load: HS 25,  Features Intersected: RTE 9A
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.853,  Lanes on structure: 6,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 23.1m (75.8ft),  Skew: 1 degrees,  Material/Design: Concrete,  Design/Construction: Frame,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 12.1m (39.7ft),  Curb or Sidewalk Widths: Left: 3.0m (9.8ft),  Right: 2.5m (8.2ft),  Curb-To-Curb Width: 23.2m (76.1ft),  Out-to-Out Width: 30.2m (99.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 76.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 45.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.46m (4.79ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2006,  Bridge Improvement Cost: $975,000,  Roadway Improvement Cost: $580,000,  Total Project Cost: $1,555,000 ( Estimate for 2007),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 103799,  Location: JCT TSP & RTE 141 (Lat: 41.107239,  Lng: -73.800647),  Route carried "on" structure: Ramp Other road ,  Year Built: 1951,  Status: Open,  Structure Length: 2.01m (6.59ft),  Average Daily Traffic: 64,776 (year 1997),  Truck Traffic: 6%,  Average Future Daily Traffic: 94,035 (year 2017),  Design Load: HS 20,  Features Intersected: RTE 141,  Facility Carried by Structure: RAMP TO TSP SB
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Skew: 2 degrees,  Material/Design: Concrete,  Design/Construction: Frame,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 18.2m (59.7ft),  Curb or Sidewalk Widths: Left: 2.4m (7.9ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 14.0m (45.9ft)

Condition: Superstructure: Good,  Substructure: Good,  Operating Rating: 85.6 metric tons,  Inventory Rating: 32.6 metric tons,  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of replacement,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Meets minimum limits,  Length Of Structure Improvement: 2.01m (6.59ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2006,  Bridge Improvement Cost: $622,000,  Roadway Improvement Cost: $370,000,  Total Project Cost: $992,000 ( Estimate for 2007),  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 105333,  Location: 2.5 MI S JCT RTE 100+TSP (Lat: 41.148342,  Lng: -73.825139),  Route carried "on" structure: State highway 100,  Year Built: 1967,  Status: Open,  Structure Length: 1.06m (3.48ft),  Average Daily Traffic: 41,446 (year 2002),  Truck Traffic: 6%,  Average Future Daily Traffic: 58,024 (year 2022),  Design Load: H 20,  Features Intersected: POCANTICO RIVER U
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 15.377,  Lanes on structure: 1,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 10.9m (35.8ft),  Skew: 2 degrees,  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 5.1m (16.7ft),  Curb-To-Curb Width: 13.4m (44.0ft),  Out-to-Out Width: 14.4m (47.2ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 73.5 metric tons,  Inventory Rating: 32.6 metric tons,  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.06m (3.48ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2006,  Bridge Improvement Cost: $341,000,  Roadway Improvement Cost: $203,000,  Total Project Cost: $544,000 ( Estimate for 2007),  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>

Structure Number: 105336,  Location: .5 MI S JCT SH 100 & TSP (Lat: 41.177694,  Lng: -73.811692),  Route carried "on" structure: State highway 100,  Year Built: 1967,  Status: Open,  Structure Length: 0.85m (2.79ft),  Average Daily Traffic: 19,873 (year 2005),  Truck Traffic: 6%,  Average Future Daily Traffic: 27,822 (year 2025),  Design Load: H 20,  Features Intersected: POCANTICO RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 19.627,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 20.4m (66.9ft),  Skew: 26 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.5m (27.9ft),  Out-to-Out Width: 62.1m (203.7ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 68.1 metric tons,  Inventory Rating: 29.3 metric tons,  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.85m (2.79ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2006,  Bridge Improvement Cost: $1,171,000,  Roadway Improvement Cost: $697,000,  Total Project Cost: $1,868,000 ( Estimate for 2007),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 105444,  Location: 2.7 MI S JCT RTE 100+TSP (Lat: 41.149744,  Lng: -73.825592),  Route carried "on" structure: State highway 9A,  Year Built: 1931,  Year Reconstructed: 1968,  Status: Open,  Structure Length: 2.86m (9.38ft),  Average Daily Traffic: 33,834 (year 1999),  Truck Traffic: 6%,  Average Future Daily Traffic: 47,368 (year 2019),  Design Load: H 20,  Features Intersected: RTE 100
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 21.385,  Lanes on structure: 4,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 16.7m (54.8ft),  Skew: 24 degrees,  Material/Design: Concrete,  Design/Construction: Frame,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 22.8m (74.8ft),  Curb-To-Curb Width: 13.2m (43.3ft),  Out-to-Out Width: 14.5m (47.6ft)

