Bridge Statistics for Andover, New York (NY)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 26Number of bridges
  • 151ft / 46.0mTotal length
  • $27,224,000Total costs
  • 22,582Total average daily traffic
  • 1,601Total average daily truck traffic
  • 24,289Total future (year 2038) average daily traffic
  • National Bridge Inventory (NBI) Registered Bridges for Andover
  • No street view available for this location

New bridges in Andover, NY - historical statistics
  • New bridges - historical statistics
  • 11930-1939
  • 21950-1959
  • 31960-1969
  • 61970-1979
  • 41980-1989
  • 31990-1999
  • 32000-2009
  • 42010-2019
Reconstructed bridges in Andover, NY - Historical Statistics
  • Reconstructed bridges - Historical Statistics
  • 21970-1979
  • 11980-1989
  • 31990-1999
  • 02000-2009
  • 12010-2019
Average Bridge Daily Traffic in Andover, NY
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 9.1%Excellent
  • 36.4%Very good
  • 22.7%Good
  • 27.3%Satisfactory
  • 4.5%Fair
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 8.7%Excellent
  • 26.1%Very good
  • 43.5%Good
  • 13.0%Satisfactory
  • 4.3%Fair
  • 4.3%Poor
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 21.7%Very good
  • 26.1%Good
  • 26.1%Satisfactory
  • 26.1%Fair
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 3.8%Very good
  • 11.5%Good
  • 38.5%Satisfactory
  • 38.5%Fair
  • 7.7%Poor
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 33.3%Good
  • 33.3%Satisfactory
  • 33.3%Fair
Find on map >>   Show street view

Structure Number: 101251,  Location: 0.2 MI SW OF ELM VALLEY (Lat: 42.151358,  Lng: -77.862281),  Route carried "on" structure: State highway 417,  Year Built: 2014,  Status: Open,  Structure Length: 2.07m (6.79ft),  Average Daily Traffic: 4,337 (year 2018),  Truck Traffic: 8%,  Average Future Daily Traffic: 4,363 (year 2040),  Design Load: HL 93,  Features Intersected: ELM VALLEY CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 45.615,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Material/Design: Prestressed concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 20.1m (65.9ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 12.0m (39.4ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Satisfactory,  Operating Rating: 97.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 53.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.07m (6.79ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Bridge Improvement Cost: $623,000,  Roadway Improvement Cost: $365,000,  Total Project Cost: $988,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Other
Find on map >>   Show street view

Structure Number: 101252,  Location: 1.4 MI W OF ANDOVER (Lat: 42.149414,  Lng: -77.820697),  Route carried "on" structure: State highway 417,  Year Built: 1994,  Status: Open,  Structure Length: 11.19m (36.71ft),  Average Daily Traffic: 2,701 (year 2020),  Truck Traffic: 8%,  Average Future Daily Traffic: 2,717 (year 2040),  Design Load: HS 25 or greater,  Features Intersected: WNY & Pa RR, Dyke Creek
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 49.058,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 47.2m (154.9ft),  Curb-To-Curb Width: 10.8m (35.4ft),  Out-to-Out Width: 11.8m (38.7ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 76.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 45.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: Equal to present minimum criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 11.18m (36.68ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $3,314,000,  Roadway Improvement Cost: $1,941,000,  Total Project Cost: $5,254,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 101253,  Location: 1.5 MILES SE OF ANDOVER (Lat: 42.150861,  Lng: -77.767486),  Route carried "on" structure: State highway 417,  Year Built: 2010,  Status: Open,  Structure Length: 1.86m (6.10ft),  Average Daily Traffic: 1,346 (year 2018),  Truck Traffic: 8%,  Average Future Daily Traffic: 1,354 (year 2040),  Design Load: HL 93,  Features Intersected: DYKE CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 53.757,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Skew: 3 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Single/Spread,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 17.6m (57.7ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 10.4m (34.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 79.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 47.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.85m (6.07ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $708,000,  Roadway Improvement Cost: $415,000,  Total Project Cost: $1,122,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 101625,  Location: .1 MI N JCT SR417 & SR 21 (Lat: 42.155056,  Lng: -77.795203),  Route carried "on" structure: State highway 21,  Year Built: 2013,  Status: Open,  Structure Length: 2.35m (7.71ft),  Average Daily Traffic: 1,991 (year 2017),  Truck Traffic: 10%,  Average Future Daily Traffic: 2,003 (year 2040),  Design Load: HL 93,  Features Intersected: DYKE CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.064,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Material/Design: Prestressed concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 21.9m (71.9ft),  Curb or Sidewalk Widths: Left: 1.7m (5.6ft),  Right: 1.7m (5.6ft),  Curb-To-Curb Width: 9.8m (32.2ft),  Out-to-Out Width: 13.7m (44.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Very good,  Channel: Satisfactory,  Operating Rating: 83.9 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 58.6 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.34m (7.68ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021,  Bridge Improvement Cost: $1,068,000,  Roadway Improvement Cost: $626,000,  Total Project Cost: $1,694,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Epoxy Overlay
Find on map >>   Show street view

