National Bridge Inventory (NBI) Statistics
Number of bridges: 98
Total length: 887 meters (2,910ft)
Total costs: $207,624,000
Total average daily traffic: 1,432,643
Total average daily truck traffic: 166,114
National Bridge Inventory (NBI) Registered Bridges for Utica

New bridges - Historical Statistics

  • Before 1900: 1
  • 1900-1909: 0
  • 1910-1919: 0
  • 1920-1929: 1
  • 1930-1939: 4
  • 1940-1949: 0
  • 1950-1959: 14
  • 1960-1969: 30
  • 1970-1979: 8
  • 1980-1989: 29
  • 1990-1999: 11

Reconstructed bridges - Historical Statistics

  • 1940-1949: 1
  • 1950-1959: 0
  • 1960-1969: 7
  • 1970-1979: 0
  • 1980-1989: 3
  • 1990-1999: 7
  • 2000-2009: 1

Average Daily Traffic

Average Truck Traffic (%)

Bridge Condition - Deck

Bridge Condition - Superstructure

Bridge Condition - Substructure

Bridge Condition - Channel

Bridge Condition - Culverts

Find on map >>

Structure Number: 1002219,  Location: JCT 5+8 NEW HARTFORD (Lat: 43.080497,  Lng: -75.292211),  Route carried "on" structure: State highway 8,  Year Built: 1960,  Status: Open,  Structure Length: 6.76m (22.18ft),  Average Daily Traffic: 24,388 (year 2007),  Truck Traffic: 7%,  Average Future Daily Traffic: 35,236 (year 2027),  Design Load: HS 20,  Features Intersected: RTE 5
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.674,  Lanes on structure: 6,  Lanes under structure: 6,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 26.8m (87.9ft),  Skew: 22 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 19.5m (64.0ft),  Curb or Sidewalk Widths: Left: 0.4m (1.3ft),  Right: 0.4m (1.3ft),  Curb-To-Curb Width: 24.3m (79.7ft),  Out-to-Out Width: 26.6m (87.3ft)

Condition: Deck: Fair,  Superstructure: Satisfactory,  Substructure: Fair,  Operating Rating: 56.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.76m (22.18ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2007,  Bridge Improvement Cost: $3,876,000,  Roadway Improvement Cost: $2,249,000,  Total Project Cost: $6,125,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 1002221,  Location: 0.2 MI N JCT SH 5 & SH 8 (Lat: 43.081419,  Lng: -75.290225),  Route carried "on" structure: State highway 5,  Year Built: 1960,  Year Reconstructed: 1973,  Status: Open,  Structure Length: 3.77m (12.37ft),  Average Daily Traffic: 4,897 (year 1999),  Truck Traffic: 7%,  Average Future Daily Traffic: 7,075 (year 2019),  Design Load: HS 20,  Features Intersected: SAUQUOIT CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.320,  Lanes on structure: 3,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 10.9m (35.8ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 18.2m (59.7ft),  Curb or Sidewalk Widths: Left: 0.5m (1.6ft),  Right: 0.5m (1.6ft),  Curb-To-Curb Width: 15.0m (49.2ft),  Out-to-Out Width: 16.6m (54.5ft)

Condition: Deck: Fair,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 56.2 metric tons,  Method Used To Determine Operating Rating: Load Testing,  Inventory Rating: 33.6 metric tons,  Method Used To Determine Inventory Rating: Load Testing,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.77m (12.37ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2006,  Bridge Improvement Cost: $1,354,000,  Roadway Improvement Cost: $805,000,  Total Project Cost: $2,159,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 1002222,  Location: 02MI N JCT RTS 5+8 (Lat: 43.081578,  Lng: -75.290536),  Route carried "on" structure: State highway 5,  Year Built: 1960,  Year Reconstructed: 1973,  Status: Open,  Structure Length: 3.77m (12.37ft),  Average Daily Traffic: 4,897 (year 1999),  Truck Traffic: 7%,  Average Future Daily Traffic: 7,075 (year 2019),  Design Load: HS 20,  Features Intersected: SAUQUOIT CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.320,  Lanes on structure: 3,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 10.9m (35.8ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 18.2m (59.7ft),  Curb or Sidewalk Widths: Left: 0.5m (1.6ft),  Right: 0.5m (1.6ft),  Curb-To-Curb Width: 15.2m (49.9ft),  Out-to-Out Width: 16.8m (55.1ft)