Condition: Superstructure: Poor,  Substructure: Good,  Operating Rating: 57.8 metric tons,  Inventory Rating: 14.3 metric tons,  Structural Evaluation: High priority of replacement,  Deck Geometry: High priority of replacement,  Underclear: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.86m (9.38ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2006,  Bridge Improvement Cost: $2,259,000,  Roadway Improvement Cost: $1,523,000,  Total Project Cost: $3,782,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>

Structure Number: 107045,  Location: 1.5 MI N INT 287I & SBSP (Lat: 41.073633,  Lng: -73.801700),  Route carried "on" structure: State highway 100C,  Year Built: 1981,  Status: Open,  Structure Length: 7.49m (24.57ft),  Average Daily Traffic: 15,947 (year 2002),  Truck Traffic: 6%,  Average Future Daily Traffic: 20,749 (year 2022),  Design Load: HS 20,  Features Intersected: RTE 987F
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 162.670,  Lanes on structure: 6,  Lanes under structure: 7,  Owner: State Highway Agency,  Approaching Roadway Width: 25.6m (84.0ft),  Skew: 31 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 39.3m (128.9ft),  Curb or Sidewalk Widths: Left: 0.1m (0.3ft),  Right: 0.1m (0.3ft),  Curb-To-Curb Width: 24.6m (80.7ft),  Out-to-Out Width: 26.2m (86.0ft)

Condition: Deck: Poor,  Superstructure: Good,  Substructure: Fair,  Operating Rating: 90.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 54.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 7.49m (24.57ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2006,  Bridge Improvement Cost: $4,231,000,  Roadway Improvement Cost: $2,455,000,  Total Project Cost: $6,686,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 10705,  Location: JCT CR 301 & SH 100 (Lat: 41.090181,  Lng: -73.803422),  Route carried "on" structure: County highway ,  Year Built: 1981,  Status: Open,  Structure Length: 6.58m (21.59ft),  Average Daily Traffic: 7,021 (year 1997),  Truck Traffic: 6%,  Average Future Daily Traffic: 9,829 (year 2017),  Design Load: HS 20,  Features Intersected: 987F,  Facility Carried by Structure: HOSPITAL RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 6,  Owner: State Highway Agency,  Approaching Roadway Width: 10.9m (35.8ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 36.5m (119.8ft),  Curb-To-Curb Width: 13.1m (43.0ft),  Out-to-Out Width: 14.0m (45.9ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Satisfactory,  Inventory Rating: 62.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.58m (21.59ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2007,  Bridge Improvement Cost: $2,037,000,  Roadway Improvement Cost: $1,182,000,  Total Project Cost: $3,219,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete
Find on map >>

Structure Number: 107475,  Location: 1.8 MI S JCT RT 133 &TSP (Lat: 41.157756,  Lng: -73.818425),  Route carried "on" structure: State highway 987G,  Year Built: 1994,  Status: Open,  Structure Length: 3.04m (9.97ft),  Average Daily Traffic: 43,232 (year 1989),  Truck Traffic: 6%,  Average Future Daily Traffic: 62,760 (year 2009),  Design Load: HS 20,  Features Intersected: CHAPPAQUA RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 6,  Lanes under structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 31.3m (102.7ft),  Skew: 22 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 29.2m (95.8ft),  Curb-To-Curb Width: 30.3m (99.4ft),  Out-to-Out Width: 32.0m (105.0ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Operating Rating: 66.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 37.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Superior to present desirable criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.04m (9.97ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2006,  Bridge Improvement Cost: $207,000,  Roadway Improvement Cost: $123,000,  Total Project Cost: $330,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Structure Number: 107734,  Location: .57 MI N JCT TSP & Rt 117,  Route carried "on" structure: Ramp State highway ,  Year Built: 2007,  Status: Open,  Structure Length: 5.32m (17.45ft),  Truck Traffic: 6%,  Design Load: HS 25,  Features Intersected: 9A + 100,  Facility Carried by Structure: 9A 9A87488A01
Minimum Vertical Clearance: 99.00m (324.80ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Lanes under structure: 4,  Owner: State Highway Agency,  Approaching Roadway Width: 8.0m (26.2ft),  Skew: 4 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 51.0m (167.3ft),  Curb-To-Curb Width: 8.0m (26.2ft),  Out-to-Out Width: 9.1m (29.9ft)

