National Bridge Inventory (NBI) Statistics
Number of bridges: 31
Total length: 115 meters (377ft)
Total costs: $45,131,000
Total average daily traffic: 378,003
Total average daily truck traffic: 36,426
National Bridge Inventory (NBI) Registered Bridges for Smithfield

New bridges - Historical Statistics

  • 1910-1919: 1
  • 1920-1929: 2
  • 1930-1939: 3
  • 1940-1949: 0
  • 1950-1959: 0
  • 1960-1969: 2
  • 1970-1979: 20
  • 1980-1989: 1
  • 1990-1999: 1
  • 2000-2009: 1

Reconstructed bridges - Historical Statistics

  • 1930-1939: 1
  • 1940-1949: 0
  • 1950-1959: 0
  • 1960-1969: 0
  • 1970-1979: 0
  • 1980-1989: 4

Average Daily Traffic

Bridge Condition - Deck

Bridge Condition - Superstructure

Bridge Condition - Substructure

Bridge Condition - Channel

Find on map >>

Structure Number: 144,  Location: 0.6 Mi N of JCT RI 116 (Lat: 41.908833,  Lng: -71.541500),  Route carried "on" structure: Alternate State highway 104,  Year Built: 2000,  Status: Open,  Structure Length: 1.13m (3.71ft),  Average Daily Traffic: 3,500 (year 2006),  Truck Traffic: 2%,  Average Future Daily Traffic: 7,600 (year 2028),  Design Load: HS 25,  Features Intersected: WOONASQUATUCKET RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.1m (29.9ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 10.2m (33.5ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Good,  Channel: Very good,  Operating Rating: 88.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 88.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.13m (3.71ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2007,  Bridge Improvement Cost: $239,000,  Roadway Improvement Cost: $24,000,  Total Project Cost: $359,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 155,  Location: 1.0 Mi W of JCT RI 116 (Lat: 41.877667,  Lng: -71.571500),  Route carried "on" structure: US 44,  Year Built: 1918,  Year Reconstructed: 1936,  Status: Open,  Structure Length: 0.76m (2.49ft),  Average Daily Traffic: 5,900 (year 2006),  Truck Traffic: 10%,  Average Future Daily Traffic: 16,120 (year 2028),  Design Load: H 20,  Features Intersected: MILL CANAL
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 4,  Base Highway Network: Yes (,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 12.5m (41.0ft),  Skew: 5 degrees,  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.1m (20.0ft),  Curb or Sidewalk Widths: Left: 2.4m (7.9ft),  Right: 1.8m (5.9ft),  Curb-To-Curb Width: 12.5m (41.0ft),  Out-to-Out Width: 22.2m (72.8ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Channel: Good,  Operating Rating: 61.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 36.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 0.76m (2.49ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: May 2007,  Underwater Inspection Date: June 2003,  Bridge Improvement Cost: $352,000,  Roadway Improvement Cost: $35,000,  Total Project Cost: $528,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 159,  Location: 0.1 Mi N of High St (Lat: 41.880000,  Lng: -71.502000),  Route carried "on" structure: State highway 104,  Year Built: 1939,  Status: Open,  Structure Length: 1.80m (5.91ft),  Average Daily Traffic: 3,700 (year 2006),  Truck Traffic: 10%,  Average Future Daily Traffic: 4,845 (year 2028),  Design Load: H 20,  Features Intersected: WOONASQUATUCKET RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Skew: 1 degrees,  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 18.0m (59.1ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 12.3m (40.4ft),  Out-to-Out Width: 17.7m (58.1ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 65.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 39.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 2.59m (8.50ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2007,  Bridge Improvement Cost: $664,000,  Roadway Improvement Cost: $66,000,  Total Project Cost: $996,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 248,  Location: 0.1 Mi S of JCT RI 104 (Lat: 41.897333,  Lng: -71.544833),  Route carried "on" structure: State highway 116,  Year Built: 1929,  Year Reconstructed: 1992,  Status: Open,  Structure Length: 0.79m (2.59ft),  Average Daily Traffic: 11,000 (year 2006),  Truck Traffic: 10%,  Average Future Daily Traffic: 15,281 (year 2028),  Design Load: H 20,  Features Intersected: STILLWATER RESERVOIR
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Skew: 1 degrees,  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.6m (24.9ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 1.7m (5.6ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 13.4m (44.0ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Fair,  Channel: Good,  Operating Rating: 78.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 46.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 0.79m (2.59ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: May 2007,  Underwater Inspection Date: June 2003,  Bridge Improvement Cost: $269,000,  Roadway Improvement Cost: $27,000,  Total Project Cost: $404,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 249,  Location: 1.1 Mi N of JCT US 44 (Lat: 41.883667,  Lng: -71.543000),  Route carried "on" structure: State highway 116,  Year Built: 1929,  Year Reconstructed: 1992,  Status: Open,  Structure Length: 0.67m (2.20ft),  Average Daily Traffic: 13,700 (year 2006),  Truck Traffic: 10%,  Average Future Daily Traffic: 17,093 (year 2028),  Design Load: H 20,  Features Intersected: GREENVILLE BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Skew: 2 degrees,  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.1m (20.0ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 12.8m (42.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 73.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 44.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 0.67m (2.20ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2007,  Bridge Improvement Cost: $63,000,  Roadway Improvement Cost: $6,000,  Total Project Cost: $95,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 278,  Location: 0.5 Mi S of JCT RI 7 (Lat: 41.906667,  Lng: -71.538167),  Route carried "on" structure: State highway 116,  Year Built: 1932,  Year Reconstructed: 1987,  Status: Open,  Structure Length: 13.69m (44.91ft),  Average Daily Traffic: 8,803 (year 1999),  Truck Traffic: 5%,  Average Future Daily Traffic: 11,131 (year 2028),  Design Load: H 20,  Features Intersected: Stillwater Reservoir
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Base Highway Network: Yes (,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 12.8m (42.0ft),  Material/Design: Concrete,  Design/Construction: Arch - Deck,  Number Of Spans In Main Unit: 1,  Number Of Approach Spans: 12,  Length of Maximum Span: 36.3m (119.1ft),  Curb or Sidewalk Widths: Left: 1.4m (4.6ft),  Right: 1.4m (4.6ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 15.2m (49.9ft)

