  • 13Number of bridges
  • 121ft / 37.5mTotal length
  • $23,804,000Total costs
  • 73,784Total average daily traffic
  • 7,176Total average daily truck traffic
  • 119,318Total future (year 2031) average daily traffic
  • National Bridge Inventory (NBI) Registered Bridges for Great Barrington
  • No street view available for this location

New bridges in Great Barrington, MA - historical statistics
  • New bridges - historical statistics
  • 21930-1939
  • 11940-1949
  • 51950-1959
  • 21990-1999
  • 32000-2009
Average Bridge Daily Traffic in Great Barrington, MA
Average Bridge Truck Traffic in Great Barrington, MA
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 54.5%Good
  • 45.5%Satisfactory
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 45.5%Good
  • 9.1%Satisfactory
  • 36.4%Fair
  • 9.1%Poor
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 63.6%Good
  • 36.4%Satisfactory
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 7.7%Very good
  • 30.8%Good
  • 38.5%Satisfactory
  • 23.1%Fair
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 50.0%Good
  • 50.0%Satisfactory
Find on map >>   Show street view

Structure Number: G1100304GMUNNBI,  Location: AT ALFORD RD INTERSECTION (Lat: 42.216556,  Lng: -73.397914),  Route carried "on" structure: City street ,  Year Built: 1996,  Status: Open,  Structure Length: 1.57m (5.15ft),  Average Daily Traffic: 2,845 (year 2018),  Truck Traffic: 3%,  Average Future Daily Traffic: 2,258 (year 2031),  Design Load: HS 20,  Features Intersected: WATER SEEKONK BROOK,  Facility Carried by Structure: HWY DIVISION ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 6.6m (21.7ft),  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 15.2m (49.9ft),  Curb-To-Curb Width: 6.6m (21.7ft),  Out-to-Out Width: 7.3m (24.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 79.3 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 48.8 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.60m (5.25ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Bridge Improvement Cost: $1,026,000,  Roadway Improvement Cost: $103,000,  Total Project Cost: $1,540,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: G1100604HMUNNBI,  Location: 0.5M S JCT RTS41&7 (Lat: 42.198192,  Lng: -73.360567),  Route carried "on" structure: City street ,  Year Built: 1934,  Year Reconstructed: 1961,  Status: Closed,  Structure Length: 4.08m (13.39ft),  Average Daily Traffic: 240 (year 2018),  Truck Traffic: 4%,  Average Future Daily Traffic: 158 (year 2031),  Design Load: H 20,  Features Intersected: WATER HOUSATONIC RIVER,  Facility Carried by Structure: HWY COTTAGE ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 37.5m (123.0ft),  Curb or Sidewalk Widths: Left: 1.8m (5.9ft),  Right: 1.0m (3.3ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 12.8m (42.0ft)

Condition: Deck: Satisfactory,  Superstructure: Poor,  Substructure: Satisfactory,  Channel: Good,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 5.10m (16.73ft),  Designated Inspection Frequency: Every 12 months,  Inspection Date: December 2021,  Bridge Improvement Cost: $3,927,000,  Roadway Improvement Cost: $393,000,  Total Project Cost: $5,891,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>   Show street view

Structure Number: G1100704JMUNNBI,  Location: E OF MAIN ST N OF JCT23&7 (Lat: 42.192531,  Lng: -73.359006),  Route carried "on" structure: City street ,  Year Built: 1951,  Status: Posted for load,  Structure Length: 4.02m (13.19ft),  Average Daily Traffic: 8,200 (year 2008),  Truck Traffic: 5%,  Average Future Daily Traffic: 12,950 (year 2031),  Design Load: H 20,  Features Intersected: WATER HOUSATONIC RIVER,  Facility Carried by Structure: HWY BRIDGE ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.370,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 39.3m (128.9ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 0.4m (1.3ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 8.9m (29.2ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 50.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 22.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 4.10m (13.45ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: June 2020,  Critical Feature Inspection Date: June 2020,  Bridge Improvement Cost: $1,434,000,  Roadway Improvement Cost: $144,000,  Total Project Cost: $2,152,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>   Show street view