Condition: Deck: Excellent,  Superstructure: Excellent,  Substructure: Very good,  Inventory Rating: 41.7 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: High priority of corrective action,  Underclear: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 5.32m (17.45ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2007,  Bridge Improvement Cost: $207,000,  Roadway Improvement Cost: $123,000,  Total Project Cost: $330,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 1091031,  Location: JCT SH 9A & SH100 & SH141 (Lat: 41.106594,  Lng: -73.807008),  Route carried "on" structure: State highway 9A,  Year Built: 1972,  Status: Open,  Structure Length: 4.96m (16.27ft),  Average Daily Traffic: 10,188 (year 2005),  Truck Traffic: 6%,  Average Future Daily Traffic: 14,263 (year 2025),  Design Load: HS 20,  Features Intersected: SH100 & 141 RAMPS
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 16.066,  Lanes on structure: 3,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 14.0m (45.9ft),  Skew: 2 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 19.2m (63.0ft),  Curb-To-Curb Width: 12.3m (40.4ft),  Out-to-Out Width: 13.5m (44.3ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 85.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 50.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.96m (16.27ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2007,  Bridge Improvement Cost: $886,000,  Roadway Improvement Cost: $528,000,  Total Project Cost: $1,414,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 1091032,  Location: JCT SH 9A & SH100 & SH141 (Lat: 41.106594,  Lng: -73.807008),  Route carried "on" structure: State highway 9A,  Year Built: 1972,  Status: Open,  Structure Length: 4.96m (16.27ft),  Average Daily Traffic: 10,188 (year 2005),  Truck Traffic: 6%,  Average Future Daily Traffic: 14,263 (year 2025),  Design Load: HS 20,  Features Intersected: RAMP
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 16.066,  Lanes on structure: 2,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 10.3m (33.8ft),  Skew: 2 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 19.2m (63.0ft),  Curb-To-Curb Width: 9.0m (29.5ft),  Out-to-Out Width: 10.1m (33.1ft)

Condition: Deck: Very good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 92.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 55.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of corrective action,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.96m (16.27ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2007,  Bridge Improvement Cost: $886,000,  Roadway Improvement Cost: $528,000,  Total Project Cost: $1,414,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 1091051,  Location: .4 MI E JCT SH 117 & US 9 (Lat: 41.107911,  Lng: -73.850667),  Route carried "on" structure: State highway 117,  Year Built: 1970,  Status: Open,  Structure Length: 1.67m (5.48ft),  Average Daily Traffic: 5,522 (year 2006),  Truck Traffic: 6%,  Average Future Daily Traffic: 7,731 (year 2026),  Features Intersected: BRIDLE PATH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.649,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 10.3m (33.8ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 15.2m (49.9ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 11.9m (39.0ft),  Out-to-Out Width: 13.1m (43.0ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Good,  Operating Rating: 54.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.67m (5.48ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2006,  Bridge Improvement Cost: $886,000,  Roadway Improvement Cost: $528,000,  Total Project Cost: $1,414,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 1091052,  Location: .4 MI E JCT SH 117 & US 9 (Lat: 41.107911,  Lng: -73.850667),  Route carried "on" structure: State highway 117,  Year Built: 1970,  Status: Open,  Structure Length: 1.67m (5.48ft),  Average Daily Traffic: 5,522 (year 2006),  Truck Traffic: 6%,  Average Future Daily Traffic: 7,731 (year 2026),  Features Intersected: BRIDLE PATH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.649,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 10.3m (33.8ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 15.2m (49.9ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 11.9m (39.0ft),  Out-to-Out Width: 13.1m (43.0ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Good,  Operating Rating: 54.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.67m (5.48ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2006,  Bridge Improvement Cost: $886,000,  Roadway Improvement Cost: $528,000,  Total Project Cost: $1,414,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 1091071,  Location: 0.7 MI E JCT RTS 117+9 (Lat: 41.108303,  Lng: -73.844814),  Route carried "on" structure: State highway 117,  Year Built: 1970,  Status: Open,  Structure Length: 6.15m (20.18ft),  Average Daily Traffic: 5,522 (year 2006),  Truck Traffic: 6%,  Average Future Daily Traffic: 7,731 (year 2026),  Features Intersected: SLEEPY HOLLOW RD, POCANT
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.627,  Lanes on structure: 2,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 10.6m (34.8ft),  Skew: 4 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 29.8m (97.8ft),  Curb or Sidewalk Widths: Left: 0.1m (0.3ft),  Right: 0.1m (0.3ft),  Curb-To-Curb Width: 11.9m (39.0ft),  Out-to-Out Width: 13.1m (43.0ft)

