National Bridge Inventory (NBI) Statistics
Number of bridges: 31
Total length: 646 meters (2,119ft)
Total costs: $58,090,000
Total average daily traffic: 419,647
Total average daily truck traffic: 55,955
National Bridge Inventory (NBI) Registered Bridges for Grand Island

New bridges - Historical Statistics

  • 1930-1939: 3
  • 1940-1949: 0
  • 1950-1959: 10
  • 1960-1969: 3
  • 1970-1979: 3
  • 1980-1989: 2
  • 1990-1999: 2
  • 2000-2009: 8

Average Daily Traffic

Bridge Condition - Deck

Bridge Condition - Superstructure

Bridge Condition - Substructure

Bridge Condition - Channel

Bridge Condition - Culverts

Find on map >>

Structure Number: 104577,  Location: INT 20 ON I-190 (Lat: 43.053517,  Lng: -78.990614),  Route carried "on" structure: City street 957C,  Year Built: 2000,  Status: Open,  Structure Length: 6.52m (21.39ft),  Average Daily Traffic: 1,313 (year 2002),  Truck Traffic: 6%,  Average Future Daily Traffic: 1,480 (year 2022),  Design Load: HS 20+Mod,  Features Intersected: RTE I190, 324 X
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 174.271,  Lanes on structure: 2,  Lanes under structure: 2,  Owner: State Toll Authority,  Approaching Roadway Width: 11.2m (36.7ft),  Skew: 1 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 32.6m (107.0ft),  Curb-To-Curb Width: 11.1m (36.4ft),  Out-to-Out Width: 12.1m (39.7ft)

Condition: Deck: Excellent,  Superstructure: Excellent,  Substructure: Excellent,  Operating Rating: 85.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 50.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Superior to present desirable criteria,  Deck Geometry: Equal to present minimum criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.52m (21.39ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2006,  Bridge Improvement Cost: $676,000,  Roadway Improvement Cost: $402,000,  Total Project Cost: $1,078,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Galvanized Reinforcing
Find on map >>

Structure Number: 1068379,  Location: 0.5 MI N WHITEHAVEN RD (Lat: 43.026481,  Lng: -79.011650),  Route carried "on" structure: State lands road 957C,  Year Built: 1982,  Status: Open,  Structure Length: 3.20m (10.50ft),  Average Daily Traffic: 1,398 (year 2006),  Truck Traffic: 4%,  Average Future Daily Traffic: 1,799 (year 2026),  Design Load: HS 20,  Features Intersected: BIG SIXMILE CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 11.746,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Park, Forest, or Reservation Agency,  Maintenance Responsibility: State Highway Agency,  Approaching Roadway Width: 22.8m (74.8ft),  Skew: 20 degrees,  Material/Design: Concrete continuous,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 11.8m (38.7ft),  Curb or Sidewalk Widths: Left: 2.2m (7.2ft),  Right: 1.4m (4.6ft),  Curb-To-Curb Width: 24.6m (80.7ft),  Out-to-Out Width: 29.7m (97.4ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Very good,  Operating Rating: 79.3 metric tons,  Inventory Rating: 32.6 metric tons,  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.20m (10.50ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2007,  Bridge Improvement Cost: $9,011,000,  Roadway Improvement Cost: $5,228,000,  Total Project Cost: $14,239,000 ( Estimate for 2007),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 226811,  Location: HALF MILE BASELINE RD (Lat: 43.036489,  Lng: -78.954353),  Route carried "on" structure: City street ,  Year Built: 1982,  Status: Open,  Structure Length: 0.67m (2.20ft),  Average Daily Traffic: 4,161 (year 2005),  Truck Traffic: 4%,  Average Future Daily Traffic: 5,355 (year 2025),  Features Intersected: TRIB WOODS CREEK,  Facility Carried by Structure: BEDELL ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.6m (24.9ft),  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 1.8m (5.9ft)

