Number of bridges: 534
Total length: 20,399 meters (66,926ft)
Total costs: $778,627,000
Total average daily traffic: 28,687,837
Total average daily truck traffic: 1,029,191
National Bridge Inventory (NBI) Registered Bridges for Oakland
No street view available for this location

New bridges - Historical Statistics

  • 1920-1929: 2
  • 1930-1939: 18
  • 1940-1949: 20
  • 1950-1959: 42
  • 1960-1969: 227
  • 1970-1979: 149
  • 1980-1989: 18
  • 1990-1999: 56
  • 2000-2009: 2

Reconstructed bridges - Historical Statistics

  • 1950-1959: 8
  • 1960-1969: 6
  • 1970-1979: 4
  • 1980-1989: 1
  • 1990-1999: 2
  • 2000-2009: 1

Average Daily Traffic

Average Truck Traffic (%)

Bridge Condition - Deck

Bridge Condition - Superstructure

Bridge Condition - Substructure

Bridge Condition - Channel

Find on map >>   Show street view

Structure Number: 33 0025,  Location: 04-ALA-080-1.15-OAK (Lat: 37.814944,  Lng: -122.356861),  Route carried "on" structure: Interstate 80,  Year Built: 1936,  Year Reconstructed: 1962,  Status: Open,  Structure Length: 716.20m (2349.74ft),  Average Daily Traffic: 277,700 (year 1997),  Truck Traffic: 10%,  Average Future Daily Traffic: 334,528 (year 2029),  Design Load: HS 20,  Features Intersected: SAN FRANCISCO BAY
Minimum Vertical Clearance: 4.88m (16.01ft),  Kilometerpoint: 1.150,  Lanes on structure: 5,  Base Highway Network: Yes (,  Subroute: 1),  Toll: Toll bridge,  Owner: State Highway Agency,  Approaching Roadway Width: 18.3m (60.0ft),  Navigation Control: Yes ( Vertical Clearance: 56.4m (185.0ft), Horizontal Clearance: 405.1m (1,329.1ft)),  Material/Design: Steel continuous,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 426.7m (1,399.9ft),  Curb or Sidewalk Widths: Left: 0.5m (1.6ft),  Right: 0.5m (1.6ft),  Curb-To-Curb Width: 17.7m (58.1ft),  Out-to-Out Width: 19.3m (63.3ft)

Condition: Deck: Fair,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Fair,  Operating Rating: 47.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 28.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 716.20m (2349.74ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: Febuary 12,  Critical Feature Inspection Date: May 11,  Underwater Inspection Date: August 2009,  Bridge Improvement Cost: $124,686,000,  Roadway Improvement Cost: $24,937,000,  Total Project Cost: $209,472,000 ( Estimate for 2010),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Epoxy Overlay
Find on map >>   Show street view

Structure Number: 33 0027,  Location: 04-ALA-880-30.38-OAK (Lat: 37.791667,  Lng: -122.260000),  Route carried "on" structure: Interstate 880,  Year Built: 1948,  Year Reconstructed: 1963,  Status: Open,  Structure Length: 77.85m (255.41ft),  Average Daily Traffic: 225,000 (year 2009),  Truck Traffic: 14%,  Average Future Daily Traffic: 294,420 (year 2033),  Design Load: HS 20,  Features Intersected: UP RR,BNSF,AMTRAK,5TH AV
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 30.380,  Lanes on structure: 8,  Lanes under structure: 3,  Base Highway Network: Yes (Inventory Route: 8,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 15.2m (49.9ft),  Skew: 29 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 49,  Length of Maximum Span: 24.4m (80.1ft),  Curb or Sidewalk Widths: Left: 0.5m (1.6ft),  Right: 0.5m (1.6ft),  Curb-To-Curb Width: 30.5m (100.1ft),  Out-to-Out Width: 33.2m (108.9ft)

Condition: Deck: Imminent failure,  Superstructure: Poor,  Substructure: Satisfactory,  Channel: Very good,  Operating Rating: 50.2 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 33.7 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Meets minimum limits,  Underclear: High priority of corrective action,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 77.85m (255.41ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: Febuary 11,  Critical Feature Inspection Date: October 10,  Bridge Improvement Cost: $55,712,000,  Roadway Improvement Cost: $11,142,000,  Total Project Cost: $93,597,000 ( Estimate for 2010),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 33 0040L,  Location: 04-ALA-880-27.63-OAK (Lat: 37.768336,  Lng: -122.218336),  Route carried "on" structure: Interstate 880,  Year Built: 1950,  Year Reconstructed: 1963,  Status: Open,  Structure Length: 52.79m (173.20ft),  Average Daily Traffic: 110,500 (year 2009),  Truck Traffic: 11%,  Average Future Daily Traffic: 145,782 (year 2033),  Design Load: HS 20,  Features Intersected: UP RR,AMTRAK,SR 77,HIGH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 27.630,  Lanes on structure: 4,  Lanes under structure: 7,  Base Highway Network: Yes (Inventory Route: 8,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 20.1m (65.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 32,  Length of Maximum Span: 23.2m (76.1ft),  Curb or Sidewalk Widths: Left: 0.0m,  Right: 0.6m (2.0ft),  Curb-To-Curb Width: 15.2m (49.9ft),  Out-to-Out Width: 16.8m (55.1ft)

Condition: Deck: Serious,  Superstructure: Poor,  Substructure: Good,  Operating Rating: 51.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 25.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: High priority of replacement,  Underclear: High priority of replacement,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 52.79m (173.20ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: January 11,  Critical Feature Inspection Date: August 11,  Bridge Improvement Cost: $21,463,000,  Roadway Improvement Cost: $4,292,000,  Total Project Cost: $36,058,000 ( Estimate for 2010),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete
Find on map >>   Show street view

