Jump to a detailed profile or search site with Google Custom Search

Bridge Statistics for Weston, Vermont (VT)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 10Number of bridges
  • 52ft / 16.0mTotal length
  • $1,886,000Total costs
  • 6,805Total average daily traffic
  • 585Total average daily truck traffic
  • 7,148Total future (year 2027) average daily traffic
  • National Bridge Inventory (NBI) Registered Bridges for Weston
  • No street view available for this location

New bridges in Weston, VT - historical statistics
  • New bridges - historical statistics
  • 21930-1939
  • 31940-1949
  • 21960-1969
  • 21970-1979
  • 12010-2019
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 37.5%Very good
  • 37.5%Good
  • 25.0%Satisfactory
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 37.5%Very good
  • 50.0%Good
  • 12.5%Fair
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 37.5%Very good
  • 50.0%Good
  • 12.5%Satisfactory
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 40.0%Very good
  • 40.0%Good
  • 20.0%Satisfactory
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 50.0%Good
  • 50.0%Satisfactory
Find on map >>   Show street view

Structure Number: 101421002414211,  Location: 0.4 MI TO JCT W VT100 (Lat: 43.320297,  Lng: -72.793956),  Route carried "on" structure: Other road C3007,  Year Built: 1946,  Status: Open,  Structure Length: 1.34m (4.40ft),  Average Daily Traffic: 30 (year 2019),  Truck Traffic: 2%,  Average Future Daily Traffic: 32 (year 2029),  Features Intersected: GREENDALE BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 4.9m (16.1ft),  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 12.5m (41.0ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 4.0m (13.1ft),  Out-to-Out Width: 4.5m (14.8ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 37.2 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 22.7 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.34m (4.40ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2021,  Bridge Improvement Cost: $229,000,  Roadway Improvement Cost: $50,000,  Total Project Cost: $280,000 ( Estimate for 2020),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 101421002614211,  Location: 2.71 MI TO JCT W VT100 (Lat: 43.346636,  Lng: -72.816592),  Route carried "on" structure: Other road C3007,  Year Built: 1940,  Status: Posted for load,  Structure Length: 1.58m (5.18ft),  Average Daily Traffic: 10 (year 2019),  Truck Traffic: 2%,  Average Future Daily Traffic: 11 (year 2029),  Design Load: HS 15,  Features Intersected: GREENDALE BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 4.3m (14.1ft),  Skew: 3 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 15.2m (49.9ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 4.3m (14.1ft),  Out-to-Out Width: 5.0m (16.4ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 55.3 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 35.4 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.58m (5.18ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2021,  Bridge Improvement Cost: $300,000,  Roadway Improvement Cost: $50,000,  Total Project Cost: $350,000 ( Estimate for 2020),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 101421002714211,  Location: @ JCT W CL3 TH16 (Lat: 43.339875,  Lng: -72.810283),  Route carried "on" structure: Other road C3007,  Year Built: 1935,  Status: Open,  Structure Length: 1.58m (5.18ft),  Average Daily Traffic: 15 (year 2019),  Truck Traffic: 2%,  Average Future Daily Traffic: 16 (year 2029),  Design Load: HS 15,  Features Intersected: JENNY COOLIDGE BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 15.2m (49.9ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 6.6m (21.7ft),  Out-to-Out Width: 6.7m (22.0ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Good,  Channel: Good,  Operating Rating: 21.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 12.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.58m (5.18ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2021,  Bridge Improvement Cost: $400,000,  Roadway Improvement Cost: $50,000,  Total Project Cost: $450,000 ( Estimate for 2020),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 101421002814211,  Location: 0.02 MI TO JCT W C3 TH11 (Lat: 43.315736,  Lng: -72.790767),  Route carried "on" structure: Other road C3007,  Year Built: 1969,  Status: Open,  Structure Length: 0.73m (2.40ft),  Average Daily Traffic: 50 (year 2019),  Truck Traffic: 2%,  Average Future Daily Traffic: 53 (year 2029),  Design Load: H 20,  Features Intersected: GREENDALE BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.6m (24.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.1m (20.0ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 37.2 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 22.7 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 21 months,  Inspection Date: September 2021
Find on map >>   Show street view