Structure Number: 101626,  Location: 0.5 MI N JCT RTS 417 + 21 (Lat: 42.161411,  Lng: -77.792108),  Route carried "on" structure: State highway 21,  Year Built: 1960,  Status: Open,  Structure Length: 1.77m (5.81ft),  Average Daily Traffic: 1,991 (year 2017),  Truck Traffic: 10%,  Average Future Daily Traffic: 2,003 (year 2040),  Design Load: HS 20,  Features Intersected: EAST VALLEY CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.853,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Skew: 5 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 7.6m (24.9ft),  Curb or Sidewalk Widths: Left: 0.0m,  Right: 1.2m (3.9ft)

Condition: Channel: Fair,  Culverts: Satisfactory,  Operating Rating: 89.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 68.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.76m (5.77ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Bridge Improvement Cost: $802,000,  Roadway Improvement Cost: $470,000,  Total Project Cost: $1,272,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 101627,  Location: 3.0 MI N JCT 417 & 21 (Lat: 42.196644,  Lng: -77.793478),  Route carried "on" structure: State highway 21,  Year Built: 1986,  Status: Open,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 1,991 (year 2017),  Truck Traffic: 10%,  Average Future Daily Traffic: 2,003 (year 2040),  Design Load: HS 20+Mod,  Features Intersected: RAILROAD BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.843,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Skew: 6 degrees,  Material/Design: Aluminum, Iron,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.4m (30.8ft)

Condition: Channel: Satisfactory,  Culverts: Fair,  Operating Rating: 89.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 89.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.97m (3.18ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $219,000,  Roadway Improvement Cost: $129,000,  Total Project Cost: $348,000 ( Estimate for 2021)
Find on map >>   Show street view

Structure Number: 221372,  Location: 3.1 MI NE OF ANDOVER (Lat: 42.192967,  Lng: -77.767014),  Route carried "on" structure: Other road ,  Year Built: 1970,  Year Reconstructed: 2010,  Status: Open,  Structure Length: 0.79m (2.59ft),  Average Daily Traffic: 134 (year 2018),  Truck Traffic: 5%,  Average Future Daily Traffic: 188 (year 2038),  Design Load: HS 25 or greater,  Features Intersected: EAST VALLEY CREEK,  Facility Carried by Structure: EAST VALLEY ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Skew: 1 degrees,  Material/Design: Wood or Timber,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.6m (24.9ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 7.3m (24.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Satisfactory,  Inventory Rating: 76.2 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.79m (2.59ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $336,000,  Roadway Improvement Cost: $197,000,  Total Project Cost: $533,000 ( Estimate for 2021),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Other
Find on map >>   Show street view

Structure Number: 221406,  Location: .2 MILE SE OF ELM VALLEY (Lat: 42.149639,  Lng: -77.854900),  Route carried "on" structure: Other road ,  Year Built: 1970,  Status: Open,  Structure Length: 2.04m (6.69ft),  Average Daily Traffic: 47 (year 2020),  Truck Traffic: 3%,  Average Future Daily Traffic: 66 (year 2040),  Design Load: HS 25 or greater,  Features Intersected: DYKE CREEK,  Facility Carried by Structure: RAY HILL ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.689,  Lanes on structure: 1,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 3.7m (12.1ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 19.2m (63.0ft),  Curb-To-Curb Width: 4.7m (15.4ft),  Out-to-Out Width: 5.0m (16.4ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Fair,  Channel: Fair,  Operating Rating: 72.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 50.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 2.04m (6.69ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $313,000,  Roadway Improvement Cost: $183,000,  Total Project Cost: $496,000 ( Estimate for 2021),  Deck Structure Type: Open Grating,  Wearing Surface/Protective System: Wearing Surface: Other
Find on map >>   Show street view

