Bridge Statistics for Preble, New York (NY) - Condition, Traffic, Stress, Structural Evaluation, Project CostsBack to: Preble, NY, New York, New York forum, All US cities. National Bridge Inventory (NBI) Statistics Number of bridges: 12 Total length: 52 meters (171ft) Total costs: $12,397,000 Total average daily traffic: 144,637 Total average daily truck traffic: 32,671 National Bridge Inventory (NBI) Registered Bridges for Preble
Bridge Condition - Deck Bridge Condition - Superstructure Bridge Condition - Substructure Bridge Condition - Channel Bridge Condition - Culverts Find on map >>
Structure Number: 103143, Location: 8 MILES N JCT I81 & SH 13 (Lat: 42.707042, Lng: -76.149244), Route carried "on" structure: Interstate 81, Year Built: 1966, Status: Open, Structure Length: 1.03m (3.38ft), Average Daily Traffic: 25,020 (year 2005), Truck Traffic: 23%, Average Future Daily Traffic: 38,193 (year 2025), Design Load: HS 20+Mod, Features Intersected: W B TIOUGHNIOGA R Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 15.442, Lanes on structure: 4, Base Highway Network: Yes, Owner: State Highway Agency, Approaching Roadway Width: 21.3m (69.9ft), Skew: 24 degrees, Material/Design: Concrete continuous, Design/Construction: Culvert, Number Of Spans In Main Unit: 2, Length of Maximum Span: 4.5m (14.8ft) Condition: Channel: Fair, Culverts: Satisfactory, Operating Rating: 75.8 metric tons, Inventory Rating: 32.6 metric tons, Structural Evaluation: Equal to present minimum criteria, Waterway Adequacy: Somewhat better than minimum adequacy, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 1.03m (3.38ft), Designated Inspection Frequency: Every 24 months, Inspection Date: November 2007, Bridge Improvement Cost: $490,000, Roadway Improvement Cost: $291,000, Total Project Cost: $781,000 ( Estimate for 2007), Wearing Surface/Protective System: Wearing Surface: Bituminous Find on map >>
Structure Number: 1031441, Location: .5 MILE S EXIT 13 OF I81 (Lat: 42.734094, Lng: -76.142378), Route carried "on" structure: Interstate 81, Year Built: 1966, Year Reconstructed: 1978, Status: Open, Structure Length: 3.99m (13.09ft), Average Daily Traffic: 12,510 (year 2005), Truck Traffic: 23%, Average Future Daily Traffic: 19,097 (year 2025), Design Load: HS 20+Mod, Features Intersected: COUNTY ROAD 108 Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 15.427, Lanes on structure: 2, Lanes under structure: 2, Base Highway Network: Yes, Owner: State Highway Agency, Approaching Roadway Width: 9.1m (29.9ft), Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 3, Length of Maximum Span: 14.3m (46.9ft), Curb or Sidewalk Widths: Left: 0.5m (1.6ft), Right: 0.5m (1.6ft), Curb-To-Curb Width: 9.1m (29.9ft), Out-to-Out Width: 10.7m (35.1ft) Condition: Deck: Fair, Superstructure: Satisfactory, Substructure: Fair, Operating Rating: 68.0 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 40.8 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Somewhat better than minimum adequacy, Deck Geometry: High priority of replacement, Underclear: Somewhat better than minimum adequacy, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 3.99m (13.09ft), Designated Inspection Frequency: Every 24 months, Inspection Date: April 2006, Bridge Improvement Cost: $925,000, Roadway Improvement Cost: $550,000, Total Project Cost: $1,475,000 ( Estimate for 2007), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Bituminous Find on map >>