Condition: Deck: Fair,  Superstructure: Good,  Substructure: Poor,  Channel: Fair,  Operating Rating: 55.3 metric tons,  Method Used To Determine Operating Rating: Load Testing,  Inventory Rating: 33.6 metric tons,  Method Used To Determine Inventory Rating: Load Testing,  Structural Evaluation: Meets minimum limits,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.77m (12.37ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2007,  Bridge Improvement Cost: $1,369,000,  Roadway Improvement Cost: $814,000,  Total Project Cost: $2,183,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 1002239,  Location: 2.3 MI S JCT SH 5 & SH 5S (Lat: 43.085603,  Lng: -75.282936),  Route carried "on" structure: State highway 5,  Year Built: 1960,  Year Reconstructed: 1995,  Status: Open,  Structure Length: 2.95m (9.68ft),  Average Daily Traffic: 36,518 (year 2000),  Truck Traffic: 7%,  Average Future Daily Traffic: 52,761 (year 2020),  Design Load: HS 20,  Features Intersected: NY SUSQUEHNNA & W
Minimum Vertical Clearance: 9.99m (32.78ft),  Kilometerpoint: 1.353,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 20.7m (67.9ft),  Skew: 26 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 29.5m (96.8ft),  Curb or Sidewalk Widths: Left: 0.4m (1.3ft),  Right: 0.4m (1.3ft),  Curb-To-Curb Width: 21.9m (71.9ft),  Out-to-Out Width: 23.4m (76.8ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Good,  Operating Rating: 58.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 38.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Underclear: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.95m (9.68ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: December 2007,  Critical Feature Inspection Date: December 2007,  Bridge Improvement Cost: $1,369,000,  Roadway Improvement Cost: $814,000,  Total Project Cost: $2,183,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 1002249,  Location: 2.2 MI S JCT RTS 5 & 5S (Lat: 43.086611,  Lng: -75.280192),  Route carried "on" structure: State highway 5,  Year Built: 1960,  Year Reconstructed: 1995,  Status: Open,  Structure Length: 6.94m (22.77ft),  Average Daily Traffic: 36,518 (year 2000),  Truck Traffic: 7%,  Average Future Daily Traffic: 52,761 (year 2020),  Design Load: HS 20,  Features Intersected: FRENCH ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.334,  Lanes on structure: 5,  Lanes under structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 25.6m (84.0ft),  Skew: 24 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 21.0m (68.9ft),  Curb-To-Curb Width: 25.1m (82.3ft),  Out-to-Out Width: 26.6m (87.3ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Fair,  Operating Rating: 61.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 34.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Better than present minimum criteria,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.94m (22.77ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2007,  Bridge Improvement Cost: $3,990,000,  Roadway Improvement Cost: $2,315,000,  Total Project Cost: $6,305,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 1002259,  Location: 1.8 MI S JCT SH 5 & SH 5S (Lat: 43.088289,  Lng: -75.276311),  Route carried "on" structure: State highway 5,  Year Built: 1960,  Year Reconstructed: 1995,  Status: Open,  Structure Length: 4.87m (15.98ft),  Average Daily Traffic: 30,051 (year 2007),  Truck Traffic: 7%,  Average Future Daily Traffic: 43,418 (year 2027),  Design Load: HS 20,  Features Intersected: FRENCH ROAD RAMP
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.762,  Lanes on structure: 5,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 24.9m (81.7ft),  Skew: 23 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 19.5m (64.0ft),  Curb-To-Curb Width: 25.1m (82.3ft),  Out-to-Out Width: 26.6m (87.3ft)

Condition: Deck: Very good,  Superstructure: Good,  Substructure: Satisfactory,  Operating Rating: 64.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 37.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.87m (15.98ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2007,  Bridge Improvement Cost: $3,990,000,  Roadway Improvement Cost: $2,315,000,  Total Project Cost: $6,305,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 1002269,  Location: 1.5 MI S JCT SH 5 & SH 5S (Lat: 43.089831,  Lng: -75.272411),  Route carried "on" structure: State highway 5,  Year Built: 1960,  Year Reconstructed: 1995,  Status: Open,  Structure Length: 7.52m (24.67ft),  Average Daily Traffic: 30,051 (year 2007),  Truck Traffic: 7%,  Average Future Daily Traffic: 43,418 (year 2027),  Design Load: HS 20,  Features Intersected: NY SUSQUEHNNA & W
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 2.135,  Lanes on structure: 6,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 31.6m (103.7ft),  Skew: 25 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 24.0m (78.7ft),  Curb-To-Curb Width: 31.2m (102.4ft),  Out-to-Out Width: 35.0m (114.8ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Good,  Inventory Rating: 61.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Underclear: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 7.52m (24.67ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2007,  Bridge Improvement Cost: $3,990,000,  Roadway Improvement Cost: $2,315,000,  Total Project Cost: $6,305,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 1002281,  Location: JCT RTS 5A+5S+5 UTICA (Lat: 43.103872,  Lng: -75.239142),  Route carried "on" structure: State highway 5,  Year Built: 1960,  Year Reconstructed: 1973,  Status: Open,  Structure Length: 38.40m (125.98ft),  Average Daily Traffic: 32,408 (year 2005),  Truck Traffic: 7%,  Average Future Daily Traffic: 46,823 (year 2025),  Design Load: HS 20,  Features Intersected: RTE 5S, COLUMBIA ST, LAF
Minimum Vertical Clearance: 5.56m (18.24ft),  Kilometerpoint: 5.038,  Lanes on structure: 2,  Lanes under structure: 9,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 19,  Length of Maximum Span: 27.1m (88.9ft),  Curb-To-Curb Width: 8.2m (26.9ft),  Out-to-Out Width: 9.2m (30.2ft)

Condition: Deck: Fair,  Superstructure: Satisfactory,  Substructure: Poor,  Operating Rating: 51.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 30.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: High priority of corrective action,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 38.40m (125.98ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2007,  Bridge Improvement Cost: $7,610,000,  Roadway Improvement Cost: $4,415,000,  Total Project Cost: $12,025,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 1002282,  Location: JCT RTS 5A+5S+5 UTICA (Lat: 43.103839,  Lng: -75.238986),  Route carried "on" structure: State highway 5,  Year Built: 1960,  Year Reconstructed: 1973,  Status: Open,  Structure Length: 38.40m (125.98ft),  Average Daily Traffic: 32,408 (year 2005),  Truck Traffic: 7%,  Average Future Daily Traffic: 46,823 (year 2025),  Design Load: HS 20,  Features Intersected: RTE 5S, COLUMBIA STREET,
Minimum Vertical Clearance: 5.53m (18.14ft),  Kilometerpoint: 5.038,  Lanes on structure: 2,  Lanes under structure: 12,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 8.2m (26.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 18,  Length of Maximum Span: 34.7m (113.8ft),  Curb or Sidewalk Widths: Left: 0.1m (0.3ft),  Right: 0.5m (1.6ft),  Curb-To-Curb Width: 8.2m (26.9ft),  Out-to-Out Width: 9.4m (30.8ft)

Condition: Deck: Fair,  Superstructure: Satisfactory,  Substructure: Poor,  Operating Rating: 55.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: High priority of corrective action,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 38.40m (125.98ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2008,  Bridge Improvement Cost: $7,812,000,  Roadway Improvement Cost: $4,532,000,  Total Project Cost: $12,344,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete
Find on map >>