Condition: Deck: Serious,  Superstructure: Poor,  Substructure: Poor,  Channel: Very good,  Operating Rating: 48.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 29.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 13.69m (44.91ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2007,  Bridge Improvement Cost: $5,821,000,  Roadway Improvement Cost: $582,000,  Total Project Cost: $8,732,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>

Structure Number: 741,  Location: 1.0 Mi E of JCT RI 116 (Lat: 41.867000,  Lng: -71.515833),  Route carried "on" structure: US 44,  Year Built: 1971,  Status: Open,  Structure Length: 7.68m (25.20ft),  Average Daily Traffic: 28,100 (year 2006),  Truck Traffic: 10%,  Average Future Daily Traffic: 41,649 (year 2028),  Design Load: HS 20+Mod,  Features Intersected: I-295 NB & SB
Minimum Vertical Clearance: 4.93m (16.17ft),  Kilometerpoint: 0.000,  Lanes on structure: 6,  Lanes under structure: 8,  Owner: State Highway Agency,  Approaching Roadway Width: 28.7m (94.2ft),  Skew: 37 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 38.1m (125.0ft),  Curb-To-Curb Width: 28.7m (94.2ft),  Out-to-Out Width: 30.3m (99.4ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Poor,  Operating Rating: 80.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 47.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Superior to present desirable criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 7.59m (24.90ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2007,  Bridge Improvement Cost: $4,847,000,  Roadway Improvement Cost: $485,000,  Total Project Cost: $7,270,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>

Structure Number: 742,  Location: 0.5 Mi N of JCT US 44 (Lat: 41.876667,  Lng: -71.515000),  Route carried "on" structure: Interstate 295,  Year Built: 1971,  Status: Open,  Structure Length: 2.12m (6.96ft),  Average Daily Traffic: 35,000 (year 2006),  Truck Traffic: 10%,  Average Future Daily Traffic: 19,069 (year 2028),  Design Load: HS 20+Mod,  Features Intersected: MOUNTAINDALE RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 3,  Lanes under structure: 2,  Base Highway Network: Yes (,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 16.5m (54.1ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 20.1m (65.9ft),  Curb-To-Curb Width: 16.5m (54.1ft),  Out-to-Out Width: 17.5m (57.4ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Operating Rating: 53.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 31.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.62m (8.60ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2007,  Bridge Improvement Cost: $772,000,  Roadway Improvement Cost: $77,000,  Total Project Cost: $1,158,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>