Structure Number: 221407,  Location: 1.8 MI NE OF ANDOVER (Lat: 42.177575,  Lng: -77.778275),  Route carried "on" structure: Other road ,  Year Built: 1977,  Year Reconstructed: 1997,  Status: Open,  Structure Length: 1.16m (3.81ft),  Average Daily Traffic: 97 (year 2020),  Average Future Daily Traffic: 136 (year 2040),  Design Load: HS 25 or greater,  Features Intersected: EAST VALLEY CREEK,  Facility Carried by Structure: EAST VALLEY ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.609,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 4.3m (14.1ft),  Material/Design: Wood or Timber,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 10.9m (35.8ft),  Curb-To-Curb Width: 7.2m (23.6ft),  Out-to-Out Width: 7.9m (25.9ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Fair,  Operating Rating: 88.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 60.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 1.15m (3.77ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $393,000,  Roadway Improvement Cost: $230,000,  Total Project Cost: $624,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>   Show street view

Structure Number: 221408,  Location: 2.4 MI NE OF ANDOVER (Lat: 42.185006,  Lng: -77.772911),  Route carried "on" structure: Other road ,  Year Built: 1961,  Year Reconstructed: 2001,  Status: Open,  Structure Length: 1.22m (4.00ft),  Average Daily Traffic: 97 (year 2020),  Average Future Daily Traffic: 136 (year 2040),  Features Intersected: EAST VALLEY CREEK,  Facility Carried by Structure: EAST VALLEY ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 2.639,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 4 degrees,  Material/Design: Wood or Timber,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 11.6m (38.1ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 7.9m (25.9ft)

Condition: Deck: Excellent,  Superstructure: Very good,  Substructure: Satisfactory,  Channel: Fair,  Operating Rating: 88.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 60.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Meets minimum limits,  Length Of Structure Improvement: 1.21m (3.97ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2020,  Bridge Improvement Cost: $377,000,  Roadway Improvement Cost: $221,000,  Total Project Cost: $598,000 ( Estimate for 2021),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Other
Find on map >>   Show street view

Structure Number: 22141,  Location: TWO MILES SE OF ANDOVER (Lat: 42.147386,  Lng: -77.758036),  Route carried "on" structure: Other road ,  Year Built: 1996,  Status: Open,  Structure Length: 0.94m (3.08ft),  Average Daily Traffic: 101 (year 2020),  Truck Traffic: 5%,  Average Future Daily Traffic: 141 (year 2040),  Features Intersected: DYKE CREEK,  Facility Carried by Structure: QUIGG HOLLOW ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 5.326,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Skew: 2 degrees,  Material/Design: Wood or Timber,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.1m (29.9ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 7.9m (25.9ft)

Condition: Deck: Very good,  Superstructure: Good,  Substructure: Fair,  Channel: Fair,  Operating Rating: 79.1 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 40.8 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.94m (3.08ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Bridge Improvement Cost: $431,000,  Roadway Improvement Cost: $252,000,  Total Project Cost: $684,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 221411,  Location: 2.2 MI SE OF ANDOVER (Lat: 42.145475,  Lng: -77.756350),  Route carried "on" structure: Other road ,  Year Built: 2008,  Status: Open,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 101 (year 2020),  Truck Traffic: 5%,  Average Future Daily Traffic: 141 (year 2040),  Design Load: HS 25 or greater,  Features Intersected: QUIGG HOLLOW CRK,  Facility Carried by Structure: QUIGG HOLLOW ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 5.068,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 3 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.4m (30.8ft),  Curb-To-Curb Width: 7.5m (24.6ft),  Out-to-Out Width: 7.7m (25.3ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Fair,  Inventory Rating: 68.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 0.97m (3.18ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2020,  Bridge Improvement Cost: $408,000,  Roadway Improvement Cost: $239,000,  Total Project Cost: $647,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Other
Find on map >>   Show street view

Structure Number: 221412,  Location: 2.5 MILES SE OF ANDOVER (Lat: 42.140722,  Lng: -77.754819),  Route carried "on" structure: Other road ,  Year Built: 2012,  Status: Open,  Structure Length: 0.85m (2.79ft),  Average Daily Traffic: 101 (year 2020),  Truck Traffic: 5%,  Average Future Daily Traffic: 141 (year 2040),  Design Load: HS 25 or greater,  Features Intersected: QUIGG HOLLOW CRK,  Facility Carried by Structure: QUIGG HOLLOW ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.521,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.5m (24.6ft),  Skew: 3 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.9m (25.9ft),  Curb-To-Curb Width: 7.5m (24.6ft),  Out-to-Out Width: 7.7m (25.3ft)

