National Bridge Inventory (NBI) Statistics
Number of bridges: 27
Total length: 101 meters (331ft)
Total costs: $29,135,000
Total average daily traffic: 110,815
Total average daily truck traffic: 11,277
National Bridge Inventory (NBI) Registered Bridges for Norwich

New bridges - Historical Statistics

  • 1920-1929: 3
  • 1930-1939: 2
  • 1940-1949: 0
  • 1950-1959: 3
  • 1960-1969: 10
  • 1970-1979: 7
  • 1980-1989: 1
  • 1990-1999: 1

Reconstructed bridges - Historical Statistics

  • 1960-1969: 1
  • 1970-1979: 1
  • 1980-1989: 2
  • 1990-1999: 1
  • 2000-2009: 1

Average Daily Traffic

Bridge Condition - Deck

Bridge Condition - Superstructure

Bridge Condition - Substructure

Bridge Condition - Channel

Bridge Condition - Culverts

Find on map >>

Structure Number: 101411001014111,  Location: 0.2 MI TO JCT W CL3 TH43 (Lat: 43.730556,  Lng: -72.316667),  Route carried "on" structure: Other road C3012,  Year Built: 1928,  Status: Open,  Structure Length: 1.04m (3.41ft),  Average Daily Traffic: 400 (year 1996),  Truck Traffic: 2%,  Average Future Daily Traffic: 600 (year 2016),  Features Intersected: BLOODY BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.8m (32.2ft),  Curb-To-Curb Width: 6.2m (20.3ft),  Out-to-Out Width: 7.1m (23.3ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 48.6 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 27.0 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.65m (5.41ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2006,  Bridge Improvement Cost: $375,000,  Roadway Improvement Cost: $150,000,  Total Project Cost: $525,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 101411001214111,  Location: 0.2 MI TO JCT W CL3 TH12 (Lat: 43.725556,  Lng: -72.317222),  Route carried "on" structure: Other road C3043,  Year Built: 1989,  Status: Open,  Structure Length: 1.49m (4.89ft),  Average Daily Traffic: 125 (year 1996),  Truck Traffic: 2%,  Average Future Daily Traffic: 187 (year 2016),  Design Load: HS 20,  Features Intersected: BLOODY BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Skew: 2 degrees,  Material/Design: Wood or Timber,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 11.3m (37.1ft),  Curb or Sidewalk Widths: Left: 0.0m,  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 6.6m (21.7ft),  Out-to-Out Width: 7.3m (24.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 10.8 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 10.8 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.38m (7.81ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2006,  Bridge Improvement Cost: $555,000,  Roadway Improvement Cost: $150,000,  Total Project Cost: $705,000 ( Estimate for 2007),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Deck Protection: Internally Sealed
Find on map >>

Structure Number: 101411001314111,  Location: @ JCT W CL3 TH36 (Lat: 43.726667,  Lng: -72.320278),  Route carried "on" structure: Other road C2002,  Year Built: 1958,  Year Reconstructed: 1973,  Status: Open,  Structure Length: 0.91m (2.99ft),  Average Daily Traffic: 300 (year 1996),  Truck Traffic: 2%,  Average Future Daily Traffic: 450 (year 2016),  Features Intersected: CHARLES BROWN BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 2 degrees,  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.5m (27.9ft),  Curb-To-Curb Width: 8.6m (28.2ft),  Out-to-Out Width: 9.1m (29.9ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 22.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 13.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.65m (5.41ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2006,  Bridge Improvement Cost: $476,000,  Roadway Improvement Cost: $150,000,  Total Project Cost: $626,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>