Structure Number: 33 0040R,  Location: 04-ALA-880-27.63-OAK (Lat: 37.768333,  Lng: -122.218333),  Route carried "on" structure: Interstate 880,  Year Built: 1950,  Year Reconstructed: 1963,  Status: Open,  Structure Length: 53.16m (174.41ft),  Average Daily Traffic: 110,500 (year 2009),  Truck Traffic: 11%,  Average Future Daily Traffic: 145,782 (year 2033),  Design Load: HS 20,  Features Intersected: UP RR,AMTRAK,SR 77,HIGH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 27.630,  Lanes on structure: 4,  Lanes under structure: 11,  Base Highway Network: Yes (Inventory Route: 8,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 15.2m (49.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 32,  Length of Maximum Span: 26.2m (86.0ft),  Curb or Sidewalk Widths: Left: 0.6m (2.0ft),  Right: 0.6m (2.0ft),  Curb-To-Curb Width: 15.2m (49.9ft),  Out-to-Out Width: 17.1m (56.1ft)

Condition: Deck: Serious,  Superstructure: Poor,  Substructure: Good,  Operating Rating: 51.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: High priority of replacement,  Underclear: High priority of replacement,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 53.16m (174.41ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: January 11,  Critical Feature Inspection Date: March 11,  Bridge Improvement Cost: $20,907,000,  Roadway Improvement Cost: $4,181,000,  Total Project Cost: $35,123,000 ( Estimate for 2010),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 33 0041,  Location: 04-ALA-880-28.24-OAK (Lat: 37.771667,  Lng: -122.225000),  Route carried "on" structure: Interstate 880,  Year Built: 1948,  Year Reconstructed: 1963,  Status: Open,  Structure Length: 42.98m (141.01ft),  Average Daily Traffic: 225,000 (year 2009),  Truck Traffic: 14%,  Average Future Daily Traffic: 294,420 (year 2033),  Design Load: HS 20,  Features Intersected: UP RR SPUR,FRUITVALE AVE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 28.240,  Lanes on structure: 8,  Lanes under structure: 7,  Base Highway Network: Yes (Inventory Route: 8,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 30.5m (100.1ft),  Skew: 30 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 23,  Length of Maximum Span: 25.9m (85.0ft),  Curb or Sidewalk Widths: Left: 0.6m (2.0ft),  Right: 0.6m (2.0ft),  Curb-To-Curb Width: 31.0m (101.7ft),  Out-to-Out Width: 33.5m (109.9ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Good,  Operating Rating: 52.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 11,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 33 0061L,  Location: 04-ALA-580-46.5-OAK (Lat: 37.827194,  Lng: -122.291861),  Route carried "on" structure: Interstate 580,  Year Built: 1955,  Year Reconstructed: 1962,  Status: Open,  Structure Length: 121.80m (399.61ft),  Average Daily Traffic: 220,000 (year 2009),  Truck Traffic: 3%,  Average Future Daily Traffic: 308,000 (year 2030),  Design Load: HS 20,  Features Intersected: UP RR,BNSF RY,AMTRAK,ETC
Minimum Vertical Clearance: 4.49m (14.73ft),  Kilometerpoint: 46.500,  Lanes on structure: 2,  Lanes under structure: 8,  Base Highway Network: Yes (Inventory Route: 5,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Skew: 9 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 55,  Length of Maximum Span: 37.2m (122.0ft),  Curb or Sidewalk Widths: Left: 0.8m (2.6ft),  Right: 0.8m (2.6ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 13.7m (44.9ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Satisfactory,  Operating Rating: 55.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 27.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 121.80m (399.61ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: May 11,  Critical Feature Inspection Date: April 10,  Bridge Improvement Cost: $26,048,000,  Roadway Improvement Cost: $5,209,000,  Total Project Cost: $43,760,000 ( Estimate for 2010),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 33 0061R,  Location: 04-ALA-580-46.5-OAK (Lat: 37.827056,  Lng: -122.290222),  Route carried "on" structure: Interstate 580,  Year Built: 1935,  Year Reconstructed: 2006,  Status: Open,  Structure Length: 112.41m (368.80ft),  Average Daily Traffic: 220,000 (year 2009),  Truck Traffic: 3%,  Average Future Daily Traffic: 308,000 (year 2030),  Design Load: H 15,  Features Intersected: UP RR,BNSF RY,AMTRAK,ETC
Minimum Vertical Clearance: 4.66m (15.29ft),  Kilometerpoint: 46.500,  Lanes on structure: 2,  Lanes under structure: 16,  Base Highway Network: Yes (Inventory Route: 5,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 10.0m (32.8ft),  Skew: 9 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 51,  Length of Maximum Span: 38.4m (126.0ft),  Curb or Sidewalk Widths: Left: 0.8m (2.6ft),  Right: 0.8m (2.6ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 10.0m (32.8ft)

Condition: Deck: Serious,  Superstructure: Fair,  Substructure: Good,  Operating Rating: 53.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 25.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 112.41m (368.80ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: May 11,  Critical Feature Inspection Date: April 10,  Bridge Improvement Cost: $18,690,000,  Roadway Improvement Cost: $3,738,000,  Total Project Cost: $31,399,000 ( Estimate for 2010),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 33 0088L,  Location: 04-ALA-880-25.5-OAK (Lat: 37.740722,  Lng: -122.196472),  Route carried "on" structure: City street ,  Year Built: 1996,  Status: Open,  Structure Length: 16.76m (54.99ft),  Average Daily Traffic: 19,000 (year 2007),  Truck Traffic: 2%,  Average Future Daily Traffic: 61,619 (year 2028),  Design Load: HS 20+Mod,  Features Intersected: INTERSTATE 880,  Facility Carried by Structure: HEGENBERGER RD WB
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 4,  Lanes under structure: 10,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 18.3m (60.0ft),  Skew: 5 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 65.5m (214.9ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 0.0m,  Curb-To-Curb Width: 17.8m (58.4ft),  Out-to-Out Width: 20.3m (66.6ft)

