National Bridge Inventory (NBI) Statistics
Number of bridges: 10
Total length: 22 meters (72ft)
Total costs: $20,000
Total average daily traffic: 22,950
Total average daily truck traffic: 1,130
Total future (year 2026) average daily traffic: 11,475
National Bridge Inventory (NBI) Registered Bridges for Salisbury

New bridges - Historical Statistics

  • 1920-1929: 2
  • 1930-1939: 2
  • 1940-1949: 0
  • 1950-1959: 3
  • 1960-1969: 0
  • 1970-1979: 0
  • 1980-1989: 0
  • 1990-1999: 0
  • 2000-2009: 3

Average Daily Traffic

Bridge Condition - Deck

Bridge Condition - Superstructure

Bridge Condition - Substructure

Bridge Condition - Channel

Find on map >>

Structure Number: 562,  Location: T.L. CANAAN & SALISBURY (Lat: 41.941667,  Lng: -73.361667),  Route carried "on" structure: US 7,  Year Built: 1931,  Year Reconstructed: 1986,  Status: Open,  Structure Length: 6.86m (22.51ft),  Average Daily Traffic: 3,300 (year 2006),  Truck Traffic: 4%,  Average Future Daily Traffic: 1,650 (year 2026),  Design Load: H 20,  Features Intersected: HOUSATONIC RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 110.908,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Steel,  Design/Construction: Truss - Deck,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 29.3m (96.1ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 10.1m (33.1ft)

Condition: Deck: Fair,  Superstructure: Satisfactory,  Substructure: Poor,  Channel: Poor,  Operating Rating: 43.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 26.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 0.01m (0.03ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 12 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: March 2007,  Critical Feature Inspection Date: March 2007,  Underwater Inspection Date: March 2007,  Other Special Inspection Date: March 2007,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2000),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>

Structure Number: 963,  Location: 0.2MI S OF MASS STATELINE (Lat: 42.048333,  Lng: -73.426667),  Route carried "on" structure: State highway 41,  Year Built: 1929,  Status: Open,  Structure Length: 1.07m (3.51ft),  Average Daily Traffic: 1,200 (year 2005),  Truck Traffic: 3%,  Average Future Daily Traffic: 600 (year 2026),  Design Load: H 15,  Features Intersected: SAGES RAVINE BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 28.705,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 8.8m (28.9ft),  Material/Design: Concrete,  Design/Construction: Arch - Deck,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 10.7m (35.1ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 10.1m (33.1ft)

Condition: Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 65.7 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 47.7 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 0.01m (0.03ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2006,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2000)
Find on map >>

Structure Number: 964,  Location: DOWNTOWN SALISBURY (Lat: 41.980000,  Lng: -73.423333),  Route carried "on" structure: US 44,  Year Built: 1951,  Status: Open,  Structure Length: 1.25m (4.10ft),  Average Daily Traffic: 7,500 (year 2005),  Truck Traffic: 6%,  Average Future Daily Traffic: 3,750 (year 2026),  Design Load: H 20,  Features Intersected: WACHOCASTINOOK CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 7.273,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 11.6m (38.1ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 11.6m (38.1ft),  Curb or Sidewalk Widths: Left: 0.5m (1.6ft),  Right: 2.4m (7.9ft),  Curb-To-Curb Width: 11.6m (38.1ft),  Out-to-Out Width: 15.5m (50.9ft)

Condition: Deck: Poor,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Good,  Operating Rating: 76.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 45.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.01m (0.03ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2006,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2000),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>

Structure Number: 965,  Location: .5 MILES EAST OF ROUTE 41 (Lat: 41.990000,  Lng: -73.416667),  Route carried "on" structure: US 44,  Year Built: 1928,  Status: Open,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 4,500 (year 2005),  Truck Traffic: 6%,  Average Future Daily Traffic: 2,250 (year 2026),  Features Intersected: SPRUCE SWAMP CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 8.383,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 9.4m (30.8ft),  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.5m (27.9ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 9.3m (30.5ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Fair,  Channel: Fair,  Operating Rating: 89.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 54.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.01m (0.03ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: September 2006,  Other Special Inspection Date: October 2007,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2000),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>