Structure Number: 101411003914111,  Location: 0.02 MI SE OF JCT TH75 (Lat: 43.717500,  Lng: -72.312778),  Route carried "on" structure: Other road C2002,  Year Built: 1973,  Status: Open,  Structure Length: 1.52m (4.99ft),  Average Daily Traffic: 500 (year 1996),  Truck Traffic: 2%,  Average Future Daily Traffic: 750 (year 2016),  Design Load: H 20,  Features Intersected: BLOODY BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Skew: 1 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 14.0m (45.9ft),  Curb or Sidewalk Widths: Left: 1.4m (4.6ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 9.0m (29.5ft),  Out-to-Out Width: 9.9m (32.5ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 54.0 metric tons,  Inventory Rating: 32.4 metric tons,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.44m (8.01ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2006,  Bridge Improvement Cost: $767,000,  Roadway Improvement Cost: $150,000,  Total Project Cost: $917,000 ( Estimate for 2007),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 101411004014111,  Location: 0.5 MI TO JCT W CL3 TH36 (Lat: 43.745278,  Lng: -72.324722),  Route carried "on" structure: Other road C3016,  Year Built: 1991,  Status: Open,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 590 (year 1996),  Truck Traffic: 2%,  Average Future Daily Traffic: 885 (year 2016),  Features Intersected: BLOODY BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.4m (21.0ft)

Condition: Channel: Good,  Culverts: Very good,  Operating Rating: 54.0 metric tons,  Inventory Rating: 32.4 metric tons,  Structural Evaluation: Equal to present desirable criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.64m (2.10ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2006,  Bridge Improvement Cost: $109,000,  Roadway Improvement Cost: $25,000,  Total Project Cost: $134,000 ( Estimate for 2007)
Find on map >>

Structure Number: 101411004114111,  Location: 0.25 MI TO JCT W C3 TH36 (Lat: 43.743611,  Lng: -72.323056),  Route carried "on" structure: Other road C3016,  Year Built: 1931,  Year Reconstructed: 1988,  Status: Open,  Structure Length: 0.79m (2.59ft),  Average Daily Traffic: 400 (year 1996),  Truck Traffic: 2%,  Average Future Daily Traffic: 600 (year 2016),  Features Intersected: BLOODY BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 3 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.6m (24.9ft),  Curb or Sidewalk Widths: Left: 0.1m (0.3ft),  Right: 0.1m (0.3ft),  Curb-To-Curb Width: 8.0m (26.2ft),  Out-to-Out Width: 8.4m (27.6ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Fair,  Channel: Fair,  Operating Rating: 38.7 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 22.5 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.43m (4.69ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2006,  Bridge Improvement Cost: $381,000,  Roadway Improvement Cost: $150,000,  Total Project Cost: $531,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 101411004214111,  Location: 0.01 MI TO JCT W C3 TH36 (Lat: 43.734722,  Lng: -72.316944),  Route carried "on" structure: Other road C3016,  Year Built: 1929,  Year Reconstructed: 1984,  Status: Open,  Structure Length: 1.01m (3.31ft),  Average Daily Traffic: 400 (year 1996),  Truck Traffic: 2%,  Average Future Daily Traffic: 600 (year 2016),  Features Intersected: BLOODY BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Skew: 3 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.4m (30.8ft),  Curb-To-Curb Width: 7.6m (24.9ft),  Out-to-Out Width: 8.4m (27.6ft)

