Since this isn't allowed by the Grand Poobah of School Protection, I'll put it here where the BOE can't get it censored.
UCPS BOND PROJECT CHANGES---These are the bond project changes the BOE has been keeping under wraps from the public which they finally presented to the BOCC yesterday.
November 20, 2017 BOCC Special Meeting - Union County, NC
Western Union Elementary
Original Cost - $ 3.9 Million Revised Cost - $ 518K
Original Scope: 8 Classrooms, Cafeteria Expansion, 2 Workrooms
Revised Scope: NO Classrooms, NO Cafeteria Expansion, NO Workrooms---Improve curb appeal by adjusting traffic circulation and adding screening and canopies.
Porter Ridge Middle
Original Cost - $6.3 Million Revised Cost - $2.9 Million
Original Scope: 15 Classrooms, Media Center Expansion, 2 Workrooms
Revised Scope: 3 Classrooms, 2 Resource Rooms, Auxiliary Gym
Monroe High
Original Cost - $3.5 Million Revised Cost - $4.3 Million
Original Scope: 8 General Classrooms, 2 Workrooms, 2 Teacher Offices
Revised Scope: 6 CTE Classrooms, Elevator Replacement, Improved Circulation
Piedmont High
Original Cost - $2.1 Million Revised Cost - $1.6 Million
Original Scope: 4 Classrooms, 2 Teacher Offices, 2 Teacher Workrooms
Revised Scope: NO Classrooms, NO Teacher Offices, NO Teacher Workrooms---Renovate 6 Classrooms in 1960’s era building.
Porter Ridge High
Original Cost - $1.5 Million Revised Cost - $2.1 Million
Original Scope: 4 Classrooms, Cafeteria Expansion
Revised Scope: 2 to 4 Classrooms, Cafeteria Expansion, New Hallway
Sun Valley High
Original Cost - $24.4 Million Revised Cost - $28.6 Million
Original Scope: 10 Classrooms, Auditorium Renovation, New Stadium, Administrative Office Expansion, Cafeteria and Kitchen Expansion, New Chorus Room, Teacher Workrooms, ADA Renovations, HVAC and Plumbing Upgrades
Revised Scope: 4 CTE Classrooms, Auditorium Renovation, New Stadium, Repurpose Administrative Offices to Flex Space, New Administrative Offices, New Cafeteria, New Weight Room, HVAC and Plumbing Upgrades.
Transportation Facility
Original Cost - $12 Million Revised Cost - $13.6 Million
Original Scope: New 16 Service Bay Facility
Revised Scope: New 12 Service Bay Facility