Structure Number: 7422,  Location: 0.5 Mi N Of JCT US 44 (Lat: 41.876333,  Lng: -71.514333),  Route carried "on" structure: Interstate 295,  Year Built: 1971,  Status: Open,  Structure Length: 2.62m (8.60ft),  Average Daily Traffic: 26,900 (year 2006),  Truck Traffic: 10%,  Average Future Daily Traffic: 13,800 (year 2028),  Design Load: HS 20+Mod,  Features Intersected: MOUNTAINDALE RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 3,  Lanes under structure: 2,  Base Highway Network: Yes (,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 16.5m (54.1ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 20.1m (65.9ft),  Curb-To-Curb Width: 16.5m (54.1ft),  Out-to-Out Width: 17.5m (57.4ft)

Condition: Deck: Good,  Superstructure: Fair,  Substructure: Satisfactory,  Operating Rating: 53.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 31.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.62m (8.60ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2007,  Bridge Improvement Cost: $955,000,  Roadway Improvement Cost: $96,000,  Total Project Cost: $1,433,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>

Structure Number: 743,  Location: 1.0 Mi S of JCT RI 5 (Lat: 41.895500,  Lng: -71.524000),  Route carried "on" structure: State highway 104,  Year Built: 1974,  Status: Open,  Structure Length: 4.51m (14.80ft),  Average Daily Traffic: 2,000 (year 2006),  Truck Traffic: 10%,  Average Future Daily Traffic: 2,649 (year 2028),  Design Load: HS 20+Mod,  Features Intersected: I-295 NORTHBOUND
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 3,  Owner: State Highway Agency,  Approaching Roadway Width: 14.3m (46.9ft),  Skew: 4 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 43.9m (144.0ft),  Curb-To-Curb Width: 14.3m (46.9ft),  Out-to-Out Width: 15.4m (50.5ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Fair,  Operating Rating: 76.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 45.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Superior to present desirable criteria,  Underclear: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 4.51m (14.80ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2007,  Bridge Improvement Cost: $1,446,000,  Roadway Improvement Cost: $145,000,  Total Project Cost: $2,169,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>

Structure Number: 7432,  Location: 1.0 Mi S of JCT RI 5 (Lat: 41.895833,  Lng: -71.525333),  Route carried "on" structure: State highway 104,  Year Built: 1974,  Status: Open,  Structure Length: 4.30m (14.11ft),  Average Daily Traffic: 2,300 (year 2006),  Truck Traffic: 10%,  Average Future Daily Traffic: 3,046 (year 2028),  Design Load: HS 20+Mod,  Features Intersected: I-295 SOUTHBOUND
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 3,  Owner: State Highway Agency,  Approaching Roadway Width: 14.3m (46.9ft),  Skew: 4 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 41.8m (137.1ft),  Curb-To-Curb Width: 14.3m (46.9ft),  Out-to-Out Width: 15.4m (50.5ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Fair,  Operating Rating: 77.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 46.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Superior to present desirable criteria,  Underclear: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 4.30m (14.11ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2007,  Bridge Improvement Cost: $1,378,000,  Roadway Improvement Cost: $138,000,  Total Project Cost: $2,066,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>

Structure Number: 744,  Location: 0.6 Mi S of JCT RI 7 (Lat: 41.902667,  Lng: -71.521500),  Route carried "on" structure: Interstate 295,  Year Built: 1973,  Status: Open,  Structure Length: 0.76m (2.49ft),  Average Daily Traffic: 51,800 (year 2006),  Truck Traffic: 10%,  Average Future Daily Traffic: 27,600 (year 2028),  Design Load: HS 20,  Features Intersected: WOONASQUATUCKET RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 6,  Base Highway Network: Yes (,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 30.5m (100.1ft),  Skew: 10 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.7m (12.1ft),  Curb-To-Curb Width: 30.5m (100.1ft),  Out-to-Out Width: 98.1m (321.9ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Equal to present desirable criteria,  Length Of Structure Improvement: 0.85m (2.79ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2007,  Bridge Improvement Cost: $1,550,000,  Roadway Improvement Cost: $155,000,  Total Project Cost: $2,326,000 ( Estimate for 2007)
Find on map >>