Condition: Deck: Satisfactory,  Superstructure: Poor,  Substructure: Satisfactory,  Channel: Fair,  Operating Rating: 18.9 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 6.3 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: High priority of replacement,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.62m (5.31ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2006,  Bridge Improvement Cost: $431,000,  Roadway Improvement Cost: $150,000,  Total Project Cost: $581,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 101411004314111,  Location: 0.3 MI TO JCT W US5 (Lat: 43.710833,  Lng: -72.312778),  Route carried "on" structure: Other road C3060,  Year Built: 1956,  Status: Open,  Structure Length: 2.01m (6.59ft),  Average Daily Traffic: 700 (year 1996),  Truck Traffic: 2%,  Average Future Daily Traffic: 1,050 (year 2016),  Design Load: H 15,  Features Intersected: BLOODY BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 19.2m (63.0ft),  Curb or Sidewalk Widths: Left: 0.6m (2.0ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 6.8m (22.3ft),  Out-to-Out Width: 7.6m (24.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Very good,  Operating Rating: 19.8 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 8.1 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: High priority of replacement,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 2.80m (9.19ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2006,  Bridge Improvement Cost: $678,000,  Roadway Improvement Cost: $150,000,  Total Project Cost: $828,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 101411004414111,  Location: 0.18 MI TO JCT W CL2 TH2 (Lat: 43.715000,  Lng: -72.314444),  Route carried "on" structure: Other road C3058,  Year Built: 1928,  Year Reconstructed: 1999,  Status: Open,  Structure Length: 1.16m (3.81ft),  Average Daily Traffic: 350 (year 1996),  Truck Traffic: 2%,  Average Future Daily Traffic: 525 (year 2016),  Features Intersected: BLOODY BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Skew: 2 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 10.7m (35.1ft),  Curb or Sidewalk Widths: Left: 0.0m,  Right: 1.2m (3.9ft),  Curb-To-Curb Width: 6.9m (22.6ft),  Out-to-Out Width: 7.3m (24.0ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Satisfactory,  Channel: Very good,  Operating Rating: 36.0 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 24.3 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.86m (6.10ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2006,  Bridge Improvement Cost: $432,000,  Roadway Improvement Cost: $150,000,  Total Project Cost: $582,000 ( Estimate for 2007),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 200091048N14112,  Location: I91 EXIT 13 (Lat: 43.705556,  Lng: -72.306389),  Route carried "on" structure: Interstate 91,  Year Built: 1968,  Status: Open,  Structure Length: 6.86m (22.51ft),  Average Daily Traffic: 8,700 (year 1998),  Truck Traffic: 13%,  Average Future Daily Traffic: 13,050 (year 2018),  Design Load: HS 20,  Features Intersected: I 91 OVER VT 10A
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 120.401,  Lanes on structure: 2,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Skew: 12 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 33.5m (109.9ft),  Curb or Sidewalk Widths: Left: 0.5m (1.6ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 11.4m (37.4ft),  Out-to-Out Width: 12.8m (42.0ft)

Condition: Deck: Good,  Superstructure: Fair,  Substructure: Fair,  Operating Rating: 56.7 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 35.1 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 7.56m (24.80ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2006,  Bridge Improvement Cost: $2,734,000,  Roadway Improvement Cost: $150,000,  Total Project Cost: $2,884,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 200091048S14112,  Location: I91 EXIT 13 (Lat: 43.705833,  Lng: -72.306389),  Route carried "on" structure: Interstate 91,  Year Built: 1968,  Status: Open,  Structure Length: 6.86m (22.51ft),  Average Daily Traffic: 8,700 (year 1998),  Truck Traffic: 13%,  Average Future Daily Traffic: 13,050 (year 2018),  Design Load: HS 20,  Features Intersected: I 91 OVER VT 10A
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 120.401,  Lanes on structure: 3,  Lanes under structure: 5,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Skew: 12 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 33.5m (109.9ft),  Curb or Sidewalk Widths: Left: 0.5m (1.6ft),  Right: 0.5m (1.6ft),  Curb-To-Curb Width: 12.8m (42.0ft),  Out-to-Out Width: 14.6m (47.9ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Fair,  Operating Rating: 56.7 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 37.8 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Underclear: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 7.56m (24.80ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2006,  Bridge Improvement Cost: $3,124,000,  Roadway Improvement Cost: $150,000,  Total Project Cost: $3,274,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 200091049N14112,  Location: 1.0 MI N EXIT 13 (Lat: 43.716944,  Lng: -72.293333),  Route carried "on" structure: Interstate 91,  Year Built: 1968,  Status: Open,  Structure Length: 4.18m (13.71ft),  Average Daily Traffic: 5,600 (year 1998),  Truck Traffic: 13%,  Average Future Daily Traffic: 8,400 (year 2018),  Design Load: HS 20,  Features Intersected: I 91 OVER US 5
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 122.027,  Lanes on structure: 2,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.6m (38.1ft),  Skew: 13 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 40.5m (132.9ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 11.4m (37.4ft),  Out-to-Out Width: 12.9m (42.3ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Poor,  Operating Rating: 89.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 57.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 5.00m (16.40ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2006,  Bridge Improvement Cost: $1,829,000,  Roadway Improvement Cost: $150,000,  Total Project Cost: $1,979,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 200091049S14112,  Location: 1.0 MI N EXIT 13 (Lat: 43.716944,  Lng: -72.293611),  Route carried "on" structure: Interstate 91,  Year Built: 1968,  Status: Open,  Structure Length: 4.24m (13.91ft),  Average Daily Traffic: 5,600 (year 1998),  Truck Traffic: 13%,  Average Future Daily Traffic: 8,400 (year 2018),  Design Load: HS 20,  Features Intersected: I 91 OVER US 5
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 122.027,  Lanes on structure: 2,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.6m (38.1ft),  Skew: 13 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 41.5m (136.2ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 11.4m (37.4ft),  Out-to-Out Width: 12.9m (42.3ft)