Condition: Deck: Satisfactory,  Superstructure: Very good,  Substructure: Good,  Operating Rating: 53.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Superior to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 10,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 33 0088R,  Location: 04-ALA-880-25.49-OAK (Lat: 37.740417,  Lng: -122.196250),  Route carried "on" structure: City street A028,  Year Built: 1976,  Status: Open,  Structure Length: 14.90m (48.88ft),  Average Daily Traffic: 19,000 (year 2010),  Truck Traffic: 2%,  Average Future Daily Traffic: 61,619 (year 2028),  Design Load: HS 20+Mod,  Features Intersected: INTERSTATE 880,  Facility Carried by Structure: HEGENBERGER RD EB
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 4,  Lanes under structure: 10,  Owner: State Highway Agency,  Approaching Roadway Width: 16.8m (55.1ft),  Skew: 5 degrees,  Material/Design: Prestressed concrete continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 37.2m (122.0ft),  Curb or Sidewalk Widths: Left: 0.0m,  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 16.8m (55.1ft),  Out-to-Out Width: 18.9m (62.0ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Satisfactory,  Operating Rating: 87.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 14.90m (48.88ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 10,  Bridge Improvement Cost: $2,816,000,  Roadway Improvement Cost: $563,000,  Total Project Cost: $4,730,000 ( Estimate for 2010),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 33 0105L,  Location: 04-ALA-013-5.01-OAK (Lat: 37.793861,  Lng: -122.182028),  Route carried "on" structure: State highway 13,  Year Built: 1966,  Status: Open,  Structure Length: 4.91m (16.11ft),  Average Daily Traffic: 47,000 (year 2009),  Truck Traffic: 2%,  Average Future Daily Traffic: 65,800 (year 2030),  Design Load: HS 20,  Features Intersected: CARSON STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 5.010,  Lanes on structure: 2,  Lanes under structure: 4,  Base Highway Network: Yes (,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Skew: 2 degrees,  Material/Design: Concrete continuous,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 24.7m (81.0ft),  Curb-To-Curb Width: 11.5m (37.7ft),  Out-to-Out Width: 12.1m (39.7ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 99.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 57.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 11,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 33 0105R,  Location: 04-ALA-013-5.01-OAK (Lat: 37.794056,  Lng: -122.181833),  Route carried "on" structure: State highway 13,  Year Built: 1966,  Status: Open,  Structure Length: 4.91m (16.11ft),  Average Daily Traffic: 47,000 (year 2009),  Truck Traffic: 2%,  Average Future Daily Traffic: 65,800 (year 2030),  Design Load: HS 20,  Features Intersected: CARSON STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 5.010,  Lanes on structure: 2,  Lanes under structure: 4,  Base Highway Network: Yes (,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Skew: 2 degrees,  Material/Design: Concrete continuous,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 24.7m (81.0ft),  Curb-To-Curb Width: 11.5m (37.7ft),  Out-to-Out Width: 12.1m (39.7ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Operating Rating: 99.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 57.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 11,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 33 0109,  Location: 04-ALA-185-8.64-OAK (Lat: 37.758319,  Lng: -122.185181),  Route carried "on" structure: State highway 185,  Year Built: 1969,  Status: Open,  Structure Length: 0.67m (2.20ft),  Average Daily Traffic: 25,000 (year 2009),  Truck Traffic: 1%,  Average Future Daily Traffic: 45,800 (year 2027),  Design Load: HS 20,  Features Intersected: ARROYO VIEJO
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 8.640,  Lanes on structure: 5,  Base Highway Network: Yes (Inventory Route: 1,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 21.2m (69.6ft),  Skew: 9 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb or Sidewalk Widths: Left: 2.6m (8.5ft),  Right: 4.5m (14.8ft),  Curb-To-Curb Width: 21.2m (69.6ft),  Out-to-Out Width: 28.5m (93.5ft)

Condition: Channel: Very good,  Culverts: Very good,  Operating Rating: 54.1 metric tons,  Inventory Rating: 32.4 metric tons,  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 48 months,  Inspection Date: December 10
Find on map >>   Show street view

Structure Number: 33 011,  Location: 04-ALA-880-24.74-OAK (Lat: 37.731694,  Lng: -122.188556),  Route carried "on" structure: City street A025,  Year Built: 1998,  Status: Open,  Structure Length: 9.30m (30.51ft),  Average Daily Traffic: 23,000 (year 2008),  Truck Traffic: 1%,  Average Future Daily Traffic: 16,431 (year 2028),  Design Load: HS 20+Mod,  Features Intersected: INTERSTATE 880,  Facility Carried by Structure: 98TH AVE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 24.740,  Lanes on structure: 6,  Lanes under structure: 8,  Owner: State Highway Agency,  Approaching Roadway Width: 35.5m (116.5ft),  Material/Design: Prestressed concrete continuous,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 47.8m (156.8ft),  Curb or Sidewalk Widths: Left: 3.0m (9.8ft),  Right: 0.0m,  Curb-To-Curb Width: 26.8m (87.9ft),  Out-to-Out Width: 35.5m (116.5ft)