Condition: Deck: Good,  Superstructure: Fair,  Substructure: Good,  Channel: Good,  Operating Rating: 69.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 38.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Better than present minimum criteria,  Underclear: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.15m (20.18ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2006,  Bridge Improvement Cost: $1,781,000,  Roadway Improvement Cost: $1,060,000,  Total Project Cost: $2,841,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 1091072,  Location: 0.7 MI E JCT RTS 117+9 (Lat: 41.108350,  Lng: -73.844825),  Route carried "on" structure: State highway 117,  Year Built: 1970,  Year Reconstructed: 1980,  Status: Open,  Structure Length: 6.15m (20.18ft),  Average Daily Traffic: 5,522 (year 2006),  Truck Traffic: 6%,  Average Future Daily Traffic: 7,731 (year 2026),  Features Intersected: SLEEPY HOLLOW RD, POCANT
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.627,  Lanes on structure: 2,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 10.6m (34.8ft),  Skew: 4 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 29.8m (97.8ft),  Curb or Sidewalk Widths: Left: 0.1m (0.3ft),  Right: 0.1m (0.3ft),  Curb-To-Curb Width: 11.9m (39.0ft),  Out-to-Out Width: 13.1m (43.0ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Good,  Operating Rating: 66.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Underclear: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.15m (20.18ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2006,  Bridge Improvement Cost: $1,781,000,  Roadway Improvement Cost: $1,060,000,  Total Project Cost: $2,841,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 1091081,  Location: 2.7 MI E JCT RTS 117+9 (Lat: 41.121231,  Lng: -73.822514),  Route carried "on" structure: State highway 117,  Year Built: 1970,  Status: Open,  Structure Length: 2.95m (9.68ft),  Average Daily Traffic: 5,522 (year 2006),  Truck Traffic: 6%,  Average Future Daily Traffic: 7,731 (year 2026),  Features Intersected: OLD SLEEPY HOLLOW
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.201,  Lanes on structure: 2,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.8m (42.0ft),  Skew: 5 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 28.0m (91.9ft),  Curb-To-Curb Width: 12.4m (40.7ft),  Out-to-Out Width: 13.4m (44.0ft)

Condition: Deck: Satisfactory,  Superstructure: Very good,  Substructure: Good,  Inventory Rating: 68.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.95m (9.68ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2006,  Bridge Improvement Cost: $1,781,000,  Roadway Improvement Cost: $1,060,000,  Total Project Cost: $2,841,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete
Find on map >>

Structure Number: 1091082,  Location: 2.7 MI E JCT SH117 & US 9 (Lat: 41.121231,  Lng: -73.822514),  Route carried "on" structure: State highway 117,  Year Built: 1970,  Year Reconstructed: 1980,  Status: Open,  Structure Length: 2.98m (9.78ft),  Average Daily Traffic: 5,522 (year 2006),  Truck Traffic: 6%,  Average Future Daily Traffic: 7,731 (year 2026),  Features Intersected: OLD SLEEPY HOLLOW
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.201,  Lanes on structure: 2,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.8m (42.0ft),  Skew: 5 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 28.3m (92.8ft),  Curb-To-Curb Width: 12.4m (40.7ft),  Out-to-Out Width: 13.4m (44.0ft)

Condition: Deck: Satisfactory,  Superstructure: Very good,  Substructure: Fair,  Inventory Rating: 69.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Better than present minimum criteria,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.98m (9.78ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2006,  Bridge Improvement Cost: $884,000,  Roadway Improvement Cost: $526,000,  Total Project Cost: $1,410,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete
Find on map >>

Structure Number: 109111,  Location: JCT RTE 100+SBP (Lat: 41.095158,  Lng: -73.802286),  Route carried "on" structure: State highway 100,  Year Built: 1972,  Status: Open,  Structure Length: 7.01m (23.00ft),  Average Daily Traffic: 10,101 (year 2005),  Truck Traffic: 6%,  Average Future Daily Traffic: 14,141 (year 2025),  Design Load: HS 20,  Features Intersected: RTE 987F
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 8.943,  Lanes on structure: 4,  Lanes under structure: 7,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 15.8m (51.8ft),  Skew: 5 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 35.0m (114.8ft),  Curb or Sidewalk Widths: Left: 1.0m (3.3ft),  Right: 1.0m (3.3ft),  Curb-To-Curb Width: 15.8m (51.8ft),  Out-to-Out Width: 18.5m (60.7ft)