Structure Number: 745,  Location: 0.5 Mi S of JCT RI 7 (Lat: 41.902833,  Lng: -71.519333),  Route carried "on" structure: Interstate 295,  Year Built: 1970,  Status: Open,  Structure Length: 2.38m (7.81ft),  Average Daily Traffic: 27,000 (year 2006),  Truck Traffic: 10%,  Average Future Daily Traffic: 51,421 (year 2028),  Design Load: HS 20+Mod,  Features Intersected: STILLWATER RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 3,  Lanes under structure: 2,  Base Highway Network: Yes (,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 16.6m (54.5ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 22.9m (75.1ft),  Curb-To-Curb Width: 16.6m (54.5ft),  Out-to-Out Width: 17.5m (57.4ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Fair,  Operating Rating: 85.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 51.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 2.38m (7.81ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2007,  Bridge Improvement Cost: $868,000,  Roadway Improvement Cost: $87,000,  Total Project Cost: $1,302,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>

Structure Number: 7452,  Location: 0.5 Mi S of JCT RI 7 (Lat: 41.903167,  Lng: -71.520333),  Route carried "on" structure: Interstate 295,  Year Built: 1970,  Status: Open,  Structure Length: 2.38m (7.81ft),  Average Daily Traffic: 24,900 (year 2006),  Truck Traffic: 10%,  Average Future Daily Traffic: 13,800 (year 2028),  Design Load: HS 20+Mod,  Features Intersected: STILLWATER RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 3,  Lanes under structure: 2,  Base Highway Network: Yes (,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 16.6m (54.5ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 22.9m (75.1ft),  Curb-To-Curb Width: 16.6m (54.5ft),  Out-to-Out Width: 17.5m (57.4ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Operating Rating: 85.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 51.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 2.38m (7.81ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2007,  Bridge Improvement Cost: $868,000,  Roadway Improvement Cost: $87,000,  Total Project Cost: $1,302,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>

Structure Number: 746,  Location: 0.5 Mi S of JCT RI 146 (Lat: 41.907667,  Lng: -71.512500),  Route carried "on" structure: State highway 7,  Year Built: 1971,  Status: Open,  Structure Length: 3.14m (10.30ft),  Average Daily Traffic: 8,300 (year 2006),  Truck Traffic: 10%,  Design Load: HS 20+Mod,  Features Intersected: I-295 SOUTHBOUND
Minimum Vertical Clearance: 5.00m (16.40ft),  Kilometerpoint: 0.000,  Lanes on structure: 6,  Lanes under structure: 4,  Owner: State Highway Agency,  Approaching Roadway Width: 28.3m (92.8ft),  Skew: 30 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 30.2m (99.1ft),  Curb-To-Curb Width: 28.3m (92.8ft),  Out-to-Out Width: 30.3m (99.4ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Fair,  Operating Rating: 72.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 43.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Superior to present desirable criteria,  Underclear: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 3.14m (10.30ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2007,  Bridge Improvement Cost: $1,979,000,  Roadway Improvement Cost: $198,000,  Total Project Cost: $2,969,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>

Structure Number: 7462,  Location: 0.5 Mi S of JCT RI 146 (Lat: 41.907667,  Lng: -71.512500),  Route carried "on" structure: State highway 7,  Year Built: 1971,  Status: Open,  Structure Length: 3.11m (10.20ft),  Average Daily Traffic: 8,000 (year 2006),  Truck Traffic: 10%,  Design Load: HS 20+Mod,  Features Intersected: I-295 NORTHBOUND
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 6,  Lanes under structure: 4,  Owner: State Highway Agency,  Approaching Roadway Width: 28.3m (92.8ft),  Skew: 30 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 30.2m (99.1ft),  Curb-To-Curb Width: 28.3m (92.8ft),  Out-to-Out Width: 30.3m (99.4ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Fair,  Operating Rating: 72.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 43.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Superior to present desirable criteria,  Underclear: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 3.11m (10.20ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2007,  Bridge Improvement Cost: $1,960,000,  Roadway Improvement Cost: $196,000,  Total Project Cost: $2,940,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>