Condition: Channel: Fair,  Culverts: Satisfactory,  Operating Rating: 73.7 metric tons,  Inventory Rating: 29.3 metric tons,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.67m (2.20ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2006,  Bridge Improvement Cost: $158,000,  Roadway Improvement Cost: $94,000,  Total Project Cost: $252,000 ( Estimate for 2007),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 226812,  Location: HALF MI. SOUTH WHITEHAVEN (Lat: 43.016914,  Lng: -78.925561),  Route carried "on" structure: City street ,  Year Built: 1976,  Status: Open,  Structure Length: 0.85m (2.79ft),  Average Daily Traffic: 671 (year 2006),  Truck Traffic: 4%,  Average Future Daily Traffic: 836 (year 2026),  Features Intersected: SPICER CREEK,  Facility Carried by Structure: HARVEY ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 6.0m (19.7ft),  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 1.8m (5.9ft)

Condition: Channel: Fair,  Culverts: Serious,  Operating Rating: 73.3 metric tons,  Inventory Rating: 19.5 metric tons,  Structural Evaluation: High priority of corrective action,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.85m (2.79ft),  Designated Inspection Frequency: Every 12 months,  Inspection Date: July 2007,  Bridge Improvement Cost: $206,000,  Roadway Improvement Cost: $123,000,  Total Project Cost: $329,000 ( Estimate for 2007),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 33265,  Location: 1.6 MI N JCT SH324&B L RD (Lat: 43.048475,  Lng: -78.966503),  Route carried "on" structure: County highway ,  Year Built: 2000,  Status: Open,  Structure Length: 1.10m (3.61ft),  Average Daily Traffic: 5,787 (year 2006),  Truck Traffic: 6%,  Average Future Daily Traffic: 6,524 (year 2026),  Design Load: HS 25,  Features Intersected: TRIB WOODS CREEK,  Facility Carried by Structure: BASELINE ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 10.8m (35.4ft),  Skew: 1 degrees,  Material/Design: Concrete,  Design/Construction: Frame,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 10.8m (35.4ft),  Curb-To-Curb Width: 10.8m (35.4ft),  Out-to-Out Width: 11.8m (38.7ft)

Condition: Deck: Excellent,  Superstructure: Excellent,  Substructure: Excellent,  Channel: Very good,  Operating Rating: 80.1 metric tons,  Inventory Rating: 40.8 metric tons,  Structural Evaluation: Superior to present desirable criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.10m (3.61ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2006,  Bridge Improvement Cost: $279,000,  Roadway Improvement Cost: $166,000,  Total Project Cost: $445,000 ( Estimate for 2007),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 332679,  Location: 1.8 MI N JCT SH324&B L RD (Lat: 43.050000,  Lng: -78.966567),  Route carried "on" structure: County highway ,  Year Built: 2000,  Status: Open,  Structure Length: 2.29m (7.51ft),  Average Daily Traffic: 4,233 (year 2006),  Truck Traffic: 4%,  Average Future Daily Traffic: 5,448 (year 2026),  Design Load: HS 25,  Features Intersected: WOODS CREEK,  Facility Carried by Structure: BASELINE ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 10.6m (34.8ft),  Skew: 3 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 21.9m (71.9ft),  Curb-To-Curb Width: 11.5m (37.7ft),  Out-to-Out Width: 12.5m (41.0ft)

Condition: Deck: Very good,  Superstructure: Excellent,  Substructure: Excellent,  Channel: Very good,  Operating Rating: 76.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 57.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Superior to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.29m (7.51ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2006,  Bridge Improvement Cost: $1,796,000,  Roadway Improvement Cost: $1,068,000,  Total Project Cost: $2,864,000 ( Estimate for 2007),  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>