Structure Number: 100228A,  Location: JCT RTS 5A+5S+5 UTICA (Lat: 43.106122,  Lng: -75.239150),  Route carried "on" structure: Ramp State highway 5,  Year Built: 1960,  Year Reconstructed: 1973,  Status: Open,  Structure Length: 10.11m (33.17ft),  Average Daily Traffic: 30,254 (year 2000),  Truck Traffic: 6%,  Average Future Daily Traffic: 36,952 (year 2020),  Design Load: HS 20,  Features Intersected: RTE 5S
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 649.038,  Lanes on structure: 1,  Lanes under structure: 5,  Owner: State Highway Agency,  Approaching Roadway Width: 6.0m (19.7ft),  Skew: 9 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 23.7m (77.8ft),  Curb or Sidewalk Widths: Left: 0.5m (1.6ft),  Right: 0.5m (1.6ft),  Curb-To-Curb Width: 6.0m (19.7ft),  Out-to-Out Width: 7.7m (25.3ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Poor,  Operating Rating: 61.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 36.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Meets minimum limits,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 10.11m (33.17ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2007,  Bridge Improvement Cost: $1,680,000,  Roadway Improvement Cost: $999,000,  Total Project Cost: $2,679,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 100228B,  Location: JCT RTS 5A+5S+5 UTICA (Lat: 43.106033,  Lng: -75.238617),  Route carried "on" structure: Ramp State highway 5,  Year Built: 1960,  Year Reconstructed: 1973,  Status: Open,  Structure Length: 5.76m (18.90ft),  Average Daily Traffic: 30,254 (year 2000),  Truck Traffic: 6%,  Average Future Daily Traffic: 36,952 (year 2020),  Design Load: HS 20,  Features Intersected: RTE 5S
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 649.038,  Lanes on structure: 1,  Lanes under structure: 5,  Owner: State Highway Agency,  Approaching Roadway Width: 6.0m (19.7ft),  Skew: 9 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 20.7m (67.9ft),  Curb or Sidewalk Widths: Left: 0.5m (1.6ft),  Right: 0.5m (1.6ft),  Curb-To-Curb Width: 6.0m (19.7ft),  Out-to-Out Width: 7.7m (25.3ft)

Condition: Deck: Fair,  Superstructure: Satisfactory,  Substructure: Fair,  Operating Rating: 73.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 24.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 5.76m (18.90ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2007,  Bridge Improvement Cost: $956,000,  Roadway Improvement Cost: $569,000,  Total Project Cost: $1,525,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 1002291,  Location: JCT.RTES 5 & 5S (Lat: 43.108208,  Lng: -75.238658),  Route carried "on" structure: State highway 5,  Year Built: 1990,  Status: Open,  Structure Length: 9.78m (32.09ft),  Average Daily Traffic: 13,175 (year 2007),  Truck Traffic: 21%,  Average Future Daily Traffic: 20,254 (year 2027),  Design Load: HS 20,  Features Intersected: CSX TRANS/AMTRAK, NY SUS
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 5.583,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.1m (39.7ft),  Skew: 9 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 48.4m (158.8ft),  Curb-To-Curb Width: 12.0m (39.4ft),  Out-to-Out Width: 12.9m (42.3ft)

Condition: Deck: Very good,  Superstructure: Excellent,  Substructure: Very good,  Operating Rating: 76.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 40.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Equal to present minimum criteria,  Underclear: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 9.78m (32.09ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2006,  Bridge Improvement Cost: $956,000,  Roadway Improvement Cost: $569,000,  Total Project Cost: $1,525,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 1002292,  Location: JCT.RTES 5 & 5S (Lat: 43.108150,  Lng: -75.238486),  Route carried "on" structure: State highway 5,  Year Built: 1990,  Status: Open,  Structure Length: 9.78m (32.09ft),  Average Daily Traffic: 13,175 (year 2007),  Truck Traffic: 21%,  Average Future Daily Traffic: 20,254 (year 2027),  Design Load: HS 20,  Features Intersected: CSX TRANS/AMTRAK, NY SUS
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 5.583,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.1m (39.7ft),  Skew: 9 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 48.4m (158.8ft),  Curb-To-Curb Width: 12.0m (39.4ft),  Out-to-Out Width: 12.9m (42.3ft)