Condition: Deck: Fair,  Superstructure: Very good,  Substructure: Good,  Operating Rating: 54.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 10,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 33 0113,  Location: 04-ALA-880-25.97-OAK (Lat: 37.746417,  Lng: -122.201444),  Route carried "on" structure: Interstate 880,  Year Built: 1948,  Year Reconstructed: 1963,  Status: Open,  Structure Length: 2.01m (6.59ft),  Average Daily Traffic: 199,000 (year 2009),  Truck Traffic: 7%,  Average Future Daily Traffic: 282,400 (year 2027),  Design Load: HS 20,  Features Intersected: ELMHURST CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 25.970,  Lanes on structure: 9,  Base Highway Network: Yes (Inventory Route: 8,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 18.5m (60.7ft),  Skew: 20 degrees,  Material/Design: Concrete continuous,  Design/Construction: Slab,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 7.9m (25.9ft),  Curb-To-Curb Width: 37.0m (121.4ft),  Out-to-Out Width: 38.7m (127.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Very good,  Operating Rating: 49.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 29.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 10,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 33 0131,  Location: 04-ALA-580-43.48-OAK (Lat: 37.810000,  Lng: -122.246667),  Route carried "on" structure: Interstate 580,  Year Built: 1962,  Status: Open,  Structure Length: 25.54m (83.79ft),  Average Daily Traffic: 182,000 (year 2009),  Truck Traffic: 1%,  Average Future Daily Traffic: 300,000 (year 2030),  Design Load: HS 20,  Features Intersected: LAKESHORE BL & GRAND AVE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 43.480,  Lanes on structure: 8,  Lanes under structure: 11,  Base Highway Network: Yes (Inventory Route: 5,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 42.1m (138.1ft),  Skew: 39 degrees,  Material/Design: Concrete continuous,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 7,  Number Of Approach Spans: 2,  Length of Maximum Span: 37.2m (122.0ft),  Curb-To-Curb Width: 41.5m (136.2ft),  Out-to-Out Width: 42.9m (140.7ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Good,  Operating Rating: 63.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 38.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 25.54m (83.79ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 11,  Bridge Improvement Cost: $11,045,000,  Roadway Improvement Cost: $2,209,000,  Total Project Cost: $18,555,000 ( Estimate for 2010),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 33 0132Y,  Location: 04-ALA-024-R4.43-OAK (Lat: 37.849472,  Lng: -122.239972),  Route carried "on" structure: State highway 24,  Year Built: 1934,  Status: Open,  Structure Length: 4.46m (14.63ft),  Average Daily Traffic: 1,050 (year 2010),  Truck Traffic: 2%,  Average Future Daily Traffic: 1,365 (year 2030),  Design Load: H 15,  Features Intersected: GOLDEN GATE AVE,  Facility Carried by Structure: BROADWAY
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.430,  Lanes on structure: 2,  Lanes under structure: 2,  Base Highway Network: Yes (,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 13.4m (44.0ft),  Skew: 2 degrees,  Material/Design: Concrete continuous,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 16.5m (54.1ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 13.4m (44.0ft),  Out-to-Out Width: 17.2m (56.4ft)

Condition: Deck: Fair,  Superstructure: Good,  Substructure: Good,  Operating Rating: 99.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 68.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present desirable criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 12,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 33 0134J,  Location: 04-ALA-980-1.68-OAK (Lat: 37.819589,  Lng: -122.270275),  Route carried "on" structure: Bypass Interstate 980,  Year Built: 1969,  Status: Open,  Structure Length: 3.72m (12.20ft),  Average Daily Traffic: 7,500 (year 1998),  Truck Traffic: 2%,  Average Future Daily Traffic: 7,753 (year 2026),  Design Load: HS 20,  Features Intersected: 30TH STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.680,  Lanes on structure: 2,  Lanes under structure: 2,  Base Highway Network: Yes (Inventory Route: 9,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Material/Design: Concrete continuous,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 18.9m (62.0ft),  Curb-To-Curb Width: 9.8m (32.2ft),  Out-to-Out Width: 10.4m (34.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 65.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 39.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of replacement,  Underclear: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 48 months,  Inspection Date: May 2008,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 33 0134T,  Location: 04-ALA-980-1.68-OAK (Lat: 37.819344,  Lng: -122.269017),  Route carried "on" structure: Bypass Interstate 980,  Year Built: 1969,  Status: Open,  Structure Length: 3.72m (12.20ft),  Average Daily Traffic: 6,600 (year 1998),  Truck Traffic: 2%,  Average Future Daily Traffic: 6,835 (year 2026),  Design Load: HS 20,  Features Intersected: 30TH STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.680,  Lanes on structure: 2,  Lanes under structure: 2,  Base Highway Network: Yes (Inventory Route: 9,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Material/Design: Concrete continuous,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 18.9m (62.0ft),  Curb-To-Curb Width: 9.8m (32.2ft),  Out-to-Out Width: 10.4m (34.1ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Operating Rating: 65.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 39.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of replacement,  Underclear: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 48 months,  Inspection Date: May 2008,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 33 0137,  Location: 04-ALA-880-29.69-OAK (Lat: 37.783333,  Lng: -122.241667),  Route carried "on" structure: City street ,  Year Built: 1997,  Status: Open,  Structure Length: 34.70m (113.85ft),  Average Daily Traffic: 5,000 (year 2005),  Truck Traffic: 1%,  Average Future Daily Traffic: 7,000 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: I 880,E 12TH ST,BARTD,RR,  Facility Carried by Structure: 16TH AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 10,  Owner: State Highway Agency,  Approaching Roadway Width: 9.9m (32.5ft),  Skew: 5 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 10,  Number Of Approach Spans: 3,  Length of Maximum Span: 51.8m (169.9ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 0.0m,  Curb-To-Curb Width: 9.9m (32.5ft),  Out-to-Out Width: 12.2m (40.0ft)

