We signed mid February and were just told they probably won't break ground until October, can anybody beat that?
Reply With Quote Quick reply to this message

 
Old 08-09-2021, 08:15 AM
 
559 posts, read 936,256 times
Reputation: 318
Quote:
Originally Posted by EonBlueSyZ View Post
We signed mid February and were just told they probably won't break ground until October, can anybody beat that?
That's a long wait. Hope things goes smoother after that for you. Which builder did you go with?
Reply With Quote Quick reply to this message
 
Old 08-09-2021, 10:05 AM
 
Location: DFW
40,952 posts, read 49,171,554 times
Reputation: 55003
Most builders are not signing these types of contracts now.
They will get a house started and price, sell it when it's about 75% complete.

You need to be prepared for some big price surprises and shortages / limited choices as you start to build. Your builder is probably someone I would avoid.
Reply With Quote Quick reply to this message
 
Old 08-10-2021, 07:24 AM
 
53 posts, read 49,788 times
Reputation: 31
Signed in December and broke ground in ... Early July ... Suppose to be closing in November ..
Reply With Quote Quick reply to this message
 
Old 08-10-2021, 11:29 AM
 
1,447 posts, read 1,486,590 times
Reputation: 1820
Signed in November 2020....form boards went up two weeks ago, but in the wrong place. No slab yet. Hopefully in the next 2 weeks with 7 month build time.
Reply With Quote Quick reply to this message
 
Old 08-10-2021, 02:41 PM
 
46 posts, read 47,296 times
Reputation: 33
Reserved the lot in October 2020, got our turn to write contract in December 2020.
Current Stage: Electrical, plumbing, HVAC and Homepro done, waiting for windows since more than a month.
Tentative closing: September, but I seriously doubt it.

Did any know what's going with windows ? Everyone seems to be waiting for 1-2 months after the home is sheathed.
Reply With Quote Quick reply to this message
 
Old 08-10-2021, 04:04 PM
 
42 posts, read 27,788 times
Reputation: 23
Signed in November, moved in July. Thank god we read the reviews here and went with highland.
Reply With Quote Quick reply to this message
 
Old 08-11-2021, 07:21 AM
 
53 posts, read 49,788 times
Reputation: 31
Quote:
Originally Posted by Fluffypoms View Post
Signed in November, moved in July. Thank god we read the reviews here and went with highland.

We are building with Highland as well, but shortage is shortage unfortunately .
Slab took forever because of the weather and the permit issuance.


Then the wood for the frame is back ordered so it is causing a 3 weeks delay .


They have windows shortage, countertop shortage etc. It is a patience game :-X
Reply With Quote Quick reply to this message
 
Old 08-11-2021, 12:07 PM
 
42 posts, read 27,788 times
Reputation: 23
Quote:
Originally Posted by denebj View Post
We are building with Highland as well, but shortage is shortage unfortunately .
Slab took forever because of the weather and the permit issuance.


Then the wood for the frame is back ordered so it is causing a 3 weeks delay .


They have windows shortage, countertop shortage etc. It is a patience game :-X
Luckily there haven't been many delays where we are building, at most 1 - 2 months from the original promised date. Mostly due to the countertops. If you signed in December it's super strange that it took until July to start... must be a permit issue. We have a few neighbors signed in December already moved in.
Reply With Quote Quick reply to this message
 
Old 08-11-2021, 02:11 PM
 
559 posts, read 936,256 times
Reputation: 318
Quote:
Originally Posted by hanex1 View Post
Reserved the lot in October 2020, got our turn to write contract in December 2020.
Current Stage: Electrical, plumbing, HVAC and Homepro done, waiting for windows since more than a month.
Tentative closing: September, but I seriously doubt it.

Did any know what's going with windows ? Everyone seems to be waiting for 1-2 months after the home is sheathed.
September closing is very ambitious. I wouldn't place my bets for this date.

From the time drywall and brick goes up, it's taking anywhere 3 to 5 months for the builder to close in this market.
Reply With Quote Quick reply to this message
Please register to post and access all features of our very popular forum. It is free and quick. Over $68,000 in prizes has already been given out to active posters on our forum. Additional giveaways are planned.

Detailed information about all U.S. cities, counties, and zip codes on our site: City-data.com.


Reply
Please update this thread with any new information or opinions. This open thread is still read by thousands of people, so we encourage all additional points of view.

Quick Reply
Message:


Settings
X
Data:
Loading data...
Based on 2000-2020 data
Loading data...

123
Hide US histogram

Over $104,000 in prizes was already given out to active posters on our forum and additional giveaways are planned!

Go Back   City-Data Forum > U.S. Forums > Texas > Dallas

All times are GMT -6.

© 2005-2024, Advameg, Inc. · Please obey Forum Rules · Terms of Use and Privacy Policy · Bug Bounty

City-Data.com - Contact Us - Archive 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37 - Top