Condition: Deck: Excellent,  Superstructure: Excellent,  Substructure: Good,  Operating Rating: 76.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 40.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Underclear: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 9.78m (32.09ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2006,  Bridge Improvement Cost: $956,000,  Roadway Improvement Cost: $569,000,  Total Project Cost: $1,525,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 1002301,  Location: .5 MI N JCT SH 5 & SH 5S (Lat: 43.111719,  Lng: -75.236625),  Route carried "on" structure: Interstate 790,  Year Built: 1989,  Status: Open,  Structure Length: 18.04m (59.19ft),  Average Daily Traffic: 13,175 (year 2007),  Truck Traffic: 21%,  Average Future Daily Traffic: 20,254 (year 2027),  Design Load: HS 20,  Features Intersected: MOHAWK ADIR & NO, MOHAWK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.650,  Lanes on structure: 3,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 16.7m (54.8ft),  Skew: 5 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 49.6m (162.7ft),  Curb-To-Curb Width: 16.7m (54.8ft),  Out-to-Out Width: 19.2m (63.0ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Satisfactory,  Channel: Very good,  Inventory Rating: 59.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Underclear: Better than present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 18.04m (59.19ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2007,  Bridge Improvement Cost: $956,000,  Roadway Improvement Cost: $569,000,  Total Project Cost: $1,525,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 1002302,  Location: .5 MI N JCT SH 5 & SH 5S (Lat: 43.111689,  Lng: -75.236378),  Route carried "on" structure: Interstate 790,  Year Built: 1989,  Status: Open,  Structure Length: 18.50m (60.70ft),  Average Daily Traffic: 11,312 (year 2007),  Truck Traffic: 21%,  Average Future Daily Traffic: 17,390 (year 2027),  Design Load: HS 20,  Features Intersected: MOHAWK ADIR & NO, MOHAWK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.934,  Lanes on structure: 3,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 15.8m (51.8ft),  Skew: 5 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 60.0m (196.9ft),  Curb-To-Curb Width: 15.6m (51.2ft),  Out-to-Out Width: 16.6m (54.5ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Good,  Channel: Very good,  Operating Rating: 84.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 50.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: High priority of corrective action,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 18.50m (60.70ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: June 2007,  Underwater Inspection Date: September 2000,  Bridge Improvement Cost: $956,000,  Roadway Improvement Cost: $569,000,  Total Project Cost: $1,525,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 1002321,  Location: JCT OF I90 & I790 (Lat: 43.122019,  Lng: -75.230839),  Route carried "on" structure: State highway 8,  Year Built: 1988,  Status: Open,  Structure Length: 10.72m (35.17ft),  Average Daily Traffic: 11,312 (year 2007),  Truck Traffic: 21%,  Average Future Daily Traffic: 17,390 (year 2027),  Design Load: HS 20,  Features Intersected: RTE I90, RTE I790
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 7.960,  Lanes on structure: 3,  Lanes under structure: 9,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.4m (40.7ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 39.6m (129.9ft),  Curb-To-Curb Width: 12.6m (41.3ft),  Out-to-Out Width: 13.6m (44.6ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Good,  Operating Rating: 98.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 59.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 10.72m (35.17ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2006,  Bridge Improvement Cost: $956,000,  Roadway Improvement Cost: $569,000,  Total Project Cost: $1,525,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 1002322,  Location: JCT OF I90 & I790 (Lat: 43.121911,  Lng: -75.230469),  Route carried "on" structure: State highway 8,  Year Built: 1988,  Status: Open,  Structure Length: 10.72m (35.17ft),  Average Daily Traffic: 10,029 (year 2007),  Truck Traffic: 7%,  Average Future Daily Traffic: 14,490 (year 2027),  Design Load: HS 20,  Features Intersected: RTE I90, RTE I790
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 8.394,  Lanes on structure: 3,  Lanes under structure: 9,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 15.8m (51.8ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 39.6m (129.9ft),  Curb-To-Curb Width: 15.6m (51.2ft),  Out-to-Out Width: 16.6m (54.5ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Satisfactory,  Operating Rating: 99.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 59.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 10.72m (35.17ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2006,  Bridge Improvement Cost: $956,000,  Roadway Improvement Cost: $569,000,  Total Project Cost: $1,525,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 1002341,  Location: .2 MILE N JCT I90 & S H 8 (Lat: 43.123689,  Lng: -75.229581),  Route carried "on" structure: State highway ,  Year Built: 1988,  Status: Open,  Structure Length: 7.89m (25.89ft),  Average Daily Traffic: 25,400 (year 1980),  Truck Traffic: 6%,  Average Future Daily Traffic: 31,024 (year 2000),  Design Load: HS 20,  Features Intersected: RTE I790, RTE I790, RIVE,  Facility Carried by Structure: Other road 8 2
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 651.259,  Lanes on structure: 3,  Lanes under structure: 6,  Owner: State Highway Agency,  Approaching Roadway Width: 15.5m (50.9ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 26.5m (86.9ft),  Curb-To-Curb Width: 15.6m (51.2ft),  Out-to-Out Width: 16.6m (54.5ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Good,  Operating Rating: 69.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 41.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 7.89m (25.89ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2006,  Bridge Improvement Cost: $956,000,  Roadway Improvement Cost: $569,000,  Total Project Cost: $1,525,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete
Find on map >>

Structure Number: 1002342,  Location: .2 MI N.JCT. 90I & RTE 8 (Lat: 43.123572,  Lng: -75.229239),  Route carried "on" structure: State highway ,  Year Built: 1988,  Status: Open,  Structure Length: 7.34m (24.08ft),  Average Daily Traffic: 25,400 (year 1980),  Truck Traffic: 6%,  Average Future Daily Traffic: 31,024 (year 2000),  Design Load: HS 20,  Features Intersected: RTE I790, RTE I790, Rive,  Facility Carried by Structure: RTS 8&12 NB
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 651.259,  Lanes on structure: 3,  Lanes under structure: 6,  Owner: State Highway Agency,  Approaching Roadway Width: 16.1m (52.8ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 24.9m (81.7ft),  Curb-To-Curb Width: 15.6m (51.2ft),  Out-to-Out Width: 16.6m (54.5ft)

Condition: Deck: Excellent,  Superstructure: Excellent,  Substructure: Very good,  Operating Rating: 78.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 47.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Equal to present minimum criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 7.34m (24.08ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2006,  Bridge Improvement Cost: $956,000,  Roadway Improvement Cost: $569,000,  Total Project Cost: $1,525,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete
Find on map >>