Condition: Deck: Good,  Superstructure: Fair,  Substructure: Poor,  Operating Rating: 89.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 57.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 5.09m (16.70ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2006,  Bridge Improvement Cost: $1,856,000,  Roadway Improvement Cost: $150,000,  Total Project Cost: $2,006,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 200091050N14112,  Location: 2.3 MI N EXIT 13 (Lat: 43.730833,  Lng: -72.278889),  Route carried "on" structure: Interstate 91,  Year Built: 1970,  Status: Open,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 5,600 (year 1998),  Truck Traffic: 13%,  Average Future Daily Traffic: 8,400 (year 2018),  Design Load: HS 20,  Features Intersected: I 91 OVER TH NO 24
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 124.006,  Lanes on structure: 2,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 23.2m (76.1ft),  Skew: 14 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.4m (21.0ft)

Condition: Culverts: Fair,  Operating Rating: 54.0 metric tons,  Inventory Rating: 32.4 metric tons,  Structural Evaluation: Somewhat better than minimum adequacy,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.64m (2.10ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2006,  Bridge Improvement Cost: $295,000,  Roadway Improvement Cost: $25,000,  Total Project Cost: $320,000 ( Estimate for 2007)
Find on map >>

Structure Number: 200091050S14112,  Location: 2.3 MI N EXIT 13 (Lat: 43.731667,  Lng: -72.278889),  Route carried "on" structure: Interstate 91,  Year Built: 1970,  Status: Open,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 5,600 (year 1998),  Truck Traffic: 13%,  Average Future Daily Traffic: 8,400 (year 2018),  Design Load: HS 20,  Features Intersected: I 91 OVER TH NO 24
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 124.006,  Lanes on structure: 2,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 23.2m (76.1ft),  Skew: 14 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.4m (21.0ft)

Condition: Culverts: Fair,  Operating Rating: 54.0 metric tons,  Inventory Rating: 32.4 metric tons,  Structural Evaluation: Somewhat better than minimum adequacy,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.64m (2.10ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2006,  Bridge Improvement Cost: $295,000,  Roadway Improvement Cost: $25,000,  Total Project Cost: $320,000 ( Estimate for 2007)
Find on map >>

Structure Number: 200091051N14112,  Location: 4.0 MI S EXIT 14 (Lat: 43.760000,  Lng: -72.233056),  Route carried "on" structure: Interstate 91,  Year Built: 1970,  Status: Open,  Structure Length: 7.62m (25.00ft),  Average Daily Traffic: 5,600 (year 1998),  Truck Traffic: 13%,  Average Future Daily Traffic: 8,400 (year 2018),  Design Load: HS 20,  Features Intersected: I 91 OVER TH 3 OMPOMR
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 129.074,  Lanes on structure: 2,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.9m (39.0ft),  Skew: 11 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 37.2m (122.0ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 12.0m (39.4ft),  Out-to-Out Width: 13.3m (43.6ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Very good,  Operating Rating: 89.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 58.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Underclear: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 8.38m (27.49ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2006,  Bridge Improvement Cost: $3,146,000,  Roadway Improvement Cost: $150,000,  Total Project Cost: $3,296,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 200091051S14112,  Location: 4.0 MI S EXIT 14 (Lat: 43.760000,  Lng: -72.233056),  Route carried "on" structure: Interstate 91,  Year Built: 1970,  Status: Open,  Structure Length: 7.62m (25.00ft),  Average Daily Traffic: 5,600 (year 1998),  Truck Traffic: 13%,  Average Future Daily Traffic: 8,400 (year 2018),  Design Load: HS 20,  Features Intersected: I 91 OVER TH 3 OMPOMR
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 129.074,  Lanes on structure: 2,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.9m (39.0ft),  Skew: 11 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 37.2m (122.0ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 12.0m (39.4ft),  Out-to-Out Width: 13.3m (43.6ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Very good,  Operating Rating: 89.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 58.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Underclear: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 8.38m (27.49ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2006,  Bridge Improvement Cost: $3,146,000,  Roadway Improvement Cost: $150,000,  Total Project Cost: $3,296,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 20009147-214112,  Location: 0.1 MI S EXIT 13 (Lat: 43.704722,  Lng: -72.307222),  Route carried "on" structure: Interstate 91,  Year Built: 1968,  Status: Open,  Structure Length: 0.73m (2.40ft),  Average Daily Traffic: 17,400 (year 1998),  Truck Traffic: 13%,  Average Future Daily Traffic: 26,100 (year 2018),  Design Load: HS 20,  Features Intersected: BLOODY BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 120.273,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 23.2m (76.1ft),  Skew: 12 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.3m (24.0ft)