Structure Number: 336205,  Location: 3.4 MI E OF I190 EXIT N19 (Lat: 43.022217,  Lng: -78.908794),  Route carried "on" structure: County highway ,  Year Built: 1970,  Status: Open,  Structure Length: 0.94m (3.08ft),  Average Daily Traffic: 2,363 (year 1998),  Truck Traffic: 4%,  Average Future Daily Traffic: 3,041 (year 2018),  Features Intersected: SPICER CREEK,  Facility Carried by Structure: WHITEHAVEN ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 12.8m (42.0ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Frame,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.8m (28.9ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Very good,  Operating Rating: 78.8 metric tons,  Inventory Rating: 32.6 metric tons,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.94m (3.08ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2006,  Bridge Improvement Cost: $273,000,  Roadway Improvement Cost: $162,000,  Total Project Cost: $435,000 ( Estimate for 2007),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 33703,  Location: .3 MI E JCT CR75&W RV PKY (Lat: 43.020858,  Lng: -79.009750),  Route carried "on" structure: County highway ,  Year Built: 2004,  Status: Open,  Structure Length: 0.82m (2.69ft),  Average Daily Traffic: 1,300 (year 2004),  Truck Traffic: 5%,  Average Future Daily Traffic: 1,625 (year 2024),  Design Load: HS 25,  Features Intersected: BIG SIX MILE CRK,  Facility Carried by Structure: WHITEHAVEN ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.0m (13.1ft),  Curb-To-Curb Width: 10.4m (34.1ft),  Out-to-Out Width: 11.6m (38.1ft)

Condition: Channel: Excellent,  Culverts: Excellent,  Operating Rating: 75.4 metric tons,  Inventory Rating: 40.8 metric tons,  Structural Evaluation: Superior to present desirable criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.82m (2.69ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2006,  Bridge Improvement Cost: $205,000,  Roadway Improvement Cost: $122,000,  Total Project Cost: $327,000 ( Estimate for 2007),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 5045751,  Location: INT EXIT 21 ON 190I (Lat: 43.068414,  Lng: -78.990953),  Route carried "on" structure: Interstate 190,  Year Built: 1963,  Status: Open,  Structure Length: 122.92m (403.28ft),  Average Daily Traffic: 26,709 (year 2002),  Truck Traffic: 17%,  Average Future Daily Traffic: 40,018 (year 2022),  Design Load: HS 20,  Features Intersected: 957A/R MOSES PKWY, NIAGA
Minimum Vertical Clearance: 5.74m (18.83ft),  Kilometerpoint: 498.693,  Lanes on structure: 2,  Lanes under structure: 5,  Owner: State Toll Authority,  Approaching Roadway Width: 14.6m (47.9ft),  Navigation Control: Yes ( Vertical Clearance: 12.1m (39.7ft), Horizontal Clearance: 82.2m (269.7ft)),  Material/Design: Steel continuous,  Design/Construction: Truss - Deck,  Number Of Spans In Main Unit: 21,  Number Of Approach Spans: 7,  Length of Maximum Span: 121.9m (399.9ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 0.0m,  Curb-To-Curb Width: 7.5m (24.6ft),  Out-to-Out Width: 10.4m (34.1ft)

Condition: Deck: Fair,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Excellent,  Operating Rating: 51.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Underclear: High priority of corrective action,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 122.92m (403.28ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: November 2007,  Critical Feature Inspection Date: November 2007,  Underwater Inspection Date: November 1995,  Bridge Improvement Cost: $2,713,000,  Roadway Improvement Cost: $1,535,000,  Total Project Cost: $4,248,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Latex Concrete
Find on map >>

