  • 18Number of bridges
  • 141ft / 42.7mTotal length
  • $16,314,000Total costs
  • 16,620Total average daily traffic
  • 1,414Total average daily truck traffic
  • 18,584Total future (year 2036) average daily traffic
  • National Bridge Inventory (NBI) Registered Bridges for Saranac
  • No street view available for this location

New bridges in Saranac, NY - historical statistics
  • New bridges - historical statistics
  • 21950-1959
  • 31960-1969
  • 11970-1979
  • 11980-1989
  • 41990-1999
  • 52000-2009
  • 22010-2019
Reconstructed bridges in Saranac, NY - Historical Statistics
  • Reconstructed bridges - Historical Statistics
  • 12000-2009
  • 12010-2019
Average Bridge Daily Traffic in Saranac, NY
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 13.3%Excellent
  • 33.3%Very good
  • 20.0%Good
  • 20.0%Satisfactory
  • 6.7%Fair
  • 6.7%Critical
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 43.8%Excellent
  • 25.0%Very good
  • 18.8%Good
  • 12.5%Satisfactory
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 37.5%Excellent
  • 12.5%Very good
  • 18.8%Good
  • 6.3%Satisfactory
  • 18.8%Fair
  • 6.3%Critical
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 16.7%Very good
  • 38.9%Good
  • 16.7%Satisfactory
  • 11.1%Fair
  • 16.7%Poor
Find on map >>   Show street view

Structure Number: 100083,  Location: 2.5 MI E OF RIVERVIEW (Lat: 44.592194,  Lng: -73.874822),  Route carried "on" structure: State highway 3,  Year Built: 2003,  Status: Open,  Structure Length: 3.26m (10.70ft),  Average Daily Traffic: 1,903 (year 2020),  Truck Traffic: 13%,  Average Future Daily Traffic: 1,921 (year 2040),  Design Load: HS 25 or greater,  Features Intersected: NO BR SARANAC RVR
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.972,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.9m (39.0ft),  Skew: 2 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 31.5m (103.3ft),  Curb-To-Curb Width: 12.0m (39.4ft),  Out-to-Out Width: 13.0m (42.7ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Good,  Inventory Rating: 75.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Meets minimum limits,  Length Of Structure Improvement: 3.26m (10.70ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $666,000,  Roadway Improvement Cost: $390,000,  