Structure Number: G1100804KMUNNBI,  Location: E OF RT7 1.3M N OF SHFFLD (Lat: 42.176114,  Lng: -73.359097),  Route carried "on" structure: City street ,  Year Built: 1949,  Status: Posted for load,  Structure Length: 4.52m (14.83ft),  Average Daily Traffic: 1,449 (year 2017),  Truck Traffic: 6%,  Average Future Daily Traffic: 158 (year 2032),  Design Load: H 15,  Features Intersected: WATER HOUSATONIC RIVER,  Facility Carried by Structure: HWY BROOKSIDE RD
Minimum Vertical Clearance: 4.31m (14.14ft),  Kilometerpoint: 0.241,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 43.5m (142.7ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 6.1m (20.0ft),  Out-to-Out Width: 6.9m (22.6ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 36.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 22.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 4.60m (15.09ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Critical Feature Inspection Date: June 2021,  Bridge Improvement Cost: $1,247,000,  Roadway Improvement Cost: $125,000,  Total Project Cost: $1,871,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>   Show street view

Structure Number: G11009A13DOTNBI,  Location: 1MI W OF US7 (Lat: 42.179383,  Lng: -73.379211),  Route carried "on" structure: State highway 23,  Year Built: 2004,  Status: Open,  Structure Length: 2.85m (9.35ft),  Average Daily Traffic: 10,345 (year 2016),  Truck Traffic: 8%,  Average Future Daily Traffic: 18,378 (year 2031),  Design Load: HS 20,  Features Intersected: WATER GREEN RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 9.814,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 9.5m (31.2ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 27.5m (90.2ft),  Curb or Sidewalk Widths: Left: 0.0m,  Right: 1.6m (5.2ft),  Curb-To-Curb Width: 9.5m (31.2ft),  Out-to-Out Width: 12.0m (39.4ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 74.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 44.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.90m (9.51ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2022,  Bridge Improvement Cost: $1,067,000,  Roadway Improvement Cost: $107,000,  Total Project Cost: $1,601,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: G11011AVQMUNNBI,  Location: 0.2M N OF RT71@EGRMNT BDR (Lat: 42.187867,  Lng: -73.413261),  Route carried "on" structure: City street ,  Year Built: 1999,  Status: Open,  Structure Length: 1.85m (6.07ft),  Average Daily Traffic: 647 (year 2019),  Truck Traffic: 6%,  Average Future Daily Traffic: 316 (year 2032),  Design Load: HS 20,  Features Intersected: WATER GREEN RIVER,  Facility Carried by Structure: HWY PUMPKIN HOLL
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.241,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Material/Design: Wood or Timber,  Design/Construction: Arch - Thru,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 18.0m (59.1ft),  Curb-To-Curb Width: 5.5m (18.0ft),  Out-to-Out Width: 6.1m (20.0ft)

Condition: Deck: Good,  Superstructure: Fair,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 56.7 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 41.4 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.90m (6.23ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Critical Feature Inspection Date: May 2021,  Bridge Improvement Cost: $456,000,  Roadway Improvement Cost: $46,000,  Total Project Cost: $685,000 ( Estimate for 2022),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Other
Find on map >>   Show street view

Structure Number: G1101204MMUNNBI,  Location: .7 MI NORTH OF ROUTE 71 (Lat: 42.190728,  Lng: -73.399539),  Route carried "on" structure: City street ,  Year Built: 1956,  Status: Posted for load,  Structure Length: 2.35m (7.71ft),  Average Daily Traffic: 776 (year 2018),  Truck Traffic: 6%,  Average Future Daily Traffic: 158 (year 2032),  Design Load: H 20,  Features Intersected: WATER GREEN RIVER,  Facility Carried by Structure: HWY SEEKONK CRSS
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.6m (24.9ft),  Skew: 1 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 12.2m (40.0ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 10.0m (32.8ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Fair,  Operating Rating: 95.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 56.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.40m (7.87ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Bridge Improvement Cost: $838,000,  Roadway Improvement Cost: $84,000,  Total Project Cost: $1,258,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: G1101304NMUNNBI,  Location: 1.5M N JCT RTS23&71 (Lat: 42.192628,  Lng: -73.391325),  Route carried "on" structure: City street ,  Year Built: 1958,  Status: Open,  Structure Length: 4.72m (15.49ft),  Average Daily Traffic: 1,164 (year 2018),  Truck Traffic: 6%,  Average Future Daily Traffic: 474 (year 2033),  Design Load: H 20,  Features Intersected: WATER GREEN RIVER,  Facility Carried by Structure: HWY HURLBURT RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 4 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 21.9m (71.9ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 8.7m (28.5ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Fair,  Operating Rating: 51.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 30.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 4.80m (15.75ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2022,  Bridge Improvement Cost: $1,641,000,  Roadway Improvement Cost: $165,000,  Total Project Cost: $2,462,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>   Show street view