Structure Number: 1002351,  Location: .2 MI S JCT SH 5 & SH921 (Lat: 43.116022,  Lng: -75.212847),  Route carried "on" structure: City street ,  Year Built: 1963,  Status: Open,  Structure Length: 1.15m (3.77ft),  Average Daily Traffic: 5,770 (year 1992),  Truck Traffic: 6%,  Average Future Daily Traffic: 7,189 (year 2012),  Design Load: HS 20,  Features Intersected: REALL CREEK,  Facility Carried by Structure: RIVER ROAD WB
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 3,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 10.9m (35.8ft),  Skew: 14 degrees,  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 5.7m (18.7ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 1.4m (4.6ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 14.6m (47.9ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 76.7 metric tons,  Inventory Rating: 32.6 metric tons,  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.15m (3.77ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2007,  Bridge Improvement Cost: $366,000,  Roadway Improvement Cost: $218,000,  Total Project Cost: $584,000 ( Estimate for 2007),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 1002352,  Location: .2 MI S JCT SH 5 & SH921 (Lat: 43.116728,  Lng: -75.212397),  Route carried "on" structure: State highway ,  Year Built: 1963,  Status: Open,  Structure Length: 1.15m (3.77ft),  Average Daily Traffic: 5,770 (year 1992),  Truck Traffic: 6%,  Average Future Daily Traffic: 7,047 (year 2012),  Design Load: HS 20,  Features Intersected: REALL CREEK,  Facility Carried by Structure: RIVER ROAD EB
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 652.852,  Lanes on structure: 3,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 10.9m (35.8ft),  Skew: 11 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 5.7m (18.7ft),  Curb or Sidewalk Widths: Left: 1.4m (4.6ft),  Right: 1.4m (4.6ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 14.5m (47.6ft)

Condition: Channel: Fair,  Culverts: Good,  Operating Rating: 76.7 metric tons,  Inventory Rating: 32.6 metric tons,  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.15m (3.77ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2007,  Bridge Improvement Cost: $363,000,  Roadway Improvement Cost: $216,000,  Total Project Cost: $579,000 ( Estimate for 2007),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 1051439,  Location: 2.4 MI E JCT SH 5A & SH5S (Lat: 43.096183,  Lng: -75.192692),  Route carried "on" structure: Ramp State highway ,  Year Built: 1968,  Status: Open,  Structure Length: 5.73m (18.80ft),  Average Daily Traffic: 3,637 (year 1999),  Truck Traffic: 3%,  Average Future Daily Traffic: 4,510 (year 2019),  Design Load: HS 20,  Features Intersected: RTE 5S,  Facility Carried by Structure: CULVER AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 6,  Owner: State Highway Agency,  Approaching Roadway Width: 10.9m (35.8ft),  Skew: 20 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 28.3m (92.8ft),  Curb or Sidewalk Widths: Left: 0.4m (1.3ft),  Right: 0.4m (1.3ft),  Curb-To-Curb Width: 10.9m (35.8ft),  Out-to-Out Width: 12.4m (40.7ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Operating Rating: 67.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 39.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 5.73m (18.80ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2007,  Bridge Improvement Cost: $1,534,000,  Roadway Improvement Cost: $912,000,  Total Project Cost: $2,446,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 1051441,  Location: 2.7 MI E JCT SH5A & SH5S (Lat: 43.092444,  Lng: -75.184961),  Route carried "on" structure: State highway 5S,  Year Built: 1968,  Status: Open,  Structure Length: 3.35m (10.99ft),  Average Daily Traffic: 8,773 (year 2007),  Truck Traffic: 7%,  Average Future Daily Traffic: 12,675 (year 2027),  Design Load: HS 20,  Features Intersected: PITCHER STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.956,  Lanes on structure: 3,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Skew: 10 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 32.0m (105.0ft),  Curb or Sidewalk Widths: Left: 0.4m (1.3ft),  Right: 0.4m (1.3ft),  Curb-To-Curb Width: 11.5m (37.7ft),  Out-to-Out Width: 13.0m (42.7ft)

Condition: Deck: Satisfactory,  Superstructure: Very good,  Substructure: Good,  Operating Rating: 62.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 37.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of replacement,  Underclear: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.35m (10.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2007,  Bridge Improvement Cost: $1,534,000,  Roadway Improvement Cost: $912,000,  Total Project Cost: $2,446,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 1051442,  Location: 2.7 MI E JCT SH5A & SH5S (Lat: 43.092369,  Lng: -75.185058),  Route carried "on" structure: State highway 5S,  Year Built: 1968,  Status: Open,  Structure Length: 3.35m (10.99ft),  Average Daily Traffic: 8,773 (year 2007),  Truck Traffic: 7%,  Average Future Daily Traffic: 12,675 (year 2027),  Design Load: HS 20,  Features Intersected: PITCHER STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.956,  Lanes on structure: 3,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Skew: 10 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 32.0m (105.0ft),  Curb or Sidewalk Widths: Left: 0.4m (1.3ft),  Right: 0.4m (1.3ft),  Curb-To-Curb Width: 11.6m (38.1ft),  Out-to-Out Width: 13.1m (43.0ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Satisfactory,  Operating Rating: 63.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 38.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.35m (10.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2007,  Bridge Improvement Cost: $1,534,000,  Roadway Improvement Cost: $912,000,  Total Project Cost: $2,446,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 105173,  Location: 04MI S JCT RTS 5+921C (Lat: 43.113481,  Lng: -75.214133),  Route carried "on" structure: Other road 921C,  Year Built: 1968,  Year Reconstructed: 1998,  Status: Open,  Structure Length: 1.34m (4.40ft),  Average Daily Traffic: 34,145 (year 2005),  Truck Traffic: 6%,  Average Future Daily Traffic: 41,705 (year 2025),  Design Load: HS 20,  Features Intersected: REALL CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.796,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 15.8m (51.8ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 12.1m (39.7ft),  Curb or Sidewalk Widths: Left: 2.4m (7.9ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 15.8m (51.8ft),  Out-to-Out Width: 20.5m (67.3ft)

