(August 22, 2013)—One southbound lane of Lockwood Drive—the one closest to the Ashley River—will be closed between the City Marina and Beaufain Street while Charleston Water System repairs a collapsed sewer line. The other southbound lane will remain open to traffic.
The repair work began today and will take about two weeks to complete. The lane will be open to traffic for Labor Day weekend. The lane closure schedule is as follows:
Friday, Aug 22: Lane closed 9 a.m. – 3 p.m.
Sat & Sun: Open to traffic
Next week: Closed 24 hours, but will reopen Friday at noon for the Labor Day weekend
Sept 3 – 6: Closed 9 a.m. – 3 p.m.
Electronic signs will be posted to inform drivers of the lane closure.