Condition: Deck: Good,  Superstructure: Poor,  Substructure: Satisfactory,  Operating Rating: 90.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 54.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Meets minimum limits,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Meets minimum limits,  Length Of Structure Improvement: 7.01m (23.00ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2007,  Bridge Improvement Cost: $2,867,000,  Roadway Improvement Cost: $1,664,000,  Total Project Cost: $4,531,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 1091331,  Location: JCT S H 117 & U S 9 (Lat: 41.110267,  Lng: -73.858344),  Route carried "on" structure: State highway 117,  Year Built: 1970,  Status: Open,  Structure Length: 3.13m (10.27ft),  Average Daily Traffic: 5,522 (year 2006),  Truck Traffic: 6%,  Average Future Daily Traffic: 7,731 (year 2026),  Features Intersected: RTE 9
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.386,  Lanes on structure: 1,  Lanes under structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.8m (42.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 29.8m (97.8ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 0.6m (2.0ft),  Curb-To-Curb Width: 12.6m (41.3ft),  Out-to-Out Width: 14.1m (46.3ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 74.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 44.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.13m (10.27ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2006,  Bridge Improvement Cost: $708,000,  Roadway Improvement Cost: $422,000,  Total Project Cost: $1,130,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete
Find on map >>

Structure Number: 1091332,  Location: JCT S H 117 & U S 9 (Lat: 41.110267,  Lng: -73.858344),  Route carried "on" structure: State highway 117,  Year Built: 1970,  Status: Open,  Structure Length: 3.13m (10.27ft),  Average Daily Traffic: 5,522 (year 2006),  Truck Traffic: 6%,  Average Future Daily Traffic: 7,731 (year 2026),  Features Intersected: RTE 9
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.386,  Lanes on structure: 2,  Lanes under structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.8m (42.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 29.8m (97.8ft),  Curb or Sidewalk Widths: Left: 0.6m (2.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 12.6m (41.3ft),  Out-to-Out Width: 14.1m (46.3ft)

Condition: Deck: Satisfactory,  Superstructure: Very good,  Substructure: Good,  Operating Rating: 74.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 44.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Underclear: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.13m (10.27ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2006,  Bridge Improvement Cost: $708,000,  Roadway Improvement Cost: $422,000,  Total Project Cost: $1,130,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete
Find on map >>

Structure Number: 2038,  Location: JCT RTE 141&RR (HAWTHORN) (Lat: 41.107467,  Lng: -73.796439),  Route carried "on" structure: State highway 141,  Year Built: 1951,  Status: Open,  Structure Length: 2.52m (8.27ft),  Average Daily Traffic: 9,870 (year 2006),  Truck Traffic: 6%,  Average Future Daily Traffic: 13,818 (year 2026),  Features Intersected: MNRR HA LINE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.162,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.1m (39.7ft),  Material/Design: Steel,  Design/Construction: Girder and Floorbeam System,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 24.9m (81.7ft),  Curb or Sidewalk Widths: Left: 1.8m (5.9ft),  Right: 1.6m (5.2ft),  Curb-To-Curb Width: 12.1m (39.7ft),  Out-to-Out Width: 15.3m (50.2ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Satisfactory,  Operating Rating: 70.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 41.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Meets minimum limits,  Length Of Structure Improvement: 2.52m (8.27ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: September 2006,  Critical Feature Inspection Date: September 2006,  Bridge Improvement Cost: $856,000,  Roadway Improvement Cost: $509,000,  Total Project Cost: $1,365,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 226571,  Location: .8 MILE E OF N TARRYTOWN (Lat: 41.088033,  Lng: -73.837431),  Route carried "on" structure: Other road ,  Year Built: 1930,  Status: Open,  Structure Length: 1.37m (4.49ft),  Average Daily Traffic: 5 (year 2007),  Truck Traffic: 8%,  Average Future Daily Traffic: 7 ,  Features Intersected: LAKE ROAD,  Facility Carried by Structure: KYKUIT HILL ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Lanes under structure: 2,  Owner: State Agenciy,  Approaching Roadway Width: 3.6m (11.8ft),  Material/Design: Concrete,  Design/Construction: Frame,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 11.5m (37.7ft),  Curb-To-Curb Width: 4.7m (15.4ft),  Out-to-Out Width: 6.1m (20.0ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Fair,  Operating Rating: 61.1 metric tons,  Inventory Rating: 25.7 metric tons,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Better than present minimum criteria,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.37m (4.49ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2007,  Bridge Improvement Cost: $187,000,  Roadway Improvement Cost: $112,000,  Total Project Cost: $299,000 ( Estimate for 2007)
Find on map >>