Condition: Deck: Excellent,  Superstructure: Excellent,  Substructure: Very good,  Channel: Satisfactory,  Operating Rating: 72.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 42.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.34m (4.40ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2007,  Bridge Improvement Cost: $1,148,000,  Roadway Improvement Cost: $683,000,  Total Project Cost: $1,831,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 1054309,  Location: 1.6 MI S JCT RTS 5 & 5A (Lat: 43.092508,  Lng: -75.263244),  Route carried "on" structure: Other road 921B,  Year Built: 1975,  Status: Open,  Structure Length: 10.45m (34.28ft),  Average Daily Traffic: 23,350 (year 2005),  Truck Traffic: 6%,  Average Future Daily Traffic: 28,520 (year 2025),  Design Load: HS 20,  Features Intersected: NO.SO. ARTERIAL, NY SUSQ
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.930,  Lanes on structure: 6,  Lanes under structure: 6,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 28.6m (93.8ft),  Skew: 34 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 36.5m (119.8ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 0.0m,  Curb-To-Curb Width: 28.6m (93.8ft),  Out-to-Out Width: 30.9m (101.4ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Fair,  Operating Rating: 49.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 29.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Superior to present desirable criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 10.45m (34.28ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2007,  Bridge Improvement Cost: $6,963,000,  Roadway Improvement Cost: $4,039,000,  Total Project Cost: $11,002,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 10736,  Location: 2 MI E.INTERS RTS 90I & 8 (Lat: 43.115069,  Lng: -75.211275),  Route carried "on" structure: Interstate 790,  Year Built: 1989,  Status: Open,  Structure Length: 5.15m (16.90ft),  Average Daily Traffic: 9,554 (year 2007),  Truck Traffic: 21%,  Average Future Daily Traffic: 14,687 (year 2027),  Design Load: HS 20,  Features Intersected: RTE 921C
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.707,  Lanes on structure: 3,  Lanes under structure: 5,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 15.8m (51.8ft),  Skew: 1 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 25.9m (85.0ft),  Curb-To-Curb Width: 15.6m (51.2ft),  Out-to-Out Width: 16.6m (54.5ft)

Condition: Deck: Excellent,  Superstructure: Very good,  Substructure: Very good,  Operating Rating: 77.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 46.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 5.15m (16.90ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2007,  Bridge Improvement Cost: $1,101,000,  Roadway Improvement Cost: $655,000,  Total Project Cost: $1,756,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 107366,  Location: .1 MI E OF RTES 5 8&12INT (Lat: 43.123114,  Lng: -75.227831),  Route carried "on" structure: Ramp Other road ,  Year Built: 1989,  Status: Open,  Structure Length: 7.25m (23.79ft),  Average Daily Traffic: 9,360 (year 2001),  Truck Traffic: 21%,  Average Future Daily Traffic: 14,389 (year 2021),  Design Load: HS 20,  Features Intersected: RM FM 8NB TO 49WB, I790,  Facility Carried by Structure: RM FM 5WB TO 12NB
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Lanes under structure: 8,  Owner: State Highway Agency,  Approaching Roadway Width: 7.6m (24.9ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 24.3m (79.7ft),  Curb-To-Curb Width: 7.4m (24.3ft),  Out-to-Out Width: 8.4m (27.6ft)

Condition: Deck: Excellent,  Superstructure: Excellent,  Substructure: Good,  Operating Rating: 93.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 56.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 7.25m (23.79ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2006,  Bridge Improvement Cost: $1,101,000,  Roadway Improvement Cost: $655,000,  Total Project Cost: $1,756,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 107367,  Location: 1MI EAST OF RTES 8 12&5 (Lat: 43.113042,  Lng: -75.212153),  Route carried "on" structure: Interstate 790,  Year Built: 1989,  Status: Open,  Structure Length: 6.52m (21.39ft),  Average Daily Traffic: 29,575 (year 1989),  Truck Traffic: 21%,  Average Future Daily Traffic: 45,466 (year 2009),  Design Load: HS 20,  Features Intersected: NORTH GENESEE ST.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 3,  Lanes under structure: 5,  Owner: State Highway Agency,  Approaching Roadway Width: 14.9m (48.9ft),  Skew: 1 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 30.4m (99.7ft),  Curb-To-Curb Width: 14.6m (47.9ft),  Out-to-Out Width: 15.5m (50.9ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Good,  Operating Rating: 84.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 49.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.52m (21.39ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2006,  Bridge Improvement Cost: $1,101,000,  Roadway Improvement Cost: $655,000,  Total Project Cost: $1,756,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 10737,  Location: .25 MI E OF N-S ART & I90 (Lat: 43.121003,  Lng: -75.227936),  Route carried "on" structure: Ramp Other road ,  Year Built: 1989,  Status: Open,  Structure Length: 10.42m (34.19ft),  Average Daily Traffic: 5,108 (year 2001),  Truck Traffic: 21%,  Average Future Daily Traffic: 7,853 (year 2021),  Design Load: HS 20,  Features Intersected: RTE I90, RTE I790, 790 E,  Facility Carried by Structure: FROM SH8 &SH12 NB
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 10,  Owner: State Highway Agency,  Approaching Roadway Width: 12.1m (39.7ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 39.3m (128.9ft),  Curb-To-Curb Width: 12.0m (39.4ft),  Out-to-Out Width: 12.9m (42.3ft)

Condition: Deck: Very good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 54.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 10.42m (34.19ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2006,  Bridge Improvement Cost: $1,101,000,  Roadway Improvement Cost: $655,000,  Total Project Cost: $1,756,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 107371,  Location: .1 MI W JCT SH 5/8 & SH12 (Lat: 43.123089,  Lng: -75.233497),  Route carried "on" structure: Ramp Other road 790,  Year Built: 1989,  Status: Open,  Structure Length: 14.08m (46.19ft),  Average Daily Traffic: 922 (year 2001),  Truck Traffic: 21%,  Average Future Daily Traffic: 1,417 (year 2021),  Design Load: HS 20,  Features Intersected: RTE I90, RTE 49
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 11,  Owner: State Highway Agency,  Approaching Roadway Width: 12.1m (39.7ft),  Skew: 1 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 69.4m (227.7ft),  Curb-To-Curb Width: 12.0m (39.4ft),  Out-to-Out Width: 12.9m (42.3ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Serious,  Operating Rating: 64.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 38.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: High priority of corrective action,  Deck Geometry: Superior to present desirable criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 14.08m (46.19ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2006,  Bridge Improvement Cost: $1,101,000,  Roadway Improvement Cost: $655,000,  Total Project Cost: $1,756,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 107385,  Location: JCT SH 5 & SH 5S (Lat: 43.108311,  Lng: -75.239267),  Route carried "on" structure: Ramp Interstate ,  Year Built: 1990,  Status: Open,  Structure Length: 7.95m (26.08ft),  Average Daily Traffic: 8,771 (year 1997),  Truck Traffic: 21%,  Average Future Daily Traffic: 13,484 (year 2017),  Design Load: HS 20,  Features Intersected: CSX TRANS/AMTRAK, NY SUS,  Facility Carried by Structure: FROM I790 S.B.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 10.3m (33.8ft),  Skew: 3 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 39.0m (128.0ft),  Curb-To-Curb Width: 10.3m (33.8ft),  Out-to-Out Width: 11.3m (37.1ft)