Condition: Deck: Excellent,  Superstructure: Excellent,  Substructure: Very good,  Channel: Satisfactory,  Operating Rating: 97.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 58.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Meets minimum limits,  Length Of Structure Improvement: 0.85m (2.79ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Bridge Improvement Cost: $260,000,  Roadway Improvement Cost: $152,000,  Total Project Cost: $412,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 221529,  Location: IN ANDOVER (Lat: 42.159036,  Lng: -77.795269),  Route carried "on" structure: Other road ,  Year Built: 1931,  Status: Posted for load,  Structure Length: 1.25m (4.10ft),  Average Daily Traffic: 874 (year 2019),  Truck Traffic: 5%,  Average Future Daily Traffic: 1,224 (year 2039),  Features Intersected: EAST VALLEY CREEK,  Facility Carried by Structure: NORTH MAIN STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.048,  Lanes on structure: 1,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.6m (24.9ft),  Material/Design: Concrete,  Design/Construction: Arch - Deck,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 11.5m (37.7ft),  Curb or Sidewalk Widths: Left: 1.2m (3.9ft),  Right: 0.0m,  Curb-To-Curb Width: 7.7m (25.3ft),  Out-to-Out Width: 8.7m (28.5ft)

Condition: Superstructure: Poor,  Substructure: Fair,  Channel: Fair,  Operating Rating: 13.6 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 13.6 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Meets minimum limits,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 1.24m (4.07ft),  Designated Inspection Frequency: Every 12 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $437,000,  Roadway Improvement Cost: $256,000,  Total Project Cost: $693,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>   Show street view

Structure Number: 22153,  Location: IN ANDOVER (Lat: 42.154586,  Lng: -77.798428),  Route carried "on" structure: City street ,  Year Built: 1973,  Status: Open,  Structure Length: 2.32m (7.61ft),  Average Daily Traffic: 222 (year 2018),  Truck Traffic: 5%,  Average Future Daily Traffic: 311 (year 2038),  Features Intersected: DYKE CREEK,  Facility Carried by Structure: SECOND STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.113,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 21.3m (69.9ft),  Curb or Sidewalk Widths: Left: 0.9m (3.0ft),  Right: 0.9m (3.0ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 9.8m (32.2ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Poor,  Operating Rating: 46.0 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 35.6 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 2.31m (7.58ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Bridge Improvement Cost: $743,000,  Roadway Improvement Cost: $435,000,  Total Project Cost: $1,177,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 221531,  Location: IN ANDOVER (Lat: 42.158506,  Lng: -77.799633),  Route carried "on" structure: Other road ,  Year Built: 1962,  Year Reconstructed: 2001,  Status: Open,  Structure Length: 0.91m (2.99ft),  Average Daily Traffic: 339 (year 2020),  Truck Traffic: 5%,  Average Future Daily Traffic: 475 (year 2040),  Design Load: HS 25 or greater,  Features Intersected: TRIB E VALLEY CRK,  Facility Carried by Structure: ROCHAMBEAU AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.370,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.0m (23.0ft),  Skew: 1 degrees,  Material/Design: Wood or Timber,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.8m (28.9ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 7.1m (23.3ft),  Out-to-Out Width: 11.5m (37.7ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 78.8 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 40.8 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.91m (2.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $409,000,  Roadway Improvement Cost: $240,000,  Total Project Cost: $649,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Other
Find on map >>   Show street view

Structure Number: 221533,  Location: IN ANDOVER (Lat: 42.164300,  Lng: -77.786789),  Route carried "on" structure: Other road ,  Year Built: 2004,  Status: Open,  Structure Length: 1.22m (4.00ft),  Average Daily Traffic: 215 (year 2019),  Truck Traffic: 5%,  Average Future Daily Traffic: 301 (year 2039),  Design Load: HS 25 or greater,  Features Intersected: EAST VALLEY CREEK,  Facility Carried by Structure: WATER STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.483,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.0m (23.0ft),  Skew: 2 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 11.9m (39.0ft),  Curb-To-Curb Width: 8.1m (26.6ft),  Out-to-Out Width: 8.3m (27.2ft)

