National Bridge Inventory (NBI) Statistics
Number of bridges: 13
Total length: 20 meters (66ft)
Total costs: $19,500,000
Total average daily traffic: 5,260
Total average daily truck traffic: 156
Total future (year 2026) average daily traffic: 7,784
National Bridge Inventory (NBI) Registered Bridges for Pittsburg

New bridges - Historical Statistics

  • Before 1900: 2
  • 1900-1909: 1
  • 1910-1919: 0
  • 1920-1929: 0
  • 1930-1939: 1
  • 1940-1949: 0
  • 1950-1959: 2
  • 1960-1969: 2
  • 1970-1979: 1
  • 1980-1989: 1
  • 1990-1999: 3

Reconstructed bridges - Historical Statistics

  • 1960-1969: 1
  • 1970-1979: 0
  • 1980-1989: 1
  • 1990-1999: 1

Bridge Condition - Deck

Bridge Condition - Superstructure

Bridge Condition - Substructure

Bridge Condition - Channel

Bridge Condition - Culverts

Find on map >>

Structure Number: 210007000032,  Location: 2.5 MI N OF CLARKSVILLETL (Lat: 45.046997,  Lng: -71.442022),  Route carried "on" structure: US 3,  Year Built: 1976,  Status: Open,  Structure Length: 2.87m (9.42ft),  Average Daily Traffic: 1,400 (year 2005),  Truck Traffic: 4%,  Average Future Daily Traffic: 2,072 (year 2026),  Design Load: HS 20,  Features Intersected: INDIAN STREAM
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.016,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 27.4m (89.9ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 9.8m (32.2ft),  Out-to-Out Width: 11.0m (36.1ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 45.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.87m (9.42ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2008,  Bridge Improvement Cost: $1,000,000,  Roadway Improvement Cost: $100,000,  Total Project Cost: $1,500,000 ( Estimate for 2008),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 210008800037,  Location: SOUTH OF U.S.RT.3 (Lat: 45.049256,  Lng: -71.392058),  Route carried "on" structure: Other road OLDRD,  Year Built: 1876,  Status: Closed,  Structure Length: 2.71m (8.89ft),  Features Intersected: CONNECTICUT RIVER,  Facility Carried by Structure: BYPASSED HISTORIC
Minimum Vertical Clearance: 3.66m (12.01ft),  Kilometerpoint: 0.002,  Lanes on structure: 1,  Owner: City or Municipal Highway Agency,  Material/Design: Wood or Timber,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 22.3m (73.2ft),  Curb-To-Curb Width: 4.5m (14.8ft),  Out-to-Out Width: 4.9m (16.1ft)

Condition: Deck: Imminent failure,  Superstructure: Failed,  Substructure: Imminent failure,  Channel: Satisfactory,  Waterway Adequacy: Better than present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 2.71m (8.89ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2006,  Bridge Improvement Cost: $1,000,000,  Roadway Improvement Cost: $100,000,  Total Project Cost: $1,500,000 ( Estimate for 2008),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>

Structure Number: 210009900034,  Location: 0.2 MI FROM US RT 3 (Lat: 45.049964,  Lng: -71.375456),  Route carried "on" structure: City street ,  Year Built: 1938,  Status: Posted for load,  Structure Length: 1.16m (3.81ft),  Average Daily Traffic: 10 (year 2000),  Truck Traffic: 4%,  Average Future Daily Traffic: 15 (year 2026),  Features Intersected: DAM SPILLWAY,  Facility Carried by Structure: MURPHY DAM ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.306,  Lanes on structure: 2,  Owner: State Agenciy,  Approaching Roadway Width: 4.9m (16.1ft),  Material/Design: Steel,  Design/Construction: Girder and Floorbeam System,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.4m (30.8ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 5.2m (17.1ft),  Out-to-Out Width: 6.2m (20.3ft)