Condition: Deck: Excellent,  Superstructure: Excellent,  Substructure: Good,  Operating Rating: 82.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 39.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Underclear: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 7.95m (26.08ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2006,  Bridge Improvement Cost: $351,000,  Roadway Improvement Cost: $209,000,  Total Project Cost: $560,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 107386,  Location: JCT SH 5 & SH 5S (Lat: 43.107856,  Lng: -75.237044),  Route carried "on" structure: Ramp Interstate ,  Year Built: 1990,  Status: Open,  Structure Length: 8.65m (28.38ft),  Average Daily Traffic: 7,376 (year 1997),  Truck Traffic: 21%,  Average Future Daily Traffic: 11,339 (year 2017),  Design Load: HS 20,  Features Intersected: CSX TRANS/AMTRAK, NY SUS,  Facility Carried by Structure: TO I790 NORTHBND
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: State Highway Agency,  Approaching Roadway Width: 9.4m (30.8ft),  Skew: 1 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 49.9m (163.7ft),  Curb-To-Curb Width: 9.5m (31.2ft),  Out-to-Out Width: 10.5m (34.4ft)

Condition: Deck: Very good,  Superstructure: Excellent,  Substructure: Satisfactory,  Operating Rating: 94.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 56.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Underclear: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 8.65m (28.38ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2006,  Bridge Improvement Cost: $351,000,  Roadway Improvement Cost: $209,000,  Total Project Cost: $560,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 107387,  Location: JCT SH 5 & SH 5S (Lat: 43.106478,  Lng: -75.240753),  Route carried "on" structure: Ramp Interstate ,  Year Built: 1990,  Status: Open,  Structure Length: 10.45m (34.28ft),  Average Daily Traffic: 5,814 (year 1998),  Truck Traffic: 21%,  Average Future Daily Traffic: 8,938 (year 2018),  Design Load: HS 20,  Features Intersected: RTE 5S,  Facility Carried by Structure: FROM I790 SOUTHBD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 4,  Owner: State Highway Agency,  Approaching Roadway Width: 11.5m (37.7ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 52.7m (172.9ft),  Curb-To-Curb Width: 11.5m (37.7ft),  Out-to-Out Width: 12.5m (41.0ft)

Condition: Deck: Very good,  Superstructure: Excellent,  Substructure: Very good,  Operating Rating: 79.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 39.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Superior to present desirable criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 10.45m (34.28ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2006,  Bridge Improvement Cost: $351,000,  Roadway Improvement Cost: $209,000,  Total Project Cost: $560,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 107388,  Location: JCT SH 5 & SH 5S (Lat: 43.105433,  Lng: -75.237197),  Route carried "on" structure: Ramp Interstate ,  Year Built: 1990,  Status: Open,  Structure Length: 4.45m (14.60ft),  Average Daily Traffic: 6,757 (year 2001),  Truck Traffic: 21%,  Average Future Daily Traffic: 10,388 (year 2021),  Design Load: HS 20,  Features Intersected: RTE 5S,  Facility Carried by Structure: TO ROUTES 5-8-12
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 4,  Owner: State Highway Agency,  Approaching Roadway Width: 14.3m (46.9ft),  Skew: 21 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 23.4m (76.8ft),  Curb-To-Curb Width: 14.0m (45.9ft),  Out-to-Out Width: 15.6m (51.2ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Good,  Operating Rating: 70.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 35.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.45m (14.60ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2006,  Bridge Improvement Cost: $351,000,  Roadway Improvement Cost: $209,000,  Total Project Cost: $560,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Structure Number: 107877,  Location: Route 5S WB Ramps,  Route carried "on" structure: Ramp State highway ,  Year Built: 1968,  Status: Open,  Structure Length: 0.85m (2.79ft),  Truck Traffic: 7%,  Design Load: H 20,  Features Intersected: Starch Factory Ck,  Facility Carried by Structure: Rt. 5S WB Ramp
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 15.2m (49.9ft),  Skew: 24 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.0m (23.0ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 74.7 metric tons,  Inventory Rating: 32.6 metric tons,  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.85m (2.79ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2006,  Bridge Improvement Cost: $291,000,  Roadway Improvement Cost: $173,000,  Total Project Cost: $464,000 ( Estimate for 2007),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 1090509,  Location: 02MI N JCT RTS 5S+921C (Lat: 43.104581,  Lng: -75.224939),  Route carried "on" structure: Other road 921C,  Year Built: 1973,  Status: Open,  Structure Length: 38.40m (125.98ft),  Average Daily Traffic: 7,736 (year 2007),  Truck Traffic: 6%,  Average Future Daily Traffic: 9,449 (year 2027),  Design Load: HS 20,  Features Intersected: LEE STREET-RAMP, CSX/AMT
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.339,  Lanes on structure: 3,  Lanes under structure: 6,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 17.6m (57.7ft),  Skew: 39 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 13,  Length of Maximum Span: 46.0m (150.9ft),  Curb-To-Curb Width: 16.1m (52.8ft),  Out-to-Out Width: 17.0m (55.8ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Fair,  Operating Rating: 78.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 46.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Better than present minimum criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 38.40m (125.98ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2007,  Bridge Improvement Cost: $14,112,000,  Roadway Improvement Cost: $8,187,000,  Total Project Cost: $22,299,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 109050A,  Location: .2 MI N JCT SH 5S & 921C (Lat: 43.104350,  Lng: -75.224850),  Route carried "on" structure: Ramp City street ,  Year Built: 1973,  Status: Open,  Structure Length: 11.55m (37.89ft),  Average Daily Traffic: 9,300 (year 2003),  Truck Traffic: 6%,  Average Future Daily Traffic: 11,587 (year 2023),  Design Load: HS 20,  Features Intersected: RR PARKING LOT,  Facility Carried by Structure: RAMP TO RT921C NB
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 8.8m (28.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 30.7m (100.7ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 0.0m,  Curb-To-Curb Width: 8.8m (28.9ft),  Out-to-Out Width: 11.1m (36.4ft)