Structure Number: 1031442, Location: .5 MILE S EXIT 13 OF I81 (Lat: 42.733894, Lng: -76.141789), Route carried "on" structure: Interstate 81, Year Built: 1966, Year Reconstructed: 1978, Status: Open, Structure Length: 3.99m (13.09ft), Average Daily Traffic: 12,510 (year 2005), Truck Traffic: 23%, Average Future Daily Traffic: 19,097 (year 2025), Design Load: HS 20+Mod, Features Intersected: COUNTY ROAD 108 Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 15.427, Lanes on structure: 2, Lanes under structure: 2, Base Highway Network: Yes, Owner: State Highway Agency, Approaching Roadway Width: 12.8m (42.0ft), Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 3, Length of Maximum Span: 14.3m (46.9ft), Curb or Sidewalk Widths: Left: 0.1m (0.3ft), Right: 0.1m (0.3ft), Curb-To-Curb Width: 9.1m (29.9ft), Out-to-Out Width: 10.7m (35.1ft) Condition: Deck: Fair, Superstructure: Satisfactory, Substructure: Fair, Operating Rating: 68.0 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 40.8 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Somewhat better than minimum adequacy, Deck Geometry: High priority of replacement, Underclear: Somewhat better than minimum adequacy, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 3.99m (13.09ft), Designated Inspection Frequency: Every 24 months, Inspection Date: April 2006, Bridge Improvement Cost: $925,000, Roadway Improvement Cost: $550,000, Total Project Cost: $1,475,000 ( Estimate for 2007), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Bituminous Find on map >>
Structure Number: 103145, Location: JCT RTS 281 + I-81 (Lat: 42.746456, Lng: -76.137436), Route carried "on" structure: State highway 281, Year Built: 1966, Status: Open, Structure Length: 10.45m (34.28ft), Average Daily Traffic: 3,198 (year 2005), Truck Traffic: 9%, Average Future Daily Traffic: 3,948 (year 2025), Design Load: HS 20, Features Intersected: RTE I81 Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 15.990, Lanes on structure: 2, Lanes under structure: 4, Base Highway Network: Yes, Owner: State Highway Agency, Approaching Roadway Width: 12.1m (39.7ft), Skew: 3 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 5, Length of Maximum Span: 23.7m (77.8ft), Curb or Sidewalk Widths: Left: 0.2m (0.7ft), Right: 0.2m (0.7ft), Curb-To-Curb Width: 9.1m (29.9ft), Out-to-Out Width: 10.7m (35.1ft) Condition: Deck: Fair, Superstructure: Good, Substructure: Satisfactory, Operating Rating: 65.3 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 39.0 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Equal to present minimum criteria, Deck Geometry: Meets minimum limits, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 10.45m (34.28ft), Designated Inspection Frequency: Every 24 months, Inspection Date: October 2006, Bridge Improvement Cost: $2,422,000, Roadway Improvement Cost: $1,405,000, Total Project Cost: $3,827,000 ( Estimate for 2007), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Bituminous Find on map >>
Structure Number: 1031461, Location: 0.5 MI N JCT I81 + SH 281 (Lat: 42.751617, Lng: -76.136217), Route carried "on" structure: Interstate 81, Year Built: 1966, Status: Open, Structure Length: 0.85m (2.79ft), Average Daily Traffic: 27,337 (year 2004), Truck Traffic: 23%, Average Future Daily Traffic: 41,730 (year 2024), Design Load: HS 20+Mod, Features Intersected: W BR TIOUGHNIOGA Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 18.983, Lanes on structure: 2, Base Highway Network: Yes, Owner: State Highway Agency, Approaching Roadway Width: 11.5m (37.7ft), Skew: 4 degrees, Material/Design: Concrete continuous, Design/Construction: Culvert, Number Of Spans In Main Unit: 2, Length of Maximum Span: 3.3m (10.8ft) Condition: Channel: Good, Culverts: Good, Operating Rating: 74.9 metric tons, Inventory Rating: 32.6 metric tons, Structural Evaluation: Better than present minimum criteria, Waterway Adequacy: Meets minimum limits, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 0.85m (2.79ft), Designated Inspection Frequency: Every 24 months, Inspection Date: May 2006, Bridge Improvement Cost: $258,000, Roadway Improvement Cost: $153,000, Total Project Cost: $411,000 ( Estimate for 2007), Wearing Surface/Protective System: Wearing Surface: Bituminous Find on map >>