Condition: Channel: Very good,  Culverts: Satisfactory,  Operating Rating: 54.0 metric tons,  Inventory Rating: 32.4 metric tons,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.73m (2.40ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2006,  Bridge Improvement Cost: $337,000,  Roadway Improvement Cost: $25,000,  Total Project Cost: $362,000 ( Estimate for 2007)
Find on map >>

Structure Number: 200113008114112,  Location: 0.1 MI S JCT. VT.132 (Lat: 43.754167,  Lng: -72.230278),  Route carried "on" structure: US 5,  Year Built: 1937,  Year Reconstructed: 1993,  Status: Open,  Structure Length: 7.80m (25.59ft),  Average Daily Traffic: 1,600 (year 1998),  Truck Traffic: 6%,  Average Future Daily Traffic: 2,400 (year 2018),  Design Load: HS 25,  Features Intersected: OMPOMPANOOSUC RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 10.1m (33.1ft),  Skew: 4 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 25.6m (84.0ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 8.7m (28.5ft),  Out-to-Out Width: 9.4m (30.8ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Good,  Channel: Very good,  Operating Rating: 68.4 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 40.5 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 8.60m (28.22ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 48 months,  Inspection Date: May 2007,  Underwater Inspection Date: September 2004,  Bridge Improvement Cost: $2,281,000,  Roadway Improvement Cost: $150,000,  Total Project Cost: $2,431,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 200170000214112,  Location: 0.2 MI E JCT I 91 (Lat: 43.704167,  Lng: -72.302222),  Route carried "on" structure: Alternate State highway 10A,  Year Built: 1968,  Status: Open,  Structure Length: 2.96m (9.71ft),  Average Daily Traffic: 12,800 (year 1998),  Truck Traffic: 6%,  Average Future Daily Traffic: 19,200 (year 2018),  Design Load: HS 20,  Features Intersected: VT 10A OVER CONN RIV RR
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 4,  Owner: State Highway Agency,  Approaching Roadway Width: 20.1m (65.9ft),  Skew: 21 degrees,  Material/Design: Concrete continuous,  Design/Construction: Slab,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 11.9m (39.0ft),  Curb or Sidewalk Widths: Left: 1.6m (5.2ft),  Right: 1.6m (5.2ft),  Curb-To-Curb Width: 19.7m (64.6ft),  Out-to-Out Width: 23.7m (77.8ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Operating Rating: 54.0 metric tons,  Inventory Rating: 32.4 metric tons,  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Underclear: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.54m (11.61ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2007,  Bridge Improvement Cost: $2,376,000,  Roadway Improvement Cost: $150,000,  Total Project Cost: $2,526,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>