Structure Number: 250204,  Location: .5 MI S JCT TSP & SMRP (Lat: 41.104372,  Lng: -73.796853),  Route carried "on" structure: City street ,  Year Built: 1920,  Status: Open,  Structure Length: 6.43m (21.10ft),  Average Daily Traffic: 3,444 (year 1996),  Truck Traffic: 8%,  Average Future Daily Traffic: 4,822 (year 2016),  Design Load: HS 20,  Features Intersected: 987F, MNRR HA LINE,  Facility Carried by Structure: CHELSEA STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 8,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 10.0m (32.8ft),  Skew: 9 degrees,  Material/Design: Steel,  Design/Construction: Girder and Floorbeam System,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 25.2m (82.7ft),  Curb or Sidewalk Widths: Left: 0.8m (2.6ft),  Right: 0.9m (3.0ft),  Curb-To-Curb Width: 10.0m (32.8ft),  Out-to-Out Width: 12.3m (40.4ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Operating Rating: 69.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 41.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 6.43m (21.10ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: October 2006,  Critical Feature Inspection Date: October 2006,  Bridge Improvement Cost: $1,752,000,  Roadway Improvement Cost: $1,043,000,  Total Project Cost: $2,795,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 33649,  Location: S END KENSICO RESERVOIR (Lat: 41.074411,  Lng: -73.775319),  Route carried "on" structure: Other road ,  Year Built: 1930,  Status: Open,  Structure Length: 2.43m (7.97ft),  Average Daily Traffic: 5,500 (year 1995),  Truck Traffic: 6%,  Average Future Daily Traffic: 7,977 (year 2015),  Features Intersected: MNRR HA LINE,  Facility Carried by Structure: LEGION DRIVE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Skew: 1 degrees,  Material/Design: Concrete,  Design/Construction: Frame,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 21.3m (69.9ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 1.4m (4.6ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 11.9m (39.0ft)

Condition: Superstructure: Satisfactory,  Substructure: Satisfactory,  Operating Rating: 89.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 72.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of corrective action,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.43m (7.97ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2007,  Bridge Improvement Cost: $641,000,  Roadway Improvement Cost: $382,000,  Total Project Cost: $1,023,000 ( Estimate for 2007),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 5006131,  Location: JCT SMRP&RTE 9A HAWTHORNE (Lat: 41.108144,  Lng: -73.806217),  Route carried "on" structure: Other road 987D,  Year Built: 1972,  Status: Open,  Structure Length: 8.74m (28.67ft),  Average Daily Traffic: 22,047 (year 2002),  Truck Traffic: 6%,  Average Future Daily Traffic: 32,006 (year 2022),  Design Load: HS 20,  Features Intersected: RTE 9A
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 338.501,  Lanes on structure: 4,  Lanes under structure: 5,  Owner: State Highway Agency,  Approaching Roadway Width: 14.6m (47.9ft),  Skew: 4 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 26.2m (86.0ft),  Curb or Sidewalk Widths: Left: 0.6m (2.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 14.6m (47.9ft),  Out-to-Out Width: 17.1m (56.1ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Fair,  Operating Rating: 86.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 51.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 8.74m (28.67ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2006,  Bridge Improvement Cost: $3,312,000,  Roadway Improvement Cost: $1,923,000,  Total Project Cost: $5,235,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Latex Concrete
Find on map >>

Structure Number: 5006132,  Location: JCT SMRP&RTE 9A HAWTHORNE (Lat: 41.107906,  Lng: -73.806328),  Route carried "on" structure: Other road 987D,  Year Built: 1972,  Status: Open,  Structure Length: 8.74m (28.67ft),  Average Daily Traffic: 22,047 (year 2002),  Truck Traffic: 6%,  Average Future Daily Traffic: 30,866 (year 2022),  Design Load: HS 20,  Features Intersected: RTE 9A
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 17.012,  Lanes on structure: 4,  Lanes under structure: 5,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.1m (39.7ft),  Skew: 4 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 26.2m (86.0ft),  Curb or Sidewalk Widths: Left: 0.6m (2.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 14.6m (47.9ft),  Out-to-Out Width: 17.1m (56.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 84.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 50.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of replacement,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 8.74m (28.67ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2006,  Bridge Improvement Cost: $3,312,000,  Roadway Improvement Cost: $1,923,000,  Total Project Cost: $5,235,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Latex Concrete
Find on map >>