Structure Number: 1031462, Location: 0.5 MI N JCT I81 & SH 281 (Lat: 42.751189, Lng: -76.135789), Route carried "on" structure: Interstate 81, Year Built: 1966, Status: Open, Structure Length: 0.64m (2.10ft), Average Daily Traffic: 12,717 (year 1999), Truck Traffic: 23%, Average Future Daily Traffic: 19,413 (year 2019), Design Load: HS 20+Mod, Features Intersected: W BR TIOUGHNIOGA Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 18.983, Lanes on structure: 2, Base Highway Network: Yes, Owner: State Highway Agency, Approaching Roadway Width: 10.9m (35.8ft), Skew: 4 degrees, Material/Design: Concrete continuous, Design/Construction: Culvert, Number Of Spans In Main Unit: 2, Length of Maximum Span: 3.3m (10.8ft) Condition: Channel: Satisfactory, Culverts: Satisfactory, Operating Rating: 74.9 metric tons, Inventory Rating: 32.6 metric tons, Structural Evaluation: Equal to present minimum criteria, Waterway Adequacy: Somewhat better than minimum adequacy, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 0.64m (2.10ft), Designated Inspection Frequency: Every 24 months, Inspection Date: May 2006, Bridge Improvement Cost: $193,000, Roadway Improvement Cost: $115,000, Total Project Cost: $308,000 ( Estimate for 2007), Wearing Surface/Protective System: Wearing Surface: Bituminous Find on map >>
Structure Number: 103147, Location: 1.4 MI N JCT RTS I-81+281 (Lat: 42.764186, Lng: -76.131625), Route carried "on" structure: County highway , Year Built: 1966, Status: Open, Structure Length: 8.99m (29.49ft), Average Daily Traffic: 143 (year 1999), Truck Traffic: 6%, Average Future Daily Traffic: 180 (year 2019), Design Load: HS 20+Mod, Features Intersected: RTE I81, Facility Carried by Structure: CROSSING ROAD Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 0.000, Lanes on structure: 2, Lanes under structure: 4, Owner: State Highway Agency, Approaching Roadway Width: 7.3m (24.0ft), Skew: 1 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 5, Length of Maximum Span: 20.7m (67.9ft), Curb or Sidewalk Widths: Left: 0.3m (1.0ft), Right: 0.3m (1.0ft), Curb-To-Curb Width: 9.1m (29.9ft), Out-to-Out Width: 10.7m (35.1ft) Condition: Deck: Fair, Superstructure: Good, Substructure: Fair, Operating Rating: 49.9 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 29.9 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Somewhat better than minimum adequacy, Deck Geometry: Meets minimum limits, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 8.99m (29.49ft), Designated Inspection Frequency: Every 24 months, Inspection Date: May 2006, Bridge Improvement Cost: $2,083,000, Roadway Improvement Cost: $1,208,000, Total Project Cost: $3,291,000 ( Estimate for 2007), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete Find on map >>
Structure Number: 220746, Location: 1.3 MI SE OF PREBLE (Lat: 42.718747, Lng: -76.135331), Route carried "on" structure: City street , Year Built: 1964, Year Reconstructed: 1997, Status: Open, Structure Length: 1.18m (3.87ft), Average Daily Traffic: 57 (year 2003), Truck Traffic: 6%, Average Future Daily Traffic: 72 (year 2023), Design Load: HS 25, Features Intersected: W B TIOUGHNIOGA R, Facility Carried by Structure: CLARK ROAD Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 0.000, Lanes on structure: 1, Owner: Town or Township Highway Agency, Approaching Roadway Width: 4.8m (15.7ft), Material/Design: Prestressed concrete, Design/Construction: Slab, Number Of Spans In Main Unit: 1, Length of Maximum Span: 11.2m (36.7ft), Curb-To-Curb Width: 4.1m (13.5ft), Out-to-Out Width: 4.8m (15.7ft) Condition: Deck: Good, Superstructure: Good, Substructure: Satisfactory, Channel: Very good, Operating Rating: 68.0 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 42.6 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Equal to present minimum criteria, Deck Geometry: Somewhat better than minimum adequacy, Waterway Adequacy: Somewhat better than minimum adequacy, Approach Roadway Alignment: Somewhat better than minimum adequacy, Length Of Structure Improvement: 1.18m (3.87ft), Designated Inspection Frequency: Every 24 months, Inspection Date: May 2007, Bridge Improvement Cost: $107,000, Roadway Improvement Cost: $64,000, Total Project Cost: $171,000 ( Estimate for 2007), Wearing Surface/Protective System: Wearing Surface: Bituminous Find on map >>