Structure Number: 200177004614112,  Location: 0.9 MI W JCT. U.S.5 (Lat: 43.763056,  Lng: -72.239444),  Route carried "on" structure: County highway 3,  Year Built: 1950,  Year Reconstructed: 2005,  Status: Open,  Structure Length: 3.05m (10.01ft),  Average Daily Traffic: 330 (year 2003),  Truck Traffic: 4%,  Average Future Daily Traffic: 495 (year 2023),  Design Load: HS 25,  Features Intersected: OMPOMANOOSUC RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 14.3m (46.9ft),  Curb or Sidewalk Widths: Left: 0.5m (1.6ft),  Right: 0.5m (1.6ft),  Curb-To-Curb Width: 7.6m (24.9ft),  Out-to-Out Width: 8.3m (27.2ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Good,  Channel: Good,  Operating Rating: 70.2 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 42.3 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: High priority of corrective action,  Length Of Structure Improvement: 3.66m (12.01ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 48 months,  Inspection Date: August 2006,  Underwater Inspection Date: September 2004,  Bridge Improvement Cost: $862,000,  Roadway Improvement Cost: $150,000,  Total Project Cost: $1,012,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 200091048N14112,  Location: I91 EXIT 12 (Lat: 43.705556,  Lng: -72.306389),  Route carried "under" structure: Alternate State highway 10A,  Year Built: 1968,  Structure Length: 6.86m (22.51ft),  Average Daily Traffic: 10,800 (year 1998),  Truck Traffic: 6%,  Features Intersected: I 91 OVER VT.10A,  Facility Carried by Structure: I 00091 ML
Minimum Vertical Clearance: 4.78m (15.68ft),  Kilometerpoint: 0.000,  Lanes on structure: 5,  Lanes under structure: 5,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 33.5m (109.9ft)

Find on map >>

Structure Number: 200091048S14112,  Location: I91 EXIT 12 (Lat: 43.705833,  Lng: -72.306389),  Route carried "under" structure: Alternate State highway 10A,  Year Built: 1968,  Structure Length: 6.86m (22.51ft),  Average Daily Traffic: 10,800 (year 1998),  Truck Traffic: 6%,  Features Intersected: I 91 OVER VT.10A,  Facility Carried by Structure: I 00091 ML
Minimum Vertical Clearance: 4.44m (14.57ft),  Kilometerpoint: 0.000,  Lanes on structure: 5,  Lanes under structure: 5,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 33.5m (109.9ft)

Find on map >>

Structure Number: 200091049N14112,  Location: 1.1 MI N JCT. VT.10 (Lat: 43.716944,  Lng: -72.293333),  Route carried "under" structure: US 5,  Year Built: 1968,  Structure Length: 4.18m (13.71ft),  Average Daily Traffic: 860 (year 1998),  Truck Traffic: 6%,  Features Intersected: I 91 OVER U.S.5,  Facility Carried by Structure: I 00091 ML
Minimum Vertical Clearance: 0.48m (1.57ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 2,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 40.5m (132.9ft)

Find on map >>

Structure Number: 200091049S14112,  Location: 1.1 MI N JCT. VT.10 (Lat: 43.716944,  Lng: -72.293611),  Route carried "under" structure: US 5,  Year Built: 1968,  Structure Length: 4.18m (13.71ft),  Average Daily Traffic: 860 (year 1998),  Truck Traffic: 6%,  Features Intersected: I 91 OVER U.S.5,  Facility Carried by Structure: I 00091 ML
Minimum Vertical Clearance: 4.34m (14.24ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 2,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 40.5m (132.9ft)

Find on map >>

Structure Number: 200091051N14112,  Location: 0.3 MI W JCT. U.S.5 (Lat: 43.760000,  Lng: -72.233056),  Route carried "under" structure: County highway 3,  Year Built: 1970,  Structure Length: 7.62m (25.00ft),  Average Daily Traffic: 300 (year 1995),  Truck Traffic: 6%,  Features Intersected: I 91 OVER TH NO 3,  Facility Carried by Structure: I 00091 ML
Minimum Vertical Clearance: 4.62m (15.16ft),  Kilometerpoint: 0.000,  Lanes on structure: 4,  Lanes under structure: 2,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 37.2m (122.0ft)

Find on map >>

Structure Number: 200091051S14112,  Location: 0.3 MI W JCT. U.S.5 (Lat: 43.760000,  Lng: -72.233056),  Route carried "under" structure: County highway 3,  Year Built: 1970,  Structure Length: 7.62m (25.00ft),  Average Daily Traffic: 300 (year 1995),  Truck Traffic: 6%,  Features Intersected: I 91 OVER TH NO 3,  Facility Carried by Structure: I 00091 ML
Minimum Vertical Clearance: 0.50m (1.64ft),  Kilometerpoint: 0.000,  Lanes on structure: 4,  Lanes under structure: 2,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 37.2m (122.0ft)

Discuss this city on our hugely popular Vermont forum