Condition: Deck: Fair,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 13.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 6.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: High priority of replacement,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 0.1 - 9.9% below),  Length Of Structure Improvement: 1.16m (3.81ft),  Designated Inspection Frequency: Every 8 months,  Critical Feature Inspection Frequency: Every 8 months,  Inspection Date: April 2008,  Critical Feature Inspection Date: April 2008,  Bridge Improvement Cost: $1,000,000,  Roadway Improvement Cost: $100,000,  Total Project Cost: $1,500,000 ( Estimate for 2008),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 210013000058,  Location: 5.0 MI EAST NH145 (Lat: 45.085053,  Lng: -71.198611),  Route carried "on" structure: US 3,  Year Built: 1996,  Status: Open,  Structure Length: 2.56m (8.40ft),  Average Daily Traffic: 1,300 (year 2005),  Average Future Daily Traffic: 1,924 (year 2026),  Design Load: HS 25,  Features Intersected: PERRY STREAM
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 24.4m (80.1ft),  Curb or Sidewalk Widths: Left: 0.1m (0.3ft),  Right: 0.1m (0.3ft),  Curb-To-Curb Width: 8.9m (29.2ft),  Out-to-Out Width: 10.0m (32.8ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Very good,  Channel: Good,  Operating Rating: 78.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 47.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.56m (8.40ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2008,  Bridge Improvement Cost: $1,000,000,  Roadway Improvement Cost: $100,000,  Total Project Cost: $1,500,000 ( Estimate for 2008),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 210013000059,  Location: 5.0 MI EAST OF RTE 145 (Lat: 45.085053,  Lng: -71.319903),  Route carried "on" structure: Other road 3,  Year Built: 1996,  Status: Open,  Structure Length: 2.56m (8.40ft),  Truck Traffic: 4%,  Design Load: H 10,  Features Intersected: PERRY STREAM,  Facility Carried by Structure: SNOWMOBILE TRAIL
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 16.608,  Lanes on structure: 1,  Owner: State Highway Agency,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 24.4m (80.1ft),  Curb or Sidewalk Widths: Left: 0.1m (0.3ft),  Right: 0.1m (0.3ft),  Curb-To-Curb Width: 4.1m (13.5ft),  Out-to-Out Width: 4.9m (16.1ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Very good,  Channel: Good,  Operating Rating: 39.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 23.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.56m (8.40ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: May 2008,  Critical Feature Inspection Date: June 2004,  Bridge Improvement Cost: $1,000,000,  Roadway Improvement Cost: $100,000,  Total Project Cost: $1,500,000 ( Estimate for 2008),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 210013100058,  Location: 5.0 MI EAST NH145 (Lat: 45.189739,  Lng: -71.190053),  Route carried "on" structure: US 3,  Year Built: 1996,  Status: Open,  Structure Length: 0.85m (2.79ft),  Average Daily Traffic: 1,300 (year 2005),  Truck Traffic: 4%,  Average Future Daily Traffic: 1,924 (year 2026),  Design Load: HS 25,  Features Intersected: PERRY STREAM OVERFLOW
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 16.673,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Concrete,  Design/Construction: Frame,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.3m (24.0ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 9.9m (32.5ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Good,  Operating Rating: 56.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 40.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.85m (2.79ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2008,  Bridge Improvement Cost: $1,000,000,  Roadway Improvement Cost: $100,000,  Total Project Cost: $1,500,000 ( Estimate for 2008),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 210013400057,  Location: 0.2 MI FROM US RTE 3 (Lat: 45.084161,  Lng: -71.313372),  Route carried "on" structure: Other road ,  Year Built: 1860,  Year Reconstructed: 1991,  Status: Open,  Structure Length: 2.38m (7.81ft),  Average Daily Traffic: 110 (year 2005),  Truck Traffic: 4%,  Average Future Daily Traffic: 163 (year 2026),  Features Intersected: PERRY STREAM,  Facility Carried by Structure: HILL ROAD
Minimum Vertical Clearance: 2.80m (9.19ft),  Kilometerpoint: 4.571,  Lanes on structure: 1,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 16.8m (55.1ft),  Curb-To-Curb Width: 3.2m (10.5ft),  Out-to-Out Width: 5.6m (18.4ft)

Condition: Deck: Good,  Superstructure: Fair,  Substructure: Poor,  Channel: Fair,  Operating Rating: 39.0 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 25.4 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Meets minimum limits,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: High priority of corrective action,  Length Of Structure Improvement: 2.38m (7.81ft),  Designated Inspection Frequency: Every 12 months,  Inspection Date: October 2007,  Bridge Improvement Cost: $1,000,000,  Roadway Improvement Cost: $100,000,  Total Project Cost: $1,500,000 ( Estimate for 2008),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>

Structure Number: 21001380005,  Location: 3.5MILE N OF PITTSBURGVIL (Lat: 45.072250,  Lng: -71.304950),  Route carried "on" structure: Other road OLDRD,  Year Built: 1900,  Year Reconstructed: 1960,  Status: Closed,  Structure Length: 1.55m (5.09ft),  Features Intersected: PERRY STREAM,  Facility Carried by Structure: BYPASSED HISTORIC
Minimum Vertical Clearance: 2.74m (8.99ft),  Kilometerpoint: 0.002,  Lanes on structure: 1,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 4.0m (13.1ft),  Material/Design: Wood or Timber,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 14.0m (45.9ft),  Curb-To-Curb Width: 4.0m (13.1ft),  Out-to-Out Width: 4.0m (13.1ft)