Structure Number: 747,  Location: 1.0 Mi W of RI 123 (Lat: 41.891667,  Lng: -71.520167),  Route carried "on" structure: State highway 116,  Year Built: 1967,  Year Reconstructed: 1987,  Status: Open,  Structure Length: 10.03m (32.91ft),  Average Daily Traffic: 10,900 (year 2006),  Truck Traffic: 4%,  Average Future Daily Traffic: 12,835 (year 2028),  Design Load: HS 20+Mod,  Features Intersected: I-295 NB & SB
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 6,  Base Highway Network: Yes (,  Subroute: 1),  Owner: State Highway Agency,  Approaching Roadway Width: 13.4m (44.0ft),  Skew: 4 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 39.3m (128.9ft),  Curb or Sidewalk Widths: Left: 0.6m (2.0ft),  Right: 0.6m (2.0ft),  Curb-To-Curb Width: 13.4m (44.0ft),  Out-to-Out Width: 15.2m (49.9ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Fair,  Operating Rating: 72.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 43.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Underclear: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 9.81m (32.19ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2007,  Bridge Improvement Cost: $3,103,000,  Roadway Improvement Cost: $310,000,  Total Project Cost: $4,654,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>

Structure Number: 792,  Location: 1.0 Mi E of JCT RI 104 (Lat: 41.902333,  Lng: -71.522667),  Route carried "on" structure: City street ,  Year Built: 1932,  Status: Posted for load,  Structure Length: 1.19m (3.90ft),  Average Daily Traffic: 2,000 (year 2006),  Truck Traffic: 10%,  Design Load: H 20,  Features Intersected: WOONASQUATUCKET RIVER,  Facility Carried by Structure: CAPRON RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 5.8m (19.0ft),  Skew: 2 degrees,  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.7m (12.1ft),  Curb-To-Curb Width: 5.8m (19.0ft),  Out-to-Out Width: 7.9m (25.9ft)

Condition: Deck: Poor,  Superstructure: Poor,  Substructure: Serious,  Channel: Satisfactory,  Operating Rating: 22.5 metric tons,  Inventory Rating: 22.5 metric tons,  Structural Evaluation: High priority of corrective action,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 10.0 - 19.9% below),  Length Of Structure Improvement: 1.19m (3.90ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: June 2007,  Other Special Inspection Date: January 2003,  Bridge Improvement Cost: $633,000,  Roadway Improvement Cost: $63,000,  Total Project Cost: $950,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 797,  Location: 1.0 Mi S of JCT RI 116 (Lat: 41.908667,  Lng: -71.513667),  Route carried "on" structure: Ramp State highway 7,  Year Built: 1975,  Status: Open,  Structure Length: 3.87m (12.70ft),  Average Daily Traffic: 5,200 (year 2006),  Truck Traffic: 10%,  Design Load: HS 20,  Features Intersected: RAMP 5 of I-295,  Facility Carried by Structure: RAMP DOUGLAS PIKE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Lanes under structure: 1,  Owner: State Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Skew: 2 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 38.1m (125.0ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 9.6m (31.5ft)

Condition: Deck: Good,  Superstructure: Fair,  Substructure: Satisfactory,  Operating Rating: 74.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 45.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Superior to present desirable criteria,  Underclear: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 3.87m (12.70ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2007,  Bridge Improvement Cost: $774,000,  Roadway Improvement Cost: $77,000,  Total Project Cost: $1,161,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Latex Concrete
Find on map >>

Structure Number: 798,  Location: 0.5 Mi E of JCT RI 116 (Lat: 41.906667,  Lng: -71.513333),  Route carried "on" structure: Ramp Interstate 295,  Year Built: 1976,  Status: Open,  Structure Length: 3.23m (10.60ft),  Average Daily Traffic: 3,400 (year 2006),  Truck Traffic: 10%,  Average Future Daily Traffic: 5,000 (year 2026),  Design Load: HS 20,  Features Intersected: RAMP 5 EXIT TO RI 7
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Lanes under structure: 1,  Owner: State Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 31.7m (104.0ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 9.7m (31.8ft)