Condition: Deck: Fair,  Superstructure: Very good,  Substructure: Good,  Operating Rating: 54.0 metric tons,  Inventory Rating: 32.4 metric tons,  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 11,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 33 0139,  Location: 04-ALA-880-28.93-OAK (Lat: 37.776669,  Lng: -122.235003),  Route carried "on" structure: City street A321,  Year Built: 1947,  Status: Open,  Structure Length: 15.33m (50.30ft),  Average Daily Traffic: 5,800 (year 1998),  Truck Traffic: 1%,  Average Future Daily Traffic: 15,456 (year 2029),  Design Load: HS 20,  Features Intersected: INTERSTATE 880,  Facility Carried by Structure: 23RD AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 8,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 5 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Number Of Approach Spans: 3,  Length of Maximum Span: 33.5m (109.9ft),  Curb or Sidewalk Widths: Left: 0.6m (2.0ft),  Right: 1.6m (5.2ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 9.8m (32.2ft)

Condition: Deck: Fair,  Superstructure: Good,  Substructure: Good,  Operating Rating: 63.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 36.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of replacement,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 15.33m (50.30ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: Febuary 11,  Critical Feature Inspection Date: March 11,  Bridge Improvement Cost: $1,505,000,  Roadway Improvement Cost: $301,000,  Total Project Cost: $2,528,000 ( Estimate for 2010),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 33 0141,  Location: 04-ALA-880-28.69-OAK (Lat: 37.775000,  Lng: -122.231667),  Route carried "on" structure: City street A258,  Year Built: 1947,  Status: Open,  Structure Length: 18.56m (60.89ft),  Average Daily Traffic: 11,300 (year 1998),  Truck Traffic: 2%,  Average Future Daily Traffic: 12,531 (year 2033),  Design Load: HS 20,  Features Intersected: INTERSTATE 880,  Facility Carried by Structure: 29TH AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 8,  Owner: State Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 11,  Length of Maximum Span: 19.2m (63.0ft),  Curb or Sidewalk Widths: Left: 1.7m (5.6ft),  Right: 1.7m (5.6ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 11.2m (36.7ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Operating Rating: 56.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 34.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of corrective action,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 18.56m (60.89ft),  Designated Inspection Frequency: Every 48 months,  Inspection Date: Febuary 11,  Bridge Improvement Cost: $2,012,000,  Roadway Improvement Cost: $402,000,  Total Project Cost: $3,380,000 ( Estimate for 2010),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 33 0142,  Location: 04-ALA-880-26.53-OAK (Lat: 37.753194,  Lng: -122.207403),  Route carried "on" structure: Interstate 880,  Year Built: 1948,  Year Reconstructed: 1963,  Status: Open,  Structure Length: 5.18m (16.99ft),  Average Daily Traffic: 199,000 (year 2009),  Truck Traffic: 7%,  Average Future Daily Traffic: 288,095 (year 2033),  Design Load: HS 20,  Features Intersected: DAMON SLOUGH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 26.530,  Lanes on structure: 9,  Base Highway Network: Yes (Inventory Route: 8,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 18.6m (61.0ft),  Skew: 30 degrees,  Material/Design: Concrete continuous,  Design/Construction: Slab,  Number Of Spans In Main Unit: 7,  Length of Maximum Span: 7.9m (25.9ft),  Curb-To-Curb Width: 37.1m (121.7ft),  Out-to-Out Width: 38.6m (126.6ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 43.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 25.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 11,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 33 0142K,  Location: 04-ALA-880-26.53-OAK (Lat: 37.753083,  Lng: -122.207694),  Route carried "on" structure: Ramp Interstate 880,  Year Built: 1948,  Status: Open,  Structure Length: 5.18m (16.99ft),  Average Daily Traffic: 3,300 (year 1998),  Truck Traffic: 10%,  Average Future Daily Traffic: 7,213 (year 2029),  Design Load: HS 20,  Features Intersected: DAMON SLOUGH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 26.530,  Lanes on structure: 1,  Owner: State Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Material/Design: Concrete continuous,  Design/Construction: Slab,  Number Of Spans In Main Unit: 7,  Length of Maximum Span: 7.9m (25.9ft),  Curb or Sidewalk Widths: Left: 1.3m (4.3ft),  Right: 0.6m (2.0ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 10.4m (34.1ft)

Condition: Deck: Poor,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Good,  Operating Rating: 54.0 metric tons,  Inventory Rating: 32.4 metric tons,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present desirable criteria,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 11,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 33 0142S,  Location: 04-ALA-880-26.53-OAK (Lat: 37.753375,  Lng: -122.207014),  Route carried "on" structure: Ramp Interstate 880,  Year Built: 1968,  Status: Open,  Structure Length: 5.21m (17.09ft),  Average Daily Traffic: 1,250 (year 1998),  Truck Traffic: 10%,  Average Future Daily Traffic: 4,152 (year 2029),  Design Load: HS 20,  Features Intersected: DAMON SLOUGH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 26.530,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Skew: 1 degrees,  Material/Design: Concrete continuous,  Design/Construction: Slab,  Number Of Spans In Main Unit: 7,  Length of Maximum Span: 7.9m (25.9ft),  Curb or Sidewalk Widths: Left: 0.6m (2.0ft),  Right: 0.6m (2.0ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 10.4m (34.1ft)