Structure Number: 5045752,  Location: INT EXIT 21 ON 190I (Lat: 43.068053,  Lng: -78.990708),  Route carried "on" structure: Interstate 190,  Year Built: 1935,  Year Reconstructed: 1990,  Status: Open,  Structure Length: 122.68m (402.49ft),  Average Daily Traffic: 26,709 (year 2002),  Truck Traffic: 17%,  Average Future Daily Traffic: 40,018 (year 2022),  Design Load: HS 20,  Features Intersected: 957A/R MOSES PKWY, NIAGA
Minimum Vertical Clearance: 5.21m (17.09ft),  Kilometerpoint: 498.693,  Lanes on structure: 2,  Lanes under structure: 5,  Toll: On toll road,  Owner: State Toll Authority,  Approaching Roadway Width: 11.5m (37.7ft),  Navigation Control: Yes ( Vertical Clearance: 12.1m (39.7ft), Horizontal Clearance: 82.2m (269.7ft)),  Material/Design: Steel,  Design/Construction: Truss - Deck,  Number Of Spans In Main Unit: 21,  Number Of Approach Spans: 7,  Length of Maximum Span: 121.9m (399.9ft),  Curb or Sidewalk Widths: Left: 0.0m,  Right: 1.7m (5.6ft),  Curb-To-Curb Width: 7.5m (24.6ft),  Out-to-Out Width: 9.9m (32.5ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Good,  Channel: Excellent,  Operating Rating: 53.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Underclear: High priority of corrective action,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 122.68m (402.49ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: November 2007,  Critical Feature Inspection Date: November 2007,  Underwater Inspection Date: November 1995,  Bridge Improvement Cost: $2,713,000,  Roadway Improvement Cost: $1,535,000,  Total Project Cost: $4,248,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 5045761,  Location: 1.1 MI S INT 21 ON I-90 (Lat: 43.059303,  Lng: -78.990647),  Route carried "on" structure: Interstate 190,  Year Built: 1963,  Status: Open,  Structure Length: 7.62m (25.00ft),  Average Daily Traffic: 22,346 (year 2002),  Truck Traffic: 17%,  Average Future Daily Traffic: 33,481 (year 2022),  Features Intersected: BURNT SHIP CRK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 482.813,  Lanes on structure: 2,  Toll: On toll road,  Owner: State Toll Authority,  Material/Design: Concrete,  Design/Construction: Arch - Deck,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 22.5m (73.8ft),  Curb or Sidewalk Widths: Left: 0.6m (2.0ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 14.2m (46.6ft),  Out-to-Out Width: 15.7m (51.5ft)

Condition: Superstructure: Satisfactory,  Substructure: Good,  Channel: Excellent,  Operating Rating: 84.7 metric tons,  Inventory Rating: 32.6 metric tons,  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 7.62m (25.00ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2006,  Bridge Improvement Cost: $2,575,000,  Roadway Improvement Cost: $1,494,000,  Total Project Cost: $4,069,000 ( Estimate for 2007),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 5045762,  Location: 1.1 MI S INT 21 ON I-90 (Lat: 43.059294,  Lng: -78.990414),  Route carried "on" structure: Interstate 190,  Year Built: 1935,  Status: Open,  Structure Length: 7.62m (25.00ft),  Average Daily Traffic: 26,709 (year 2002),  Truck Traffic: 17%,  Average Future Daily Traffic: 40,018 (year 2022),  Features Intersected: BURNT SHIP CRK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 496.924,  Lanes on structure: 2,  Toll: On toll road,  Owner: State Toll Authority,  Material/Design: Concrete,  Design/Construction: Arch - Deck,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 22.5m (73.8ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 0.6m (2.0ft),  Curb-To-Curb Width: 11.8m (38.7ft),  Out-to-Out Width: 17.0m (55.8ft)