Condition: Deck: Imminent failure,  Superstructure: Imminent failure,  Substructure: Serious,  Channel: Satisfactory,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 1.55m (5.09ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2006,  Bridge Improvement Cost: $1,000,000,  Roadway Improvement Cost: $100,000,  Total Project Cost: $1,500,000 ( Estimate for 2008),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>

Structure Number: 210013800051,  Location: 0.5 MI FROM US RTE 3 (Lat: 45.072506,  Lng: -71.305528),  Route carried "on" structure: Other road ,  Year Built: 1984,  Status: Open,  Structure Length: 1.52m (4.99ft),  Average Daily Traffic: 20 (year 1984),  Truck Traffic: 4%,  Average Future Daily Traffic: 30 (year 2026),  Features Intersected: PERRY STREAM,  Facility Carried by Structure: RIVER ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.625,  Lanes on structure: 1,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Skew: 3 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 14.0m (45.9ft),  Curb-To-Curb Width: 3.2m (10.5ft),  Out-to-Out Width: 4.9m (16.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 29.9 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 22.7 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.52m (4.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2006,  Bridge Improvement Cost: $1,000,000,  Roadway Improvement Cost: $100,000,  Total Project Cost: $1,500,000 ( Estimate for 2008),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>

Structure Number: 210017600088,  Location: 11.4 MI S CANADIAN BORDER (Lat: 45.127883,  Lng: -71.227544),  Route carried "on" structure: US 3,  Year Built: 1951,  Status: Open,  Structure Length: 0.55m (1.80ft),  Average Daily Traffic: 280 (year 2005),  Truck Traffic: 4%,  Average Future Daily Traffic: 414 (year 2026),  Design Load: H 20,  Features Intersected: COON BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 26.635,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 5.5m (18.0ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 36.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 21.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.55m (1.80ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2008,  Bridge Improvement Cost: $1,000,000,  Roadway Improvement Cost: $100,000,  Total Project Cost: $1,500,000 ( Estimate for 2008)
Find on map >>

Structure Number: 210018700093,  Location: 10.15 MI S CANADIAN LINE (Lat: 45.134703,  Lng: -71.206575),  Route carried "on" structure: US 3,  Year Built: 1958,  Year Reconstructed: 2001,  Status: Open,  Structure Length: 0.63m (2.07ft),  Average Daily Traffic: 280 (year 2005),  Truck Traffic: 4%,  Average Future Daily Traffic: 414 (year 2026),  Design Load: H 20,  Features Intersected: BIG BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 28.357,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 1 degrees,  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 5.5m (18.0ft),  Curb-To-Curb Width: 10.4m (34.1ft),  Out-to-Out Width: 11.5m (37.7ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 97.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 58.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.63m (2.07ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2007,  Bridge Improvement Cost: $1,000,000,  Roadway Improvement Cost: $100,000,  Total Project Cost: $1,500,000 ( Estimate for 2008),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 21001960013,  Location: 17.4 MI E OF ROUTE 145 (Lat: 45.189725,  Lng: -71.190053),  Route carried "on" structure: US 3,  Year Built: 1961,  Status: Open,  Structure Length: 0.73m (2.40ft),  Average Daily Traffic: 280 (year 2005),  Truck Traffic: 4%,  Average Future Daily Traffic: 414 (year 2026),  Design Load: HS 20,  Features Intersected: CONNECTICUT RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 36.709,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.3m (24.0ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 32.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 20.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.73m (2.40ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2008,  Bridge Improvement Cost: $1,000,000,  Roadway Improvement Cost: $100,000,  Total Project Cost: $1,500,000 ( Estimate for 2008)
Find on map >>

Structure Number: 21001970012,  Location: 6.2 MI S CANADIAN LINE (Lat: 45.174869,  Lng: -71.187050),  Route carried "on" structure: US 3,  Year Built: 1960,  Status: Open,  Structure Length: 0.42m (1.38ft),  Average Daily Traffic: 280 (year 2005),  Truck Traffic: 4%,  Average Future Daily Traffic: 414 (year 2026),  Design Load: H 20,  Features Intersected: WEST INLET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 34.633,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 4.2m (13.8ft)

Condition: Channel: Good,  Culverts: Fair,  Operating Rating: 39.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 23.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.42m (1.38ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2008,  Bridge Improvement Cost: $1,000,000,  Roadway Improvement Cost: $100,000,  Total Project Cost: $1,500,000 ( Estimate for 2008)

Discuss this city on our hugely popular New Hampshire forum