Condition: Deck: Fair,  Superstructure: Good,  Substructure: Good,  Channel: Very good,  Operating Rating: 56.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 11,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 33 0143,  Location: 04-ALA-880-27.23-OAK (Lat: 37.761431,  Lng: -122.214639),  Route carried "on" structure: Interstate 880,  Year Built: 1948,  Year Reconstructed: 1968,  Status: Open,  Structure Length: 2.80m (9.19ft),  Average Daily Traffic: 221,000 (year 2009),  Truck Traffic: 11%,  Average Future Daily Traffic: 291,564 (year 2033),  Design Load: HS 20,  Features Intersected: EAST CREEK SLOUGH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 27.230,  Lanes on structure: 9,  Base Highway Network: Yes (Inventory Route: 8,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 22.3m (73.2ft),  Skew: 20 degrees,  Material/Design: Concrete continuous,  Design/Construction: Slab,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 7.9m (25.9ft),  Curb-To-Curb Width: 40.7m (133.5ft),  Out-to-Out Width: 42.2m (138.5ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Fair,  Operating Rating: 46.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 27.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 11,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 33 0146S,  Location: 04-ALA-880-27.7-OAK (Lat: 37.770000,  Lng: -122.220000),  Route carried "on" structure: Ramp Interstate 880,  Year Built: 1950,  Status: Open,  Structure Length: 5.21m (17.09ft),  Average Daily Traffic: 8,500 (year 1998),  Truck Traffic: 2%,  Average Future Daily Traffic: 14,941 (year 2029),  Design Load: HS 20,  Features Intersected: SR 77 & S880-N77 CONNCTR
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 27.700,  Lanes on structure: 1,  Lanes under structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 6.4m (21.0ft),  Skew: 9 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 22.3m (73.2ft),  Curb or Sidewalk Widths: Left: 0.6m (2.0ft),  Right: 0.6m (2.0ft),  Curb-To-Curb Width: 6.4m (21.0ft),  Out-to-Out Width: 8.1m (26.6ft)

Condition: Deck: Serious,  Superstructure: Good,  Substructure: Good,  Operating Rating: 54.0 metric tons,  Inventory Rating: 32.4 metric tons,  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 11,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 33 0147,  Location: 04-ALA-013-5.39-OAK (Lat: 37.798500,  Lng: -122.185222),  Route carried "on" structure: City street A323,  Year Built: 1966,  Status: Open,  Structure Length: 9.69m (31.79ft),  Average Daily Traffic: 10,000 (year 2009),  Truck Traffic: 3%,  Average Future Daily Traffic: 14,000 (year 2030),  Design Load: HS 20,  Features Intersected: STATE ROUTE 13,  Facility Carried by Structure: REDWOOD ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 4,  Lanes under structure: 4,  Owner: State Highway Agency,  Approaching Roadway Width: 17.1m (56.1ft),  Skew: 25 degrees,  Material/Design: Concrete continuous,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 33.5m (109.9ft),  Curb or Sidewalk Widths: Left: 2.1m (6.9ft),  Right: 2.1m (6.9ft),  Curb-To-Curb Width: 20.9m (68.6ft),  Out-to-Out Width: 26.8m (87.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 59.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 35.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Better than present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 11,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 33 0149,  Location: 04-ALA-880-28.98-OAK (Lat: 37.776667,  Lng: -122.235000),  Route carried "on" structure: City street A321,  Year Built: 1947,  Status: Open,  Structure Length: 28.62m (93.90ft),  Average Daily Traffic: 11,500 (year 2000),  Truck Traffic: 1%,  Average Future Daily Traffic: 15,456 (year 2029),  Design Load: HS 20,  Features Intersected: INTERSTATE 880,  Facility Carried by Structure: 23RD AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 8,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 6 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Number Of Approach Spans: 10,  Length of Maximum Span: 42.1m (138.1ft),  Curb or Sidewalk Widths: Left: 0.6m (2.0ft),  Right: 0.6m (2.0ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 9.1m (29.9ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Good,  Operating Rating: 65.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 41.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 28.62m (93.90ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: Febuary 11,  Critical Feature Inspection Date: March 11,  Bridge Improvement Cost: $2,530,000,  Roadway Improvement Cost: $506,000,  Total Project Cost: $4,250,000 ( Estimate for 2010),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 33 0159,  Location: 04-ALA-013-7.4-OAK (Lat: 37.821639,  Lng: -122.207250),  Route carried "on" structure: City street A024,  Year Built: 1956,  Status: Open,  Structure Length: 4.05m (13.29ft),  Average Daily Traffic: 22,979 (year 2009),  Truck Traffic: 2%,  Average Future Daily Traffic: 32,170 (year 2030),  Design Load: HS 20,  Features Intersected: STATE ROUTE 13,  Facility Carried by Structure: PARK BLVD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 4,  Lanes under structure: 4,  Owner: State Highway Agency,  Approaching Roadway Width: 17.7m (58.1ft),  Skew: 21 degrees,  Material/Design: Concrete continuous,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 22.6m (74.1ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 15.8m (51.8ft),  Out-to-Out Width: 21.3m (69.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 99.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 59.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 4.05m (13.29ft),  Designated Inspection Frequency: Every 48 months,  Inspection Date: March 11,  Bridge Improvement Cost: $865,000,  Roadway Improvement Cost: $173,000,  Total Project Cost: $1,453,000 ( Estimate for 2010),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 33 016,  Location: 04-ALA-013-7.76-OAK (Lat: 37.826028,  Lng: -122.210861),  Route carried "on" structure: City street A334,  Year Built: 1956,  Status: Open,  Structure Length: 3.32m (10.89ft),  Average Daily Traffic: 8,000 (year 2009),  Truck Traffic: 3%,  Average Future Daily Traffic: 11,200 (year 2030),  Design Load: HS 20,  Features Intersected: STATE ROUTE 13,  Facility Carried by Structure: LA SALLE AVE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 4,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Concrete continuous,  Design/Construction: Slab,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 15.8m (51.8ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 12.7m (41.7ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 73.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 53.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of corrective action,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 3.32m (10.89ft),  Designated Inspection Frequency: Every 48 months,  Inspection Date: March 11,  Bridge Improvement Cost: $422,000,  Roadway Improvement Cost: $84,000,  Total Project Cost: $708,000 ( Estimate for 2010),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 33 0162,  Location: 04-ALA-013-9.07-OAK (Lat: 37.841611,  Lng: -122.224694),  Route carried "on" structure: State highway 13,  Year Built: 1951,  Status: Open,  Structure Length: 3.63m (11.91ft),  Average Daily Traffic: 136,000 (year 2009),  Truck Traffic: 2%,  Average Future Daily Traffic: 190,400 (year 2030),  Design Load: HS 20,  Features Intersected: BROADWAY TERRACE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 9.070,  Lanes on structure: 4,  Lanes under structure: 2,  Base Highway Network: Yes (,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 15.8m (51.8ft),  Skew: 25 degrees,  Material/Design: Concrete continuous,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 17.4m (57.1ft),  Curb or Sidewalk Widths: Left: 0.6m (2.0ft),  Right: 0.6m (2.0ft),  Curb-To-Curb Width: 14.6m (47.9ft),  Out-to-Out Width: 19.4m (63.6ft)