Condition: Superstructure: Very good,  Substructure: Good,  Channel: Excellent,  Operating Rating: 59.2 metric tons,  Inventory Rating: 23.8 metric tons,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 7.62m (25.00ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2006,  Bridge Improvement Cost: $2,800,000,  Roadway Improvement Cost: $1,624,000,  Total Project Cost: $4,424,000 ( Estimate for 2007),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 504578,  Location: 0.4 MI S INT 20 ON I-90 (Lat: 43.048569,  Lng: -78.990675),  Route carried "on" structure: State highway ,  Year Built: 1954,  Year Reconstructed: 1997,  Status: Open,  Structure Length: 6.16m (20.21ft),  Average Daily Traffic: 5,389 (year 2007),  Truck Traffic: 6%,  Average Future Daily Traffic: 6,076 (year 2027),  Design Load: HS 20+Mod,  Features Intersected: RTE I190,  Facility Carried by Structure: LONG ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 2.961,  Lanes on structure: 3,  Lanes under structure: 5,  Base Highway Network: Yes,  Owner: State Toll Authority,  Approaching Roadway Width: 14.9m (48.9ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 19.8m (65.0ft),  Curb or Sidewalk Widths: Left: 0.6m (2.0ft),  Right: 0.6m (2.0ft),  Curb-To-Curb Width: 14.3m (46.9ft),  Out-to-Out Width: 14.9m (48.9ft)

Condition: Deck: Very good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 31.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 19.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 6.16m (20.21ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2006,  Bridge Improvement Cost: $2,800,000,  Roadway Improvement Cost: $1,624,000,  Total Project Cost: $4,424,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Galvanized Reinforcing
Find on map >>

Structure Number: 50458,  Location: INT N18 ON I-90 (Lat: 43.005000,  Lng: -78.948275),  Route carried "on" structure: State highway ,  Year Built: 1954,  Status: Open,  Structure Length: 8.53m (27.99ft),  Average Daily Traffic: 11,164 (year 1994),  Truck Traffic: 6%,  Average Future Daily Traffic: 12,586 (year 2014),  Features Intersected: RTE I190,  Facility Carried by Structure: BEAVER ISLAND PKY
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 169.975,  Lanes on structure: 2,  Lanes under structure: 5,  Owner: State Toll Authority,  Approaching Roadway Width: 12.5m (41.0ft),  Skew: 4 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 26.8m (87.9ft),  Curb or Sidewalk Widths: Left: 1.4m (4.6ft),  Right: 1.4m (4.6ft),  Curb-To-Curb Width: 9.8m (32.2ft),  Out-to-Out Width: 13.1m (43.0ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Poor,  Operating Rating: 33.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 20.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Meets minimum limits,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Meets minimum limits,  Length Of Structure Improvement: 8.53m (27.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2006,  Bridge Improvement Cost: $2,408,000,  Roadway Improvement Cost: $1,397,000,  Total Project Cost: $3,805,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 55117,  Location: 0.3 MI W NW SANDY BEACH (Lat: 43.056642,  Lng: -78.971553),  Route carried "on" structure: City street ,  Year Built: 1957,  Status: Open,  Structure Length: 1.95m (6.40ft),  Average Daily Traffic: 1,654 (year 2005),  Truck Traffic: 4%,  Average Future Daily Traffic: 2,061 (year 2025),  Design Load: H 20,  Features Intersected: WOODS CREEK,  Facility Carried by Structure: EAST WEST ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: State Park, Forest, or Reservation Agency,  Approaching Roadway Width: 7.6m (24.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 18.2m (59.7ft),  Curb or Sidewalk Widths: Left: 1.6m (5.2ft),  Right: 1.6m (5.2ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 11.1m (36.4ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Satisfactory,  Operating Rating: 63.5 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 38.1 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.95m (6.40ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2006,  Bridge Improvement Cost: $1,556,000,  Roadway Improvement Cost: $920,000,  Total Project Cost: $2,476,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 551171,  Location: 1.2 MI S JCT W R RD(Lat: 42.961922,  Lng: -78.962797),  Route carried "on" structure: City street ,  Year Built: 1954,  Status: Open,  Structure Length: 1.43m (4.69ft),  Average Daily Traffic: 150 (year 2000),  Truck Traffic: 4%,  Average Future Daily Traffic: 187 (year 2020),  Design Load: H 20,  Features Intersected: SIDE CH NAIGARARV,  Facility Carried by Structure: BEAVER IS PARK RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: State Park, Forest, or Reservation Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 13.7m (44.9ft),  Curb or Sidewalk Widths: Left: 1.6m (5.2ft),  Right: 1.6m (5.2ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 11.1m (36.4ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 63.5 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 38.1 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.43m (4.69ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2006,  Bridge Improvement Cost: $1,556,000,  Roadway Improvement Cost: $920,000,  Total Project Cost: $2,476,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 55127,  Location: 0.4 MI NW JCT I190LS PKWY (Lat: 43.007208,  Lng: -78.953514),  Route carried "on" structure: City street ,  Year Built: 1990,  Status: Open,  Structure Length: 9.75m (31.99ft),  Average Daily Traffic: 3,018 (year 2006),  Truck Traffic: 4%,  Average Future Daily Traffic: 3,884 (year 2026),  Design Load: HS 20,  Features Intersected: RTE I190,  Facility Carried by Structure: STALEY ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 4,  Owner: State Toll Authority,  Approaching Roadway Width: 9.4m (30.8ft),  Skew: 6 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 48.8m (160.1ft),  Curb-To-Curb Width: 7.6m (24.9ft),  Out-to-Out Width: 10.0m (32.8ft)