Structure Number: 101421002914211,  Location: 0.06 MI TO JCT W VT100 (Lat: 43.317314,  Lng: -72.788058),  Route carried "on" structure: Other road C3011,  Year Built: 1939,  Status: Open,  Structure Length: 2.10m (6.89ft),  Average Daily Traffic: 150 (year 2019),  Truck Traffic: 2%,  Average Future Daily Traffic: 158 (year 2029),  Design Load: H 15,  Features Intersected: WEST RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.0m (23.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 20.4m (66.9ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 5.9m (19.4ft),  Out-to-Out Width: 6.1m (20.0ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Channel: Very good,  Operating Rating: 30.8 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 13.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Meets minimum limits,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.10m (6.89ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2021,  Bridge Improvement Cost: $483,000,  Roadway Improvement Cost: $50,000,  Total Project Cost: $533,000 ( Estimate for 2020),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 101421003714211,  Location: 3.41 MI TO JCT W VT100 (Lat: 43.354028,  Lng: -72.824986),  Route carried "on" structure: Other road C3007,  Year Built: 1940,  Status: Open,  Structure Length: 1.19m (3.90ft),  Average Daily Traffic: 10 (year 2019),  Truck Traffic: 2%,  Average Future Daily Traffic: 11 (year 2029),  Design Load: H 15,  Features Intersected: GREENDALE BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 4.3m (14.1ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 10.7m (35.1ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 4.3m (14.1ft),  Out-to-Out Width: 5.0m (16.4ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 64.4 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 42.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.19m (3.90ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2021,  Bridge Improvement Cost: $222,000,  Roadway Improvement Cost: $50,000,  Total Project Cost: $273,000 ( Estimate for 2020),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 200013009214212,  Location: 2.6 MI N JCT. VT.11 W (Lat: 43.255756,  Lng: -72.791392),  Route carried "on" structure: State highway 100,  Year Built: 1975,  Status: Open,  Structure Length: 3.44m (11.29ft),  Average Daily Traffic: 2,800 (year 2018),  Truck Traffic: 9%,  Average Future Daily Traffic: 2,940 (year 2028),  Design Load: HS 20,  Features Intersected: WEST RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 94.918,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Skew: 2 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 33.5m (109.9ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 10.2m (33.5ft),  Out-to-Out Width: 11.3m (37.1ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Good,  Channel: Good,  Operating Rating: 77.1 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 39.0 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>   Show street view

Structure Number: 200013009814212,  Location: 1.1 MI S JCT. VT.155 (Lat: 43.322397,  Lng: -72.782986),  Route carried "on" structure: State highway 100,  Year Built: 2016,  Status: Open,  Structure Length: 1.92m (6.30ft),  Average Daily Traffic: 2,200 (year 2018),  Truck Traffic: 9%,  Average Future Daily Traffic: 2,310 (year 2028),  Design Load: HL 93,  Features Intersected: WEST RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 102.818,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Skew: 2 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 18.6m (61.0ft),  Curb-To-Curb Width: 9.8m (32.2ft),  Out-to-Out Width: 10.8m (35.4ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 45.4 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor (LRFR),  Inventory Rating: 33.6 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor (LRFR),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Deck Protection: Other Coated Reinforcing
Find on map >>   Show street view

Structure Number: 200013098A14212,  Location: 0.1 MI N JCT. VT.155 (Lat: 43.337308,  Lng: -72.785306),  Route carried "on" structure: State highway 100,  Year Built: 1967,  Status: Open,  Structure Length: 0.61m (2.00ft),  Average Daily Traffic: 1,300 (year 2018),  Truck Traffic: 9%,  Average Future Daily Traffic: 1,365 (year 2028),  Design Load: H 20,  Features Intersected: WEST RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 104.620,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 8.8m (28.9ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.1m (20.0ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 37.2 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 22.7 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021
Find on map >>   Show street view

Structure Number: 200120001014212,  Location: 0.2 MI W JCT. VT.100 (Lat: 43.291528,  Lng: -72.794358),  Route carried "on" structure: Federal lands road 4,  Year Built: 1976,  Status: Open,  Structure Length: 1.52m (4.99ft),  Average Daily Traffic: 240 (year 2017),  Truck Traffic: 6%,  Average Future Daily Traffic: 252 (year 2027),  Design Load: HS 20,  Features Intersected: WEST RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Material/Design: Prestressed concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 14.0m (45.9ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 10.0m (32.8ft),  Out-to-Out Width: 10.2m (33.5ft)

Condition: Deck: Very good,  Superstructure: Good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 39.9 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 35.4 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Discuss Weston, Vermont (VT) on our hugely popular Vermont forum.


City-data.com does not guarantee the accuracy or timeliness of any information on this site.  Use at your own risk.
Some parts © 2024 Advameg, Inc.