  • National Bridge Inventory (NBI) Statistics
  • 15Number of bridges
  • 128ft / 38.9mTotal length
  • $35,320,000Total costs
  • 233,080Total average daily traffic
  • 41,514Total average daily truck traffic
  • National Bridge Inventory (NBI) Registered Bridges for Draper
  • No street view available for this location

New bridges in Draper, VA - historical statistics
  • New bridges - historical statistics
  • 11920-1929
  • 51950-1959
  • 61960-1969
  • 31970-1979
Average Bridge Daily Traffic in Draper, VA
Average Bridge Truck Traffic in Draper, VA
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 11.1%Very good
  • 22.2%Good
  • 22.2%Satisfactory
  • 44.4%Fair
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 11.1%Very good
  • 11.1%Good
  • 33.3%Satisfactory
  • 44.4%Fair
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 11.1%Good
  • 33.3%Satisfactory
  • 55.6%Fair
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 20.0%Very good
  • 20.0%Good
  • 60.0%Satisfactory
Find on map >>   Show street view

Structure Number: 14443,  Location: 2.55-WytheCo; 0.08-Rte100 (Lat: 36.991700,  Lng: -80.793433),  Route carried "on" structure: ServiceCounty highway F047,  Year Built: 1924,  Status: Posted for load,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 561 (year 2017),  Average Future Daily Traffic: 626 (year 2040),  Design Load: H 15,  Features Intersected: Pine Run,  Facility Carried by Structure: Kirby Road / FO47
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.103,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Skew: 4 degrees,  Material/Design: Concrete continuous,  Design/Construction: Slab,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.9m (16.1ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 6.4m (21.0ft),  Out-to-Out Width: 7.2m (23.6ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 18.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 10.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: High priority of corrective action,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 0.98m (3.22ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021,  Bridge Improvement Cost: $321,000,  Roadway Improvement Cost: $113,000,  Total Project Cost: $1,045,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1445,  Location: 0.00-SERV/RD; 0.07-RT 748 (Lat: 37.007044,  Lng: -80.751975),  Route carried "on" structure: County highway F327,  Year Built: 1959,  Status: Open,  Structure Length: 7.24m (23.75ft),  Average Daily Traffic: 910 (year 2008),  Average Future Daily Traffic: 1,056 (year 2040),  Design Load: HS 20,  Features Intersected: RTES I 81 & 100
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.097,  Lanes on structure: 2,  Lanes under structure: 4,  Owner: State Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 19.2m (63.0ft),  Curb or Sidewalk Widths: Left: 0.5m (1.6ft),  Right: 0.5m (1.6ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 8.2m (26.9ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Operating Rating: 76.2 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor (LRFR),  Inventory Rating: 55.3 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor (LRFR),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Underclear: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 7.25m (23.79ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2022,  Bridge Improvement Cost: $2,378,000,  Roadway Improvement Cost: $832,000,  Total Project Cost: $7,730,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Latex Concrete
Find on map >>   Show street view

Structure Number: 14464,  Location: 2.63-WYTHE CO; 4.34-RT 99 (Lat: 36.993692,  Lng: -80.793014),  Route carried "on" structure: Interstate 81,  Year Built: 1959,  Status: Open,  Structure Length: 5.94m (19.49ft),  Average Daily Traffic: 18,237 (year 2020),  Truck Traffic: 26%,  Average Future Daily Traffic: 25,532 (year 2040),  Design Load: HS 20+Mod,  Features Intersected: RTES 100 & 11
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 145.373,  Lanes on structure: 3,  Lanes under structure: 6,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.5m (41.0ft),  Skew: 2 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 17.4m (57.1ft),  Curb-To-Curb Width: 12.7m (41.7ft),  Out-to-Out Width: 13.7m (44.9ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Operating Rating: 64.4 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor (LRFR),  Inventory Rating: 49.0 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor (LRFR),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 5.94m (19.49ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2021,  Bridge Improvement Cost: $5,924,000,  Roadway Improvement Cost: $2,666,000,  Total Project Cost: $21,031,000 ( Estimate for 2019),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Latex Concrete
Find on map >>   Show street view