Condition: Deck: Fair,  Superstructure: Good,  Substructure: Good,  Operating Rating: 87.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 51.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of replacement,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 9.75m (31.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2006,  Bridge Improvement Cost: $1,077,000,  Roadway Improvement Cost: $625,000,  Total Project Cost: $1,702,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>

Structure Number: 551271,  Location: 1 MI NW EXIT 18 OF I190 (Lat: 43.012169,  Lng: -78.965419),  Route carried "on" structure: County highway ,  Year Built: 2000,  Status: Open,  Structure Length: 7.38m (24.21ft),  Average Daily Traffic: 5,346 (year 1998),  Truck Traffic: 6%,  Average Future Daily Traffic: 6,027 (year 2018),  Design Load: HS 20,  Features Intersected: RTE I190,  Facility Carried by Structure: BASELINE RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 4,  Owner: State Toll Authority,  Approaching Roadway Width: 10.7m (35.1ft),  Skew: 3 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 36.9m (121.1ft),  Curb-To-Curb Width: 10.8m (35.4ft),  Out-to-Out Width: 11.7m (38.4ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Operating Rating: 89.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 53.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Meets minimum limits,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 7.38m (24.21ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2006,  Bridge Improvement Cost: $1,077,000,  Roadway Improvement Cost: $625,000,  Total Project Cost: $1,702,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Galvanized Reinforcing
Find on map >>

Structure Number: 551272,  Location: 2.0 MI NW JCT I190(Lat: 43.021581,  Lng: -78.974614),  Route carried "on" structure: County highway ,  Year Built: 1955,  Status: Open,  Structure Length: 6.82m (22.38ft),  Average Daily Traffic: 7,779 (year 2005),  Truck Traffic: 4%,  Average Future Daily Traffic: 10,012 (year 2025),  Design Load: HS 20+Mod,  Features Intersected: RTE I190,  Facility Carried by Structure: WHITEHAVEN ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 3,  Owner: State Toll Authority,  Approaching Roadway Width: 10.9m (35.8ft),  Skew: 2 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 19.8m (65.0ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 10.9m (35.8ft),  Out-to-Out Width: 14.6m (47.9ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Operating Rating: 38.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 22.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.82m (22.38ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2006,  Bridge Improvement Cost: $2,150,000,  Roadway Improvement Cost: $1,248,000,  Total Project Cost: $3,398,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 551627,  Location: 1.3 MI S JCT WR PKWY(Lat: 43.036017,  Lng: -78.984186),  Route carried "on" structure: City street ,  Year Built: 1954,  Status: Open,  Structure Length: 6.58m (21.59ft),  Average Daily Traffic: 1,125 (year 2005),  Truck Traffic: 4%,  Average Future Daily Traffic: 1,402 (year 2025),  Design Load: HS 20+Mod,  Features Intersected: RTE I190,  Facility Carried by Structure: BEDELL ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: State Toll Authority,  Approaching Roadway Width: 7.9m (25.9ft),  Skew: 2 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 19.8m (65.0ft),  Curb or Sidewalk Widths: Left: 0.7m (2.3ft),  Right: 0.7m (2.3ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 10.0m (32.8ft)