Structure Number: G1101409MDOTNBI,  Location: 3.0 MI N OF SHEFFLD TL (Lat: 42.201417,  Lng: -73.357858),  Route carried "on" structure: US 7,  Year Built: 1931,  Status: Posted for load,  Structure Length: 3.63m (11.91ft),  Average Daily Traffic: 13,813 (year 2018),  Truck Traffic: 9%,  Average Future Daily Traffic: 28,427 (year 2032),  Design Load: H 20,  Features Intersected: WATER HOUSATONIC RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 18.426,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 33.1m (108.6ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 1.8m (5.9ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 13.3m (43.6ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 44.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 28.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 3.70m (12.14ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Critical Feature Inspection Date: July 2021,  Bridge Improvement Cost: $1,933,000,  Roadway Improvement Cost: $194,000,  Total Project Cost: $2,900,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>   Show street view

Structure Number: G11019ANNDOTNBI,  Location: 0.2 MI N OF SHEFFIELD TL (Lat: 42.163514,  Lng: -73.364967),  Route carried "on" structure: US 7,  Year Built: 2002,  Status: Open,  Structure Length: 4.35m (14.27ft),  Average Daily Traffic: 15,400 (year 2012),  Truck Traffic: 18%,  Average Future Daily Traffic: 15,951 (year 2031),  Design Load: HS 20,  Features Intersected: WATER GREEN RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 13.991,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 42.5m (139.4ft),  Curb or Sidewalk Widths: Left: 0.1m (0.3ft),  Right: 1.8m (5.9ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 14.8m (48.6ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 85.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 51.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.40m (14.44ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $498,000,  Roadway Improvement Cost: $50,000,  Total Project Cost: $748,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: G1102109NDOTNBI,  Location: AT ST.PETERS/ELMWOOD CEM. (Lat: 42.203519,  Lng: -73.346897),  Route carried "on" structure: US 7,  Year Built: 1953,  Status: Open,  Structure Length: 0.82m (2.69ft),  Average Daily Traffic: 11,448 (year 2017),  Truck Traffic: 10%,  Average Future Daily Traffic: 28,585 (year 2032),  Design Load: H 20,  Features Intersected: WATER TOM PALMER BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 19.553,  Lanes on structure: 3,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.7m (12.1ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 16.5m (54.1ft)

Condition: Channel: Fair,  Culverts: Good,  Operating Rating: 41.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 25.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.30m (4.27ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021,  Bridge Improvement Cost: $419,000,  Roadway Improvement Cost: $42,000,  Total Project Cost: $629,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: G11029AFTMUNNBI,  Location: 100' WEST OF ALFORD RD (Lat: 42.213100,  Lng: -73.391483),  Route carried "on" structure: City street ,  Year Built: 2003,  Status: Open,  Structure Length: 1.65m (5.41ft),  Average Daily Traffic: 457 (year 2017),  Truck Traffic: 6%,  Average Future Daily Traffic: 450 (year 2032),  Design Load: HS 20,  Features Intersected: WATER SEEKONK BROOK,  Facility Carried by Structure: HWY SEEKONK RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.2m (23.6ft),  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 15.4m (50.5ft),  Curb or Sidewalk Widths: Left: 0.0m,  Right: 1.6m (5.2ft),  Curb-To-Curb Width: 7.2m (23.6ft),  Out-to-Out Width: 9.7m (31.8ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Very good,  Inventory Rating: 86.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.70m (5.58ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Bridge Improvement Cost: $802,000,  Roadway Improvement Cost: $81,000,  Total Project Cost: $1,204,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: G110300C9DOTNBI,  Location: 150' E. OF E. MOUNTAIN RD (Lat: 42.191567,  Lng: -73.330986),  Route carried "on" structure: State highway 23,  Year Built: 1950,  Status: Open,  Structure Length: 1.07m (3.51ft),  Average Daily Traffic: 7,000 (year 2011),  Truck Traffic: 6%,  Average Future Daily Traffic: 11,055 (year 2032),  Features Intersected: WATER TOM PALMER BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 15.686,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 13.4m (44.0ft),  Skew: 7 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 10.1m (33.1ft),  Curb-To-Curb Width: 13.4m (44.0ft),  Out-to-Out Width: 15.2m (49.9ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 47.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 28.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.00m (13.12ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021,  Bridge Improvement Cost: $575,000,  Roadway Improvement Cost: $58,000,  Total Project Cost: $863,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Discuss Great Barrington, Massachusetts (MA) on our hugely popular Massachusetts forum.


City-data.com does not guarantee the accuracy or timeliness of any information on this site.  Use at your own risk.
Some parts © 2024 Advameg, Inc.