Condition: Deck: Fair,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Operating Rating: 67.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 40.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.63m (11.91ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 11,  Bridge Improvement Cost: $704,000,  Roadway Improvement Cost: $140,000,  Total Project Cost: $1,182,000 ( Estimate for 2010),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 33 0164K,  Location: 04-ALA-013-R9.16-OAK (Lat: 37.842556,  Lng: -122.225917),  Route carried "on" structure: Ramp State highway 13,  Year Built: 1951,  Status: Open,  Structure Length: 0.76m (2.49ft),  Average Daily Traffic: 5,000 (year 2009),  Truck Traffic: 2%,  Average Future Daily Traffic: 7,000 (year 2030),  Design Load: H 20,  Features Intersected: LAKE TEMESCAL PARK ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 9.160,  Lanes on structure: 1,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 4.9m (16.1ft),  Material/Design: Concrete,  Design/Construction: Arch - Deck,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.6m (24.9ft),  Curb-To-Curb Width: 6.9m (22.6ft),  Out-to-Out Width: 6.9m (22.6ft)

Condition: Superstructure: Good,  Substructure: Good,  Operating Rating: 53.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 11,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 33 0187Y,  Location: 04-ALA-077-.18-OAK (Lat: 37.770000,  Lng: -122.220278),  Route carried "on" structure: City street ,  Year Built: 1950,  Status: Open,  Structure Length: 2.65m (8.69ft),  Average Daily Traffic: 20 (year 1998),  Average Future Daily Traffic: 26 (year 2028),  Design Load: HS 20,  Features Intersected: ROUTE 77,  Facility Carried by Structure: CLOROX
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Lanes under structure: 4,  Owner: State Highway Agency,  Approaching Roadway Width: 3.7m (12.1ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 14.9m (48.9ft),  Curb or Sidewalk Widths: Left: 0.7m (2.3ft),  Right: 1.2m (3.9ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 9.4m (30.8ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 87.9 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 59.8 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: High priority of corrective action,  Designated Inspection Frequency: Every 48 months,  Inspection Date: December 10,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 33 0198,  Location: 04-ALA-880-31.07-OAK (Lat: 37.795694,  Lng: -122.267694),  Route carried "on" structure: Interstate 880,  Year Built: 1958,  Year Reconstructed: 1985,  Status: Open,  Structure Length: 29.11m (95.51ft),  Average Daily Traffic: 203,000 (year 2009),  Truck Traffic: 14%,  Average Future Daily Traffic: 246,676 (year 2033),  Design Load: HS 20,  Features Intersected: JACKSON, MADISON, OAK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 31.070,  Lanes on structure: 9,  Lanes under structure: 8,  Base Highway Network: Yes (Inventory Route: 8,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 35.4m (116.1ft),  Skew: 20 degrees,  Material/Design: Concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 13,  Length of Maximum Span: 23.2m (76.1ft),  Curb or Sidewalk Widths: Left: 0.0m,  Right: 0.6m (2.0ft),  Curb-To-Curb Width: 39.4m (129.3ft),  Out-to-Out Width: 40.8m (133.9ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Good,  Operating Rating: 59.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 35.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Better than present minimum criteria,  Underclear: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 29.11m (95.51ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 11,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 33 02,  Location: 04-ALA-880-31.36-OAK (Lat: 37.798861,  Lng: -122.276194),  Route carried "on" structure: Interstate 880,  Year Built: 1953,  Year Reconstructed: 1984,  Status: Open,  Structure Length: 127.36m (417.85ft),  Average Daily Traffic: 203,000 (year 2009),  Truck Traffic: 14%,  Average Future Daily Traffic: 246,676 (year 2033),  Design Load: HS 20,  Features Intersected: RT260,MLK,MKT,BRDWY,WASH
Minimum Vertical Clearance: 5.15m (16.90ft),  Kilometerpoint: 31.360,  Lanes on structure: 8,  Lanes under structure: 40,  Base Highway Network: Yes (Inventory Route: 8,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 39.6m (129.9ft),  Skew: 30 degrees,  Material/Design: Concrete continuous,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 54,  Length of Maximum Span: 48.8m (160.1ft),  Curb-To-Curb Width: 32.0m (105.0ft),  Out-to-Out Width: 36.0m (118.1ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Good,  Operating Rating: 49.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 30.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 127.36m (417.85ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 11,  Bridge Improvement Cost: $58,450,000,  Roadway Improvement Cost: $11,690,000,  Total Project Cost: $98,196,000 ( Estimate for 2010),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 33 0227K,  Location: 04-ALA-013-8.32-OAK (Lat: 37.832889,  Lng: -122.217583),  Route carried "on" structure: City street A331,  Year Built: 1964,  Status: Open,  Structure Length: 4.33m (14.21ft),  Average Daily Traffic: 15,000 (year 2009),  Truck Traffic: 2%,  Average Future Daily Traffic: 21,000 (year 2030),  Design Load: H 20,  Features Intersected: S13-MORAGA AV OFF RAMP,  Facility Carried by Structure: MORAGA AVENUE WB
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Lanes under structure: 1,  Owner: State Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Material/Design: Concrete continuous,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 18.3m (60.0ft),  Curb or Sidewalk Widths: Left: 1.8m (5.9ft),  Right: 0.6m (2.0ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 11.3m (37.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 99.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 58.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of replacement,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Meets minimum limits,  Designated Inspection Frequency: Every 48 months,  Inspection Date: March 11,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 33 0227L,  Location: 04-ALA-013-8.28-OAK (Lat: 37.832528,  Lng: -122.216944),  Route carried "on" structure: State highway 13,  Year Built: 1964,  Status: Open,  Structure Length: 7.99m (26.21ft),  Average Daily Traffic: 57,000 (year 2009),  Truck Traffic: 2%,  Average Future Daily Traffic: 79,800 (year 2030),  Design Load: HS 20+Mod,  Features Intersected: MORAGA AVE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 8.280,  Lanes on structure: 2,  Lanes under structure: 5,  Base Highway Network: Yes (,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 11.3m (37.1ft),  Skew: 3 degrees,  Material/Design: Concrete continuous,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 36.3m (119.1ft),  Curb-To-Curb Width: 11.3m (37.1ft),  Out-to-Out Width: 12.1m (39.7ft)