Condition: Deck: Very good,  Superstructure: Good,  Substructure: Poor,  Operating Rating: 91.2 metric tons,  Inventory Rating: 32.6 metric tons,  Structural Evaluation: Meets minimum limits,  Deck Geometry: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 11.55m (37.89ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2007,  Bridge Improvement Cost: $2,767,000,  Roadway Improvement Cost: $1,605,000,  Total Project Cost: $4,372,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 109051,  Location: .2 MI N JCT SH 5S & 921C (Lat: 43.105544,  Lng: -75.224542),  Route carried "on" structure: Ramp City street ,  Year Built: 1973,  Status: Open,  Structure Length: 17.43m (57.19ft),  Average Daily Traffic: 8,681 (year 1997),  Truck Traffic: 6%,  Average Future Daily Traffic: 10,816 (year 2017),  Design Load: HS 20,  Features Intersected: CSX TRANS/ AMTRAK,  Facility Carried by Structure: WHITESBORO EXIT
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 8.8m (28.9ft),  Skew: 3 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 48.7m (159.8ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 0.0m,  Curb-To-Curb Width: 8.8m (28.9ft),  Out-to-Out Width: 11.1m (36.4ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Fair,  Operating Rating: 87.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 52.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 17.43m (57.19ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2008,  Bridge Improvement Cost: $4,176,000,  Roadway Improvement Cost: $2,422,000,  Total Project Cost: $6,598,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 109053,  Location: 1.6 MI S JCT SH 5 & SH 5A (Lat: 43.091686,  Lng: -75.268169),  Route carried "on" structure: Ramp State highway ,  Year Built: 1975,  Status: Open,  Structure Length: 5.54m (18.18ft),  Average Daily Traffic: 4,009 (year 1997),  Truck Traffic: 6%,  Average Future Daily Traffic: 4,897 (year 2017),  Design Load: HS 20,  Features Intersected: NY SUSQUEHNNA & W,  Facility Carried by Structure: RAMP TO N S ART
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: State Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 21.6m (70.9ft),  Curb or Sidewalk Widths: Left: 0.1m (0.3ft),  Right: 0.1m (0.3ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 7.6m (24.9ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Good,  Operating Rating: 84.9 metric tons,  Inventory Rating: 32.6 metric tons,  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Underclear: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 5.54m (18.18ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2007,  Bridge Improvement Cost: $4,176,000,  Roadway Improvement Cost: $2,422,000,  Total Project Cost: $6,598,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 109054,  Location: 1.6 MI S JCT RTS 5 & 5A (Lat: 43.091578,  Lng: -75.268611),  Route carried "on" structure: Ramp State highway ,  Year Built: 1975,  Status: Open,  Structure Length: 6.67m (21.88ft),  Average Daily Traffic: 4,176 (year 1997),  Truck Traffic: 6%,  Average Future Daily Traffic: 5,101 (year 2017),  Design Load: HS 20,  Features Intersected: NY SUSQUEHANNA& W,  Facility Carried by Structure: RAMP FROM N-S ART
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: State Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 24.0m (78.7ft),  Curb or Sidewalk Widths: Left: 0.1m (0.3ft),  Right: 0.1m (0.3ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 7.6m (24.9ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Good,  Operating Rating: 84.7 metric tons,  Inventory Rating: 32.6 metric tons,  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Underclear: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.67m (21.88ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2007,  Bridge Improvement Cost: $4,176,000,  Roadway Improvement Cost: $2,422,000,  Total Project Cost: $6,598,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 109428,  Location: BARNES AVE UTICA N OF 5A (Lat: 43.111600,  Lng: -75.244731),  Route carried "on" structure: Other road 921F,  Year Built: 1935,  Status: Posted for load-capacity,  Structure Length: 4.02m (13.19ft),  Average Daily Traffic: 858 (year 1998),  Truck Traffic: 3%,  Average Future Daily Traffic: 1,064 (year 2018),  Design Load: H 20,  Features Intersected: MOHAWK RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 39.6m (129.9ft),  Curb or Sidewalk Widths: Left: 0.0m,  Right: 1.6m (5.2ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 10.3m (33.8ft)

Condition: Deck: Poor,  Superstructure: Fair,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 55.3 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 24.5 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Meets minimum limits,  Length Of Structure Improvement: 4.02m (13.19ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: September 2007,  Critical Feature Inspection Date: September 2007,  Bridge Improvement Cost: $895,000,  Roadway Improvement Cost: $532,000,  Total Project Cost: $1,427,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous

Parts: 1, 2

Discuss this city on our hugely popular New York forum

Back to: Utica, NY, New York, All US cities.


City-data.com does not guarantee the accuracy or timeliness of any information on this site.  Use at your own risk.
Some parts © 2009 Advameg, Inc.