Condition: Deck: Fair,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Operating Rating: 33.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 20.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.58m (21.59ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2006,  Bridge Improvement Cost: $727,000,  Roadway Improvement Cost: $422,000,  Total Project Cost: $1,149,000 ( Estimate for 2007),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>

Structure Number: 104577,  Location: INT 20 ON I-190 (Lat: 43.053517,  Lng: -78.990614),  Route carried "under" structure: Interstate 190,  Year Built: 2000,  Structure Length: 6.52m (21.39ft),  Average Daily Traffic: 31,697 (year 1988),  Truck Traffic: 17%,  Features Intersected: RTE I190, 324 X,  Facility Carried by Structure: RTE 957C
Minimum Vertical Clearance: 4.52m (14.83ft),  Kilometerpoint: 1479.749,  Lanes on structure: 2,  Toll: Toll bridge is a segment,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 32.6m (107.0ft)

Find on map >>

Structure Number: 104577,  Location: INT 20 ON I-190 (Lat: 43.053517,  Lng: -78.990614),  Route carried "under" structure: State highway ,  Year Built: 2000,  Structure Length: 6.52m (21.39ft),  Average Daily Traffic: 44,748 (year 1995),  Truck Traffic: 6%,  Features Intersected: RTE I190, 324 X,  Facility Carried by Structure: RTE 957C
Minimum Vertical Clearance: 4.42m (14.50ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 2,  Toll: Toll bridge is a segment,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 32.6m (107.0ft)

Find on map >>

Structure Number: 106838,  Location: JCT LOVE ROAD & S PARKWAY (Lat: 42.995792,  Lng: -78.954689),  Route carried "under" structure: State lands road 957B,  Year Built: 1970,  Structure Length: 16.79m (55.09ft),  Average Daily Traffic: 9,958 (year 2006),  Truck Traffic: 6%,  Features Intersected: RTE 957B,  Facility Carried by Structure: PEDESTRIAN BRIDGE
Minimum Vertical Clearance: 4.64m (15.22ft),  Kilometerpoint: 0.317,  Lanes under structure: 7,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 39.3m (128.9ft)

Find on map >>

Structure Number: 5045751,  Location: INT EXIT 21 ON 190I (Lat: 43.068414,  Lng: -78.990953),  Route carried "under" structure: Other road ,  Year Built: 1963,  Structure Length: 122.92m (403.28ft),  Average Daily Traffic: 10,660 (year 1977),  Truck Traffic: 5%,  Features Intersected: 957A/R MOSES PKWY, NIAGA,  Facility Carried by Structure: RTE I190
Minimum Vertical Clearance: 4.41m (14.47ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 5,  Material/Design: Steel continuous,  Design/Construction: Truss - Deck,  Length of Maximum Span: 121.9m (399.9ft)

Find on map >>

Structure Number: 5045752,  Location: INT EXIT 21 ON 190I (Lat: 43.068053,  Lng: -78.990708),  Route carried "under" structure: Other road ,  Year Built: 1935,  Structure Length: 122.68m (402.49ft),  Average Daily Traffic: 10,660 (year 1977),  Truck Traffic: 5%,  Features Intersected: 957A/R MOSES PKWY, NIAGA,  Facility Carried by Structure: RTE I190
Minimum Vertical Clearance: 4.01m (13.16ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 5,  Toll: Toll bridge,  Material/Design: Steel,  Design/Construction: Truss - Deck,  Length of Maximum Span: 121.9m (399.9ft)