Structure Number: 5500779,  Location: 1.8 MI S JCT RTS SMRP&TSP (Lat: 41.091728,  Lng: -73.819672),  Route carried "on" structure: Other road 987D,  Year Built: 1933,  Status: Posted for load-capacity,  Structure Length: 1.06m (3.48ft),  Average Daily Traffic: 47,335 (year 2002),  Truck Traffic: 6%,  Average Future Daily Traffic: 68,716 (year 2022),  Features Intersected: SAW MILL RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 336.120,  Lanes on structure: 4,  Owner: State Highway Agency,  Approaching Roadway Width: 14.9m (48.9ft),  Skew: 23 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.4m (30.8ft),  Curb-To-Curb Width: 17.6m (57.7ft),  Out-to-Out Width: 21.0m (68.9ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 42.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 25.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.06m (3.48ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2006,  Bridge Improvement Cost: $496,000,  Roadway Improvement Cost: $295,000,  Total Project Cost: $791,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 5500789,  Location: 1.5 MI S JCT RTS SMRP+TSP (Lat: 41.094919,  Lng: -73.815625),  Route carried "on" structure: Other road 987D,  Year Built: 1933,  Status: Open,  Structure Length: 1.09m (3.58ft),  Average Daily Traffic: 44,095 (year 2002),  Truck Traffic: 6%,  Average Future Daily Traffic: 61,733 (year 2022),  Features Intersected: SAW MILL RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 16.407,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 14.6m (47.9ft),  Skew: 23 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.4m (30.8ft),  Curb-To-Curb Width: 17.6m (57.7ft),  Out-to-Out Width: 21.0m (68.9ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 41.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 25.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.09m (3.58ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2006,  Bridge Improvement Cost: $496,000,  Roadway Improvement Cost: $295,000,  Total Project Cost: $791,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 5500799,  Location: 1.2 MI S JCT RTS SMRP+TSP (Lat: 41.098000,  Lng: -73.811367),  Route carried "on" structure: Other road 987D,  Year Built: 1933,  Status: Posted for load-capacity,  Structure Length: 1.06m (3.48ft),  Average Daily Traffic: 44,095 (year 2002),  Truck Traffic: 6%,  Average Future Daily Traffic: 61,733 (year 2022),  Features Intersected: SAW MILL RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 16.407,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 14.6m (47.9ft),  Skew: 23 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.7m (31.8ft),  Curb-To-Curb Width: 18.2m (59.7ft),  Out-to-Out Width: 21.2m (69.6ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 39.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 23.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.06m (3.48ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2006,  Bridge Improvement Cost: $499,000,  Roadway Improvement Cost: $297,000,  Total Project Cost: $796,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 5500809,  Location: 0.7 MI S JCT RTS SMRP+TSP (Lat: 41.103728,  Lng: -73.811119),  Route carried "on" structure: Other road 987D,  Year Built: 1933,  Status: Open,  Structure Length: 1.03m (3.38ft),  Average Daily Traffic: 44,095 (year 2002),  Truck Traffic: 6%,  Average Future Daily Traffic: 61,733 (year 2022),  Design Load: H 15,  Features Intersected: SAW MILL RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 16.407,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 14.6m (47.9ft),  Skew: 23 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.7m (31.8ft),  Curb-To-Curb Width: 17.6m (57.7ft),  Out-to-Out Width: 21.1m (69.2ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 45.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 27.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.03m (3.38ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2006,  Bridge Improvement Cost: $484,000,  Roadway Improvement Cost: $288,000,  Total Project Cost: $772,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 5500829,  Location: 0.3 MI E JCT RTS SMRP&TSP (Lat: 41.111961,  Lng: -73.796431),  Route carried "on" structure: Other road 987D,  Year Built: 1970,  Status: Open,  Structure Length: 4.84m (15.88ft),  Average Daily Traffic: 47,970 (year 2007),  Truck Traffic: 6%,  Average Future Daily Traffic: 67,158 (year 2027),  Features Intersected: SAW MILL RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 17.675,  Lanes on structure: 7,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 35.3m (115.8ft),  Skew: 33 degrees,  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 7.3m (24.0ft),  Curb-To-Curb Width: 29.5m (96.8ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 77.8 metric tons,  Inventory Rating: 32.6 metric tons,  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 4.84m (15.88ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2006,  Bridge Improvement Cost: $3,846,000,  Roadway Improvement Cost: $2,233,000,  Total Project Cost: $6,079,000 ( Estimate for 2007),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 5500839,  Location: 1.3 MI E JCT RTS SMRP+TSP (Lat: 41.122039,  Lng: -73.783319),  Route carried "on" structure: Other road 987D,  Year Built: 1930,  Year Reconstructed: 1995,  Status: Open,  Structure Length: 0.91m (2.99ft),  Average Daily Traffic: 47,970 (year 2007),  Truck Traffic: 6%,  Average Future Daily Traffic: 67,158 (year 2027),  Design Load: HS 20,  Features Intersected: SAW MILL RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 19.625,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 14.9m (48.9ft),  Skew: 22 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.8m (28.9ft),  Curb-To-Curb Width: 9.4m (30.8ft),  Out-to-Out Width: 20.4m (66.9ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 49.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 29.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.91m (2.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2006,  Bridge Improvement Cost: $3,846,000,  Roadway Improvement Cost: $2,233,000,  Total Project Cost: $6,079,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 5500841,  Location: 4.7 MI SE OF OSSINING (Lat: 41.125092,  Lng: -73.786244),  Route carried "on" structure: Other road ,  Year Built: 1990,  Status: Open,  Structure Length: 1.82m (5.97ft),  Average Daily Traffic: 7,596 (year 1997),  Truck Traffic: 8%,  Average Future Daily Traffic: 10,103 (year 2017),  Design Load: HS 20,  Features Intersected: SAWMILL RIVER,  Facility Carried by Structure: TO SAWMILL R PKWY
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Material/Design: Prestressed concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 17.3m (56.8ft),  Curb or Sidewalk Widths: Left: 0.1m (0.3ft),  Right: 0.0m,  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 9.0m (29.5ft)