Structure Number: 14466,  Location: 4.34-RT 11; 4.34-RT 100 (Lat: 37.025761,  Lng: -80.729556),  Route carried "on" structure: Interstate 81,  Year Built: 1960,  Status: Temporarily open,  Structure Length: 7.53m (24.70ft),  Average Daily Traffic: 19,752 (year 2020),  Truck Traffic: 26%,  Average Future Daily Traffic: 27,653 (year 2040),  Design Load: HS 20+Mod,  Features Intersected: RT99/COUNT PULASKI DR.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 151.874,  Lanes on structure: 3,  Lanes under structure: 5,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.6m (38.1ft),  Skew: 2 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 21.9m (71.9ft),  Curb-To-Curb Width: 12.4m (40.7ft),  Out-to-Out Width: 13.4m (44.0ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Operating Rating: 56.2 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor (LRFR),  Inventory Rating: 43.5 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor (LRFR),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Underclear: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 7.92m (25.98ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2021,  Bridge Improvement Cost: $7,510,000,  Roadway Improvement Cost: $3,379,000,  Total Project Cost: $2,666,000 ( Estimate for 2019),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Latex Concrete
Find on map >>   Show street view

Structure Number: 14468,  Location: 4.34-RT 11; 4.34-RT 100 (Lat: 37.025925,  Lng: -80.729742),  Route carried "on" structure: Interstate 81,  Year Built: 1960,  Status: Open,  Structure Length: 6.89m (22.60ft),  Average Daily Traffic: 18,726 (year 2020),  Truck Traffic: 26%,  Average Future Daily Traffic: 26,216 (year 2040),  Design Load: HS 20+Mod,  Features Intersected: RT99/COUNT PULASKI DR.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 152.807,  Lanes on structure: 2,  Lanes under structure: 5,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.6m (38.1ft),  Skew: 3 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 22.1m (72.5ft),  Curb-To-Curb Width: 11.9m (39.0ft),  Out-to-Out Width: 12.9m (42.3ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Operating Rating: 59.9 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor (LRFR),  Inventory Rating: 46.3 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor (LRFR),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2021,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Latex Concrete
Find on map >>   Show street view

Structure Number: 14473,  Location: 0.31-RT 99; 4.03-RT 100 (Lat: 37.030208,  Lng: -80.728661),  Route carried "on" structure: Interstate 81,  Year Built: 1960,  Status: Open,  Structure Length: 5.38m (17.65ft),  Average Daily Traffic: 19,165 (year 2020),  Truck Traffic: 26%,  Average Future Daily Traffic: 26,831 (year 2040),  Design Load: HS 20+Mod,  Features Intersected: NEW RIVER TRAIL S. P.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 153.257,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.6m (38.1ft),  Skew: 3 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 20.0m (65.6ft),  Curb-To-Curb Width: 12.4m (40.7ft),  Out-to-Out Width: 13.4m (44.0ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Operating Rating: 50.8 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor (LRFR),  Inventory Rating: 39.0 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor (LRFR),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2021,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Latex Concrete
Find on map >>   Show street view

Structure Number: 14476,  Location: 1.36-Rte11/100;2.96-Rte99 (Lat: 37.000897,  Lng: -80.770364),  Route carried "on" structure: Interstate 81,  Year Built: 1960,  Status: Open,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 36,916 (year 2020),  Truck Traffic: 24%,  Average Future Daily Traffic: 48,966 (year 2040),  Design Load: HS 20,  Features Intersected: Sloan Branch
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 147.063,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 23.8m (78.1ft),  Skew: 20 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 54.4 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.64m (2.10ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $544,000,  Roadway Improvement Cost: $245,000,  Total Project Cost: $1,932,000 ( Estimate for 2021)
Find on map >>   Show street view

Structure Number: 14569,  Location: 3.40-Rte738; 0.25-Rte674 (Lat: 36.976383,  Lng: -80.796536),  Route carried "on" structure: County highway 640,  Year Built: 1977,  Status: Open,  Structure Length: 2.38m (7.81ft),  Average Daily Traffic: 234 (year 2020),  Average Future Daily Traffic: 328 (year 2040),  Design Load: HS 20+Mod,  Features Intersected: North Fork Peak Creek
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.322,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Skew: 4 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 23.8m (78.1ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 9.2m (30.2ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 73.5 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor (LRFR),  Inventory Rating: 57.2 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor (LRFR),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.38m (7.81ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $1,000,  Total Project Cost: $4,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Epoxy Overlay
Find on map >>   Show street view