Condition: Deck: Good,  Superstructure: Fair,  Substructure: Satisfactory,  Operating Rating: 85.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 51.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Superior to present desirable criteria,  Underclear: Equal to present minimum criteria,  Approach Roadway Alignment: Meets minimum limits,  Length Of Structure Improvement: 3.26m (10.70ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2007,  Bridge Improvement Cost: $977,000,  Roadway Improvement Cost: $98,000,  Total Project Cost: $1,466,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Latex Concrete
Find on map >>

Structure Number: 947,  Location: 0.1 Mi E of JCT RI 104 (Lat: 41.885000,  Lng: -71.505667),  Route carried "on" structure: City street ,  Year Built: 1980,  Status: Open,  Structure Length: 1.52m (4.99ft),  Average Daily Traffic: 1,900 (year 2006),  Truck Traffic: 10%,  Average Future Daily Traffic: 2,549 (year 2028),  Design Load: HS 20+Mod,  Features Intersected: WOONASQUATUCKET RIVER,  Facility Carried by Structure: WHIPPLE AV
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Skew: 7 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 14.6m (47.9ft),  Curb or Sidewalk Widths: Left: 0.0m,  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 11.6m (38.1ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 54.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.52m (4.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2007,  Bridge Improvement Cost: $366,000,  Roadway Improvement Cost: $37,000,  Total Project Cost: $549,000 ( Estimate for 2007),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>

Structure Number: 948,  Location: 0.1 Mi S of JCT RI 104 (Lat: 41.877833,  Lng: -71.503333),  Route carried "on" structure: City street ,  Year Built: 1979,  Status: Open,  Structure Length: 1.46m (4.79ft),  Average Daily Traffic: 7,200 (year 2006),  Truck Traffic: 10%,  Average Future Daily Traffic: 8,736 (year 2028),  Design Load: HS 20+Mod,  Features Intersected: WOONASQUATUCKET RIVER,  Facility Carried by Structure: ESMOND ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Skew: 2 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 13.4m (44.0ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 12.2m (40.0ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 64.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 38.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.46m (4.79ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2007,  Bridge Improvement Cost: $120,000,  Roadway Improvement Cost: $12,000,  Total Project Cost: $180,000 ( Estimate for 2007),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>

Structure Number: 9492,  Location: 0.3 Mi N of JCT RI 104 (Lat: 41.893333,  Lng: -71.508333),  Route carried "on" structure: City street ,  Year Built: 1994,  Status: Closed,  Structure Length: 2.19m (7.19ft),  Design Load: Pedestrian,  Features Intersected: WOONASQUSTUCKET RIVER,  Facility Carried by Structure: STILLWATER RD(PED)
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Owner: State Highway Agency,  Approaching Roadway Width: 8.8m (28.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 14.9m (48.9ft),  Curb-To-Curb Width: 1.4m (4.6ft),  Out-to-Out Width: 1.8m (5.9ft)

Condition: Deck: Serious,  Superstructure: Fair,  Substructure: Fair,  Channel: Very good,  Waterway Adequacy: Better than present minimum criteria,  Length Of Structure Improvement: 2.19m (7.19ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: June 2007,  Other Special Inspection Date: June 2007,  Bridge Improvement Cost: $81,000,  Roadway Improvement Cost: $8,000,  Total Project Cost: $122,000 ( Estimate for 2007),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>

Structure Number: 741,  Location: 1.0 Mi E of JCT RI 116 (Lat: 41.867000,  Lng: -71.515833),  Route carried "under" structure: Interstate 295,  Year Built: 1971,  Structure Length: 7.68m (25.20ft),  Average Daily Traffic: 14,800 (year 2006),  Truck Traffic: 10%,  Features Intersected: I-295 NB & SB,  Facility Carried by Structure: US 44 PUTNAM PIKE
Minimum Vertical Clearance: 4.97m (16.31ft),  Kilometerpoint: 0.000,  Lanes on structure: 6,  Lanes under structure: 8,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 38.1m (125.0ft)

Find on map >>

Structure Number: 743,  Location: 1.0 Mi S of JCT RI 5 (Lat: 41.895500,  Lng: -71.524000),  Route carried "under" structure: Interstate 295,  Year Built: 1974,  Structure Length: 4.51m (14.80ft),  Average Daily Traffic: 7,400 (year 2006),  Truck Traffic: 10%,  Features Intersected: I-295 NORTHBOUND,  Facility Carried by Structure: RI 104 FARNUM PIKE
Minimum Vertical Clearance: 4.92m (16.14ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 3,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 43.9m (144.0ft)