Structure Number: 226317, Location: 3.2 MILES NE OF PREBLE (Lat: 42.775803, Lng: -76.127517), Route carried "on" structure: City street , Year Built: 1978, Status: Open, Structure Length: 0.73m (2.40ft), Average Daily Traffic: 221 (year 2002), Truck Traffic: 6%, Average Future Daily Traffic: 278 (year 2022), Features Intersected: TULLY LAKE CREEK, Facility Carried by Structure: SAULSBURY ROAD Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 0.000, Lanes on structure: 2, Owner: Town or Township Highway Agency, Approaching Roadway Width: 5.4m (17.7ft), Skew: 4 degrees, Material/Design: Steel, Design/Construction: Culvert, Number Of Spans In Main Unit: 2, Length of Maximum Span: 3.0m (9.8ft) Condition: Channel: Fair, Culverts: Satisfactory, Operating Rating: 74.7 metric tons, Inventory Rating: 32.6 metric tons, Structural Evaluation: Equal to present minimum criteria, Waterway Adequacy: Meets minimum limits, Approach Roadway Alignment: Equal to present minimum criteria, Length Of Structure Improvement: 0.73m (2.40ft), Designated Inspection Frequency: Every 24 months, Inspection Date: June 2007, Bridge Improvement Cost: $125,000, Roadway Improvement Cost: $74,000, Total Project Cost: $199,000 ( Estimate for 2007), Wearing Surface/Protective System: Wearing Surface: Bituminous Find on map >>
Structure Number: 331195, Location: 1 MILE SE OF PREBLE (Lat: 42.732072, Lng: -76.130814), Route carried "on" structure: County highway , Year Built: 1975, Status: Open, Structure Length: 1.46m (4.79ft), Average Daily Traffic: 469 (year 1999), Truck Traffic: 8%, Average Future Daily Traffic: 541 (year 2019), Features Intersected: WB TIOUGHNIOGA RV, Facility Carried by Structure: COUNTY ROAD 108B Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 0.000, Lanes on structure: 2, Owner: County Highway Agency, Approaching Roadway Width: 6.7m (22.0ft), Material/Design: Steel, Design/Construction: Culvert, Number Of Spans In Main Unit: 5, Length of Maximum Span: 2.1m (6.9ft) Condition: Channel: Satisfactory, Culverts: Fair, Operating Rating: 73.9 metric tons, Inventory Rating: 29.3 metric tons, Structural Evaluation: Somewhat better than minimum adequacy, Waterway Adequacy: Meets minimum limits, Approach Roadway Alignment: Better than present minimum criteria, Length Of Structure Improvement: 1.46m (4.79ft), Designated Inspection Frequency: Every 24 months, Inspection Date: August 2007, Bridge Improvement Cost: $288,000, Roadway Improvement Cost: $171,000, Total Project Cost: $459,000 ( Estimate for 2007), Wearing Surface/Protective System: Wearing Surface: Bituminous Find on map >>
Structure Number: 103145, Location: JCT RTS 281 + I-81 (Lat: 42.746456, Lng: -76.137436), Route carried "under" structure: Interstate 81, Year Built: 1966, Structure Length: 10.45m (34.28ft), Average Daily Traffic: 25,020 (year 2005), Truck Traffic: 23%, Features Intersected: RTE I81 Minimum Vertical Clearance: 4.97m (16.31ft), Kilometerpoint: 15.446, Lanes on structure: 2, Lanes under structure: 4, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Length of Maximum Span: 23.7m (77.8ft) Find on map >>
Structure Number: 103147, Location: 1.4 MI N JCT RTS I-81+281 (Lat: 42.764186, Lng: -76.131625), Route carried "under" structure: Interstate 81, Year Built: 1966, Structure Length: 8.99m (29.49ft), Average Daily Traffic: 25,435 (year 1999), Truck Traffic: 23%, Features Intersected: RTE I81, Facility Carried by Structure: CROSSING ROAD Minimum Vertical Clearance: 5.13m (16.83ft), Kilometerpoint: 1.749, Lanes on structure: 2, Lanes under structure: 4, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Length of Maximum Span: 20.7m (67.9ft) Discuss this city on our hugely popular New York forum Back to: Preble, NY, New York, All US cities.
|
![]() |