Condition: Deck: Good,  Superstructure: Fair,  Substructure: Good,  Operating Rating: 82.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 49.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Better than present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 11,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 33 0227R,  Location: 04-ALA-013-8.27-OAK (Lat: 37.832389,  Lng: -122.216500),  Route carried "on" structure: State highway 13,  Year Built: 1964,  Status: Open,  Structure Length: 7.68m (25.20ft),  Average Daily Traffic: 57,000 (year 2009),  Truck Traffic: 3%,  Average Future Daily Traffic: 79,800 (year 2030),  Design Load: HS 20,  Features Intersected: MORAGA AVE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 8.270,  Lanes on structure: 3,  Lanes under structure: 5,  Base Highway Network: Yes (,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Skew: 3 degrees,  Material/Design: Concrete continuous,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 35.1m (115.2ft),  Curb or Sidewalk Widths: Left: 0.0m,  Right: 0.6m (2.0ft),  Curb-To-Curb Width: 12.5m (41.0ft),  Out-to-Out Width: 13.8m (45.3ft)

Condition: Deck: Good,  Superstructure: Fair,  Substructure: Good,  Operating Rating: 99.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 55.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Meets minimum limits,  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 11,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 33 0247,  Location: 04-ALA-013-6.47-OAK (Lat: 37.810583,  Lng: -122.197639),  Route carried "on" structure: City street A342,  Year Built: 1956,  Status: Open,  Structure Length: 3.29m (10.79ft),  Average Daily Traffic: 15,000 (year 2011),  Truck Traffic: 5%,  Average Future Daily Traffic: 17,000 (year 2030),  Design Load: HS 20,  Features Intersected: STATE ROUTE 13,  Facility Carried by Structure: LINCOLN AVE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 4,  Lanes under structure: 4,  Owner: State Highway Agency,  Approaching Roadway Width: 17.7m (58.1ft),  Skew: 20 degrees,  Material/Design: Concrete continuous,  Design/Construction: Slab,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 16.5m (54.1ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 15.8m (51.8ft),  Out-to-Out Width: 21.3m (69.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 73.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 43.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Meets minimum limits,  Length Of Structure Improvement: 3.29m (10.79ft),  Designated Inspection Frequency: Every 48 months,  Inspection Date: March 11,  Bridge Improvement Cost: $702,000,  Roadway Improvement Cost: $140,000,  Total Project Cost: $1,179,000 ( Estimate for 2010),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 33 0280L,  Location: 04-ALA-580-45.74-OAK (Lat: 37.826944,  Lng: -122.280000),  Route carried "on" structure: Interstate 580,  Year Built: 1961,  Status: Open,  Structure Length: 32.64m (107.09ft),  Average Daily Traffic: 220,000 (year 2009),  Truck Traffic: 3%,  Average Future Daily Traffic: 308,000 (year 2030),  Design Load: HS 20,  Features Intersected: SAN PBLO, ADLN, MGNO,PER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 45.740,  Lanes on structure: 5,  Lanes under structure: 14,  Base Highway Network: Yes (Inventory Route: 5,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 20.1m (65.9ft),  Skew: 9 degrees,  Material/Design: Concrete continuous,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 12,  Length of Maximum Span: 36.9m (121.1ft),  Curb-To-Curb Width: 20.1m (65.9ft),  Out-to-Out Width: 20.9m (68.6ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Operating Rating: 58.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 35.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 32.64m (107.09ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 11,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 33 0280R,  Location: 04-ALA-580-45.74-OAK (Lat: 37.827222,  Lng: -122.279722),  Route carried "on" structure: Interstate 580,  Year Built: 1961,  Status: Open,  Structure Length: 32.13m (105.41ft),  Average Daily Traffic: 220,000 (year 2009),  Truck Traffic: 3%,  Average Future Daily Traffic: 308,000 (year 2030),  Design Load: HS 20,  Features Intersected: ADELINE, SAN PABLO,PERAL
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 45.740,  Lanes on structure: 4,  Lanes under structure: 14,  Base Highway Network: Yes (Inventory Route: 5,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 20.1m (65.9ft),  Skew: 9 degrees,  Material/Design: Concrete continuous,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 12,  Length of Maximum Span: 36.9m (121.1ft),  Curb-To-Curb Width: 20.1m (65.9ft),  Out-to-Out Width: 20.9m (68.6ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 73.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 44.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 11,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous

Parts: 1, 2, 3, 4, 5, 6, 7, 8, 9

Jump to a detailed profile or search site with Google Custom Search
Business Search - 14 Million verified businesses
Search for: near: 

Discuss this city on our hugely popular California forum

Back to: Oakland, CA, California, All US cities.


City-data.com does not guarantee the accuracy or timeliness of any information on this site.  Use at your own risk.
Some parts © 2013 Advameg, Inc.