Condition: Deck: Very good,  Superstructure: Excellent,  Substructure: Very good,  Channel: Good,  Operating Rating: 42.4 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Meets minimum limits,  Length Of Structure Improvement: 1.21m (3.97ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $337,000,  Roadway Improvement Cost: $197,000,  Total Project Cost: $534,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 225438,  Location: IN THE TOWN OF ANDOVER (Lat: 42.162406,  Lng: -77.789278),  Route carried "on" structure: Other road ,  Year Built: 1989,  Status: Open,  Structure Length: 0.91m (2.99ft),  Average Daily Traffic: 256 (year 2019),  Truck Traffic: 5%,  Average Future Daily Traffic: 358 (year 2039),  Features Intersected: EAST VALLEY CREEK,  Facility Carried by Structure: BARNEY STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.434,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Wood or Timber,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.8m (28.9ft),  Curb-To-Curb Width: 7.2m (23.6ft),  Out-to-Out Width: 7.9m (25.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 78.8 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 0.91m (2.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Bridge Improvement Cost: $257,000,  Roadway Improvement Cost: $150,000,  Total Project Cost: $407,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Other
Find on map >>   Show street view

Structure Number: 225461,  Location: 1.3 MI W ANDOVER (Lat: 42.168089,  Lng: -77.806628),  Route carried "on" structure: Other road ,  Year Built: 1989,  Status: Open,  Structure Length: 0.91m (2.99ft),  Average Daily Traffic: 200 (year 2020),  Truck Traffic: 4%,  Average Future Daily Traffic: 280 (year 2040),  Design Load: HS 20,  Features Intersected: TRIB EAST VALLEY,  Facility Carried by Structure: SWAIN HILL ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.499,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Skew: 2 degrees,  Material/Design: Wood or Timber,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.8m (28.9ft),  Curb-To-Curb Width: 7.2m (23.6ft),  Out-to-Out Width: 7.8m (25.6ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Good,  Channel: Fair,  Operating Rating: 61.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 42.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 0.91m (2.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2020,  Bridge Improvement Cost: $362,000,  Roadway Improvement Cost: $212,000,  Total Project Cost: $573,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 332993,  Location: 2.5 MI N OF ELM VALLEY (Lat: 42.188319,  Lng: -77.850064),  Route carried "on" structure: County highway ,  Year Built: 1990,  Status: Open,  Structure Length: 1.55m (5.09ft),  Average Daily Traffic: 947 (year 2018),  Truck Traffic: 4%,  Average Future Daily Traffic: 987 (year 2040),  Features Intersected: ELM VALLEY CREEK,  Facility Carried by Structure: COUNTY ROAD12
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.183,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 9.4m (30.8ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 14.6m (47.9ft),  Curb-To-Curb Width: 9.6m (31.5ft),  Out-to-Out Width: 10.2m (33.5ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Fair,  Channel: Poor,  Operating Rating: 30.8 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 23.7 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.55m (5.09ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2020,  Bridge Improvement Cost: $923,000,  Roadway Improvement Cost: $541,000,  Total Project Cost: $1,464,000 ( Estimate for 2021),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Other
Find on map >>   Show street view

Structure Number: 332994,  Location: 14 MI N OF ELM VALLEY (Lat: 42.171556,  Lng: -77.854081),  Route carried "on" structure: County highway ,  Year Built: 1984,  Status: Open,  Structure Length: 1.10m (3.61ft),  Average Daily Traffic: 947 (year 2018),  Truck Traffic: 4%,  Average Future Daily Traffic: 987 (year 2040),  Design Load: HS 20+Mod,  Features Intersected: ELM VALLEY CRK,  Facility Carried by Structure: COUNTY ROAD 12
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 2.285,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 10.1m (33.1ft),  Skew: 2 degrees,  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.8m (15.7ft),  Curb-To-Curb Width: 10.3m (33.8ft),  Out-to-Out Width: 11.0m (36.1ft)