Condition: Deck: Very good,  Superstructure: Excellent,  Substructure: Excellent,  Channel: Very good,  Operating Rating: 70.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Superior to present desirable criteria,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Meets minimum limits,  Length Of Structure Improvement: 1.82m (5.97ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2006,  Bridge Improvement Cost: $3,846,000,  Roadway Improvement Cost: $2,233,000,  Total Project Cost: $6,079,000 ( Estimate for 2007),  Wearing Surface/Protective System: Wearing Surface: Integral Concrete
Find on map >>

Structure Number: 5500842,  Location: 4.7 MI SE OF OSSINING (Lat: 41.125097,  Lng: -73.784575),  Route carried "on" structure: Ramp Other road ,  Year Built: 1949,  Status: Open,  Structure Length: 1.76m (5.77ft),  Average Daily Traffic: 45,781 (year 1997),  Truck Traffic: 8%,  Average Future Daily Traffic: 60,889 (year 2017),  Design Load: H 20,  Features Intersected: SAW MILL RIVER,  Facility Carried by Structure: TO SAWMILL R PKWY
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 7.0m (23.0ft),  Curb or Sidewalk Widths: Left: 0.0m,  Right: 1.7m (5.6ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 11.1m (36.4ft)

Condition: Deck: Poor,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 95.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 57.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.76m (5.77ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2006,  Bridge Improvement Cost: $423,000,  Roadway Improvement Cost: $252,000,  Total Project Cost: $675,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 5500859,  Location: 1.6 MI E JCT RTS SMRP+TSP (Lat: 41.124819,  Lng: -73.786497),  Route carried "on" structure: Other road 987D,  Year Built: 1930,  Year Reconstructed: 1995,  Status: Posted for load-capacity,  Structure Length: 0.88m (2.89ft),  Average Daily Traffic: 47,970 (year 2007),  Truck Traffic: 6%,  Average Future Daily Traffic: 67,158 (year 2027),  Design Load: HS 20,  Features Intersected: SAW MILL RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 19.627,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.4m (30.8ft),  Skew: 23 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.2m (26.9ft),  Curb-To-Curb Width: 9.4m (30.8ft),  Out-to-Out Width: 22.5m (73.8ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Channel: Fair,  Operating Rating: 40.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 20.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.88m (2.89ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2007,  Bridge Improvement Cost: $423,000,  Roadway Improvement Cost: $252,000,  Total Project Cost: $675,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 550201,  Location: 2.2 MI S JCT RTS BRP+TSP (Lat: 41.074456,  Lng: -73.775283),  Route carried "on" structure: County highway ,  Year Built: 1931,  Status: Open,  Structure Length: 1.67m (5.48ft),  Average Daily Traffic: 7,517 (year 1997),  Truck Traffic: 6%,  Average Future Daily Traffic: 10,903 (year 2017),  Features Intersected: RTE 987G,  Facility Carried by Structure: LEGION DRIVE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 4,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Concrete,  Design/Construction: Frame,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 14.9m (48.9ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 1.4m (4.6ft),  Curb-To-Curb Width: 9.2m (30.2ft),  Out-to-Out Width: 12.0m (39.4ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 56.9 metric tons,  Inventory Rating: 23.3 metric tons,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.67m (5.48ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2006,  Bridge Improvement Cost: $446,000,  Roadway Improvement Cost: $266,000,  Total Project Cost: $712,000 ( Estimate for 2007),  Wearing Surface/Protective System: Wearing Surface: Bituminous

Parts: 1, 2

Discuss this city on our hugely popular New York forum

Back to: Mount Pleasant, NY, New York, All US cities.


City-data.com does not guarantee the accuracy or timeliness of any information on this site.  Use at your own risk.
Some parts © 2009 Advameg, Inc.