Structure Number: 1316,  Location: INTERSECT WHITE HOLLOW RD (Lat: 41.946667,  Lng: -73.391667),  Route carried "on" structure: State highway 112,  Year Built: 1958,  Status: Open,  Structure Length: 4.48m (14.70ft),  Average Daily Traffic: 2,500 (year 2006),  Truck Traffic: 3%,  Average Future Daily Traffic: 1,250 (year 2026),  Design Load: HS 20,  Features Intersected: SALMON CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 8.351,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Skew: 6 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 19.2m (63.0ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 0.5m (1.6ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 14.8m (48.6ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 81.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 48.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 0.01m (0.03ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2007,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2000),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>

Structure Number: 1317,  Location: .55 MI W OF US7 JCT (Lat: 41.926667,  Lng: -73.373333),  Route carried "on" structure: State highway 112,  Year Built: 1930,  Year Reconstructed: 1986,  Status: Open,  Structure Length: 1.31m (4.30ft),  Average Daily Traffic: 2,600 (year 2005),  Truck Traffic: 3%,  Average Future Daily Traffic: 1,300 (year 2026),  Design Load: H 15,  Features Intersected: SALMON CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 9.863,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 12.2m (40.0ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 9.4m (30.8ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 69.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 41.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 0.01m (0.03ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2007,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2000),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>

Structure Number: 5198,  Location: JCT FACTORY STREET (Lat: 41.981667,  Lng: -73.426667),  Route carried "on" structure: City street ,  Year Built: 2002,  Status: Open,  Structure Length: 1.43m (4.69ft),  Average Daily Traffic: 500 (year 1997),  Truck Traffic: 7%,  Average Future Daily Traffic: 250 (year 2026),  Design Load: HS 20,  Features Intersected: WACHOCASTINOOK BROOK,  Facility Carried by Structure: SELLECK HILL ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.193,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.6m (24.9ft),  Skew: 6 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 12.5m (41.0ft),  Curb-To-Curb Width: 10.1m (33.1ft),  Out-to-Out Width: 10.7m (35.1ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Good,  Operating Rating: 80.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 48.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 0.01m (0.03ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2006,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2000),  Deck Structure Type: Other,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 5199,  Location: 100' W OF JCT MT. RIGA RD (Lat: 41.988333,  Lng: -73.431667),  Route carried "on" structure: City street ,  Year Built: 1957,  Status: Open,  Structure Length: 1.13m (3.71ft),  Average Daily Traffic: 100 (year 2000),  Truck Traffic: 2%,  Average Future Daily Traffic: 50 (year 2026),  Design Load: H 20,  Features Intersected: WACHOCASTINOOK BROOK,  Facility Carried by Structure: RIGA LANE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.080,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 6.4m (21.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.1m (29.9ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 7.8m (25.6ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 60.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 36.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 0.01m (0.03ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2006,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2000),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 52,  Location: 0.75 M EAST OF ROUTE 112 (Lat: 41.943333,  Lng: -73.390000),  Route carried "on" structure: City street ,  Year Built: 2002,  Status: Open,  Structure Length: 1.55m (5.09ft),  Average Daily Traffic: 450 (year 0 ),  Truck Traffic: 7%,  Average Future Daily Traffic: 225 (year 2026),  Design Load: HS 20,  Features Intersected: SALMON CREEK,  Facility Carried by Structure: SALMON KILL ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.161,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Skew: 1 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 14.0m (45.9ft),  Curb-To-Curb Width: 8.0m (26.2ft),  Out-to-Out Width: 8.9m (29.2ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Good,  Channel: Good,  Operating Rating: 59.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 34.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 0.01m (0.03ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2006,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2000),  Deck Structure Type: Other,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>

Structure Number: 5201,  Location: 500' W OF SALMON KILL RD (Lat: 41.960000,  Lng: -73.401667),  Route carried "on" structure: City street ,  Year Built: 2001,  Status: Open,  Structure Length: 2.01m (6.59ft),  Average Daily Traffic: 300 (year 1997),  Truck Traffic: 7%,  Average Future Daily Traffic: 150 (year 2026),  Design Load: HS 20,  Features Intersected: SALMON CREEK,  Facility Carried by Structure: FARNAM ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 2.269,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 18.9m (62.0ft),  Curb-To-Curb Width: 7.5m (24.6ft),  Out-to-Out Width: 8.7m (28.5ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Satisfactory,  Operating Rating: 68.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 40.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.01m (0.03ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2006,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2000),  Deck Structure Type: Other,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up

Discuss this city on our hugely popular Connecticut forum

Back to: Salisbury, CT, Connecticut, All US cities.