Condition: Channel: Fair,  Culverts: Good,  Operating Rating: 47.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 28.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.09m (3.58ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Bridge Improvement Cost: $261,000,  Roadway Improvement Cost: $153,000,  Total Project Cost: $414,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 332995,  Location: 0.9 MI N OF ELM VALLEY (Lat: 42.165117,  Lng: -77.856356),  Route carried "on" structure: County highway ,  Year Built: 1956,  Year Reconstructed: 1984,  Status: Open,  Structure Length: 1.52m (4.99ft),  Average Daily Traffic: 947 (year 2018),  Truck Traffic: 4%,  Average Future Daily Traffic: 987 (year 2040),  Features Intersected: ELM VALLEY CREEK,  Facility Carried by Structure: COUNTY ROAD 12
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.545,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Skew: 3 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 14.3m (46.9ft),  Curb-To-Curb Width: 10.4m (34.1ft),  Out-to-Out Width: 11.1m (36.4ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 13.6 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 10.7 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: High priority of corrective action,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.52m (4.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Bridge Improvement Cost: $1,377,000,  Roadway Improvement Cost: $806,000,  Total Project Cost: $2,183,000 ( Estimate for 2021),  Deck Structure Type: Corrugated Steel,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 332996,  Location: 0.4 MI N OF ELM VALLEY (Lat: 42.157489,  Lng: -77.858350),  Route carried "on" structure: County highway ,  Year Built: 1956,  Year Reconstructed: 1984,  Status: Open,  Structure Length: 1.55m (5.09ft),  Average Daily Traffic: 947 (year 2018),  Truck Traffic: 4%,  Average Future Daily Traffic: 987 (year 2040),  Design Load: HS 20,  Features Intersected: ELM VALLEY CRK,  Facility Carried by Structure: COUNTY ROAD 12
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.676,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Skew: 3 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 15.2m (49.9ft),  Curb-To-Curb Width: 10.4m (34.1ft),  Out-to-Out Width: 11.0m (36.1ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 17.2 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 13.0 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Meets minimum limits,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.55m (5.09ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Bridge Improvement Cost: $1,377,000,  Roadway Improvement Cost: $806,000,  Total Project Cost: $2,183,000 ( Estimate for 2021),  Deck Structure Type: Corrugated Steel,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 33307,  Location: 0.6 MI E OF ANDOVER (Lat: 42.152889,  Lng: -77.782169),  Route carried "on" structure: County highway ,  Year Built: 1973,  Status: Open,  Structure Length: 1.98m (6.50ft),  Average Daily Traffic: 361 (year 2020),  Truck Traffic: 4%,  Average Future Daily Traffic: 505 (year 2040),  Design Load: HS 20+Mod,  Features Intersected: DYKE CREEK,  Facility Carried by Structure: INDEPENDENCE ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 11.215,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Skew: 3 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 18.5m (60.7ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 8.2m (26.9ft)

Condition: Deck: Fair,  Superstructure: Good,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 57.7 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 44.4 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Meets minimum limits,  Length Of Structure Improvement: 1.98m (6.50ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Bridge Improvement Cost: $752,000,  Roadway Improvement Cost: $440,000,  Total Project Cost: $1,192,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 333072,  Location: 1.3MI E OF ANDOVER (Lat: 42.152439,  Lng: -77.770600),  Route carried "on" structure: County highway ,  Year Built: 2007,  Status: Open,  Structure Length: 1.68m (5.51ft),  Average Daily Traffic: 416 (year 2018),  Truck Traffic: 4%,  Average Future Daily Traffic: 582 (year 2038),  Design Load: HS 25 or greater,  Features Intersected: DYKE CREEK,  Facility Carried by Structure: COUNTY ROAD 21
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.129,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 9.4m (30.8ft),  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 16.5m (54.1ft),  Curb-To-Curb Width: 9.6m (31.5ft),  Out-to-Out Width: 10.4m (34.1ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 46.0 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 35.6 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.67m (5.48ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2021,  Bridge Improvement Cost: $371,000,  Roadway Improvement Cost: $217,000,  Total Project Cost: $588,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Other
Find on map >>   Show street view

Structure Number: 335765,  Location: 4.2 MI SW OF ALFRED (Lat: 42.206833,  Lng: -77.838581),  Route carried "on" structure: County highway ,  Year Built: 1973,  Year Reconstructed: 1992,  Status: Open,  Structure Length: 0.91m (2.99ft),  Average Daily Traffic: 876 (year 2018),  Truck Traffic: 4%,  Average Future Daily Traffic: 913 (year 2040),  Design Load: HS 20,  Features Intersected: TRIB ELM VALLEY C,  Facility Carried by Structure: CR12 ELM VAL RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 6.597,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 2 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.5m (27.9ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 8.7m (28.5ft)

Condition: Deck: Very good,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Fair,  Operating Rating: 57.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 40.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 0.91m (2.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $312,000,  Roadway Improvement Cost: $183,000,  Total Project Cost: $495,000 ( Estimate for 2021),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Bituminous