Find on map >>

Structure Number: 504578,  Location: 0.4 MI S INT 20 ON I-90 (Lat: 43.048569,  Lng: -78.990675),  Route carried "under" structure: Interstate 190,  Year Built: 1954,  Structure Length: 6.16m (20.21ft),  Average Daily Traffic: 19,900 (year 1971),  Truck Traffic: 17%,  Features Intersected: RTE I190,  Facility Carried by Structure: LONG ROAD
Minimum Vertical Clearance: 0.46m (1.51ft),  Kilometerpoint: 1479.186,  Lanes on structure: 3,  Lanes under structure: 5,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 19.8m (65.0ft)

Find on map >>

Structure Number: 50458,  Location: INT N18 ON I-90 (Lat: 43.005000,  Lng: -78.948275),  Route carried "under" structure: Interstate 190,  Year Built: 1954,  Structure Length: 8.53m (27.99ft),  Average Daily Traffic: 42,700 (year 1973),  Truck Traffic: 17%,  Features Intersected: RTE I190,  Facility Carried by Structure: BEAVER ISLAND PKY
Minimum Vertical Clearance: 4.54m (14.90ft),  Kilometerpoint: 1472.975,  Lanes on structure: 2,  Lanes under structure: 5,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 26.8m (87.9ft)

Find on map >>

Structure Number: 55127,  Location: 0.4 MI NW JCT I190LS PKWY (Lat: 43.007208,  Lng: -78.953514),  Route carried "under" structure: Spur Interstate 190,  Year Built: 1990,  Structure Length: 9.75m (31.99ft),  Average Daily Traffic: 23,400 (year 1977),  Truck Traffic: 17%,  Features Intersected: RTE I190,  Facility Carried by Structure: STALEY ROAD
Minimum Vertical Clearance: 0.48m (1.57ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 4,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 48.8m (160.1ft)

Find on map >>

Structure Number: 551271,  Location: 1 MI NW EXIT 18 OF I190 (Lat: 43.012169,  Lng: -78.965419),  Route carried "under" structure: Interstate 190,  Year Built: 2000,  Structure Length: 7.38m (24.21ft),  Average Daily Traffic: 23,400 (year 1977),  Truck Traffic: 17%,  Features Intersected: RTE I190,  Facility Carried by Structure: BASELINE RD
Minimum Vertical Clearance: 4.52m (14.83ft),  Kilometerpoint: 1474.584,  Lanes on structure: 2,  Lanes under structure: 4,  Toll: Toll bridge is a segment,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 36.9m (121.1ft)

Find on map >>

Structure Number: 551272,  Location: 2.0 MI NW JCT I190(Lat: 43.021581,  Lng: -78.974614),  Route carried "under" structure: Interstate 190,  Year Built: 1955,  Structure Length: 6.82m (22.38ft),  Average Daily Traffic: 22,200 (year 1977),  Truck Traffic: 17%,  Features Intersected: RTE I190,  Facility Carried by Structure: WHITEHAVEN ROAD
Minimum Vertical Clearance: 4.42m (14.50ft),  Kilometerpoint: 1475.887,  Lanes on structure: 3,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 19.8m (65.0ft)

Find on map >>

Structure Number: 551627,  Location: 1.3 MI S JCT WR PKWY(Lat: 43.036017,  Lng: -78.984186),  Route carried "under" structure: Interstate 190,  Year Built: 1954,  Structure Length: 6.58m (21.59ft),  Average Daily Traffic: 21,000 (year 1975),  Truck Traffic: 17%,  Features Intersected: RTE I190,  Facility Carried by Structure: BEDELL ROAD
Minimum Vertical Clearance: 4.45m (14.60ft),  Kilometerpoint: 147.769,  Lanes on structure: 2,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 19.8m (65.0ft)

Discuss this city on our hugely popular New York forum

Back to: Grand Island, NY, New York, All US cities.


City-data.com does not guarantee the accuracy or timeliness of any information on this site.  Use at your own risk.
Some parts © 2009 Advameg, Inc.