Find on map >>

Structure Number: 7432,  Location: 1.0 Mi S of JCT RI 5 (Lat: 41.895833,  Lng: -71.525333),  Route carried "under" structure: Interstate 295,  Year Built: 1974,  Structure Length: 4.30m (14.11ft),  Average Daily Traffic: 7,400 (year 2006),  Truck Traffic: 10%,  Features Intersected: I-295 SOUTHBOUND,  Facility Carried by Structure: RI 104 FARNUM PIKE
Minimum Vertical Clearance: 6.83m (22.41ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 3,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 41.8m (137.1ft)

Find on map >>

Structure Number: 746,  Location: 0.5 Mi S of JCT RI 146 (Lat: 41.907667,  Lng: -71.512500),  Route carried "under" structure: Interstate 295,  Year Built: 1971,  Structure Length: 3.14m (10.30ft),  Average Daily Traffic: 12,500 (year 2006),  Truck Traffic: 10%,  Features Intersected: I-295 SOUTHBOUND,  Facility Carried by Structure: RI 7 DOUGLAS PIKE
Minimum Vertical Clearance: 4.97m (16.31ft),  Kilometerpoint: 0.000,  Lanes on structure: 6,  Lanes under structure: 4,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 30.2m (99.1ft)

Find on map >>

Structure Number: 7462,  Location: 0.5 Mi S of JCT RI 146 (Lat: 41.907667,  Lng: -71.512500),  Route carried "under" structure: Interstate 295,  Year Built: 1971,  Structure Length: 3.11m (10.20ft),  Average Daily Traffic: 12,500 (year 2006),  Truck Traffic: 10%,  Features Intersected: I-295 NORTHBOUND,  Facility Carried by Structure: RI 7 DOUGLAS PIKE
Minimum Vertical Clearance: 4.97m (16.31ft),  Kilometerpoint: 0.000,  Lanes on structure: 6,  Lanes under structure: 4,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 30.2m (99.1ft)

Find on map >>

Structure Number: 747,  Location: 1.0 Mi W of RI 123 (Lat: 41.891667,  Lng: -71.520167),  Route carried "under" structure: Interstate 295,  Year Built: 1967,  Structure Length: 10.03m (32.91ft),  Average Daily Traffic: 25,000 (year 2006),  Truck Traffic: 10%,  Features Intersected: I-295 NB & SB,  Facility Carried by Structure: RI 116 G WASH HWY
Minimum Vertical Clearance: 5.18m (16.99ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 6,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 39.3m (128.9ft)

Find on map >>

Structure Number: 797,  Location: 1.0 Mi S of JCT RI 116 (Lat: 41.908667,  Lng: -71.513667),  Route carried "under" structure: City street ,  Year Built: 1975,  Structure Length: 3.87m (12.70ft),  Average Daily Traffic: 6,000 (year 2006),  Truck Traffic: 10%,  Features Intersected: RAMP 5 of I-295,  Facility Carried by Structure: RAMP DOUGLAS PIKE
Minimum Vertical Clearance: 4.94m (16.21ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Lanes under structure: 1,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 38.1m (125.0ft)

Find on map >>

Structure Number: 798,  Location: 0.5 Mi E of JCT RI 116 (Lat: 41.906667,  Lng: -71.513333),  Route carried "under" structure: Ramp Interstate ,  Year Built: 1976,  Structure Length: 3.23m (10.60ft),  Average Daily Traffic: 900 (year 2006),  Truck Traffic: 10%,  Features Intersected: RAMP 5 EXIT TO RI 7,  Facility Carried by Structure: RAMP 6 ENTR I-295
Minimum Vertical Clearance: 7.08m (23.23ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Lanes under structure: 1,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 31.7m (104.0ft)

Discuss this city on our hugely popular Rhode Island forum

Back to: Smithfield, RI, Rhode Island, All US cities.


City-data.com does not guarantee the accuracy or timeliness of any information on this site.  Use at your own risk.
Some parts © 2009 Advameg, Inc.