Structure Number: 14584,  Location: 0.00-Rte100; 0.47-Rte709 (Lat: 36.975750,  Lng: -80.789733),  Route carried "on" structure: County highway 654,  Year Built: 1971,  Status: Open,  Structure Length: 0.91m (2.99ft),  Average Daily Traffic: 87 (year 2020),  Truck Traffic: 4%,  Average Future Daily Traffic: 102 (year 2040),  Features Intersected: Pine Run
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.489,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 4.3m (14.1ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.9m (16.1ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 6.2m (20.3ft),  Out-to-Out Width: 6.5m (21.3ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Fair,  Channel: Very good,  Operating Rating: 52.6 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor (LRFR),  Inventory Rating: 40.8 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor (LRFR),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.91m (2.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Bridge Improvement Cost: $281,000,  Roadway Improvement Cost: $98,000,  Total Project Cost: $912,000 ( Estimate for 2016),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1459,  Location: 0.70-Rte654; 0.50-Rte651 (Lat: 36.994297,  Lng: -80.746197),  Route carried "on" structure: County highway 658,  Year Built: 1974,  Status: Open,  Structure Length: 1.04m (3.41ft),  Average Daily Traffic: 503 (year 2020),  Truck Traffic: 2%,  Average Future Daily Traffic: 553 (year 2040),  Features Intersected: Sloan Branch
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 5.792,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 10.4m (34.1ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 8.2m (26.9ft),  Out-to-Out Width: 8.5m (27.9ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 53.5 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor (LRFR),  Inventory Rating: 40.8 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor (LRFR),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2021,  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1445,  Location: 0.00-SERV/RD; 0.07-RT 748 (Lat: 37.007044,  Lng: -80.751975),  Route carried "under" structure: Interstate 81,  Year Built: 1959,  Structure Length: 0. m,  Average Daily Traffic: 40,000 (year 2014),  Truck Traffic: 26%,  Features Intersected: RTES I 81 & 100,  Facility Carried by Structure: ROUTE F327
Minimum Vertical Clearance: 5.69m (18.67ft),  Kilometerpoint: 8.190,  Lanes on structure: 2,  Lanes under structure: 4,  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 19.2m (63.0ft)

Find on map >>   Show street view

Structure Number: 14462,  Location: 2.63-WYTHE CO; 4.34-RT 99 (Lat: 36.993492,  Lng: -80.793003),  Route carried "under" structure: US 100,  Year Built: 1959,  Structure Length: 0. m,  Average Daily Traffic: 2,089 (year 2008),  Truck Traffic: 2%,  Features Intersected: RTES 100 & 11,  Facility Carried by Structure: NBL ROUTE 0081
Minimum Vertical Clearance: 5.89m (19.32ft),  Kilometerpoint: 142.462,  Lanes on structure: 3,  Lanes under structure: 6,  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 17.2m (56.4ft)

Find on map >>   Show street view

Structure Number: 14464,  Location: 2.63-WYTHE CO; 4.34-RT 99 (Lat: 36.993692,  Lng: -80.793014),  Route carried "under" structure: US 100,  Year Built: 1959,  Structure Length: 0. m,  Average Daily Traffic: 3,300 (year 2014),  Truck Traffic: 9%,  Features Intersected: RTES 100 & 11,  Facility Carried by Structure: SBL ROUTE 0081
Minimum Vertical Clearance: 5.31m (17.42ft),  Kilometerpoint: 142.462,  Lanes on structure: 3,  Lanes under structure: 6,  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 17.4m (57.1ft)

Find on map >>   Show street view

Structure Number: 14466,  Location: 4.34-RT 11; 4.34-RT 100 (Lat: 37.025761,  Lng: -80.729556),  Route carried "under" structure: State highway 99,  Year Built: 1960,  Structure Length: 0. m,  Average Daily Traffic: 6,600 (year 2014),  Truck Traffic: 3%,  Features Intersected: RT99/COUNT PULASKI DR.,  Facility Carried by Structure: NBL ROUTE 0081
Minimum Vertical Clearance: 6.22m (20.41ft),  Kilometerpoint: 8.061,  Lanes on structure: 3,  Lanes under structure: 5,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 21.9m (71.9ft)

Find on map >>   Show street view

Structure Number: 14468,  Location: 4.34-RT 11; 4.34-RT 100 (Lat: 37.025925,  Lng: -80.729742),  Route carried "under" structure: State highway 99,  Year Built: 1960,  Structure Length: 0. m,  Average Daily Traffic: 66,000 (year 2014),  Truck Traffic: 3%,  Features Intersected: RT99/COUNT PULASKI DR.,  Facility Carried by Structure: SBL ROUTE 0081
Minimum Vertical Clearance: 4.29m (14.07ft),  Kilometerpoint: 8.061,  Lanes on structure: 2,  Lanes under structure: 5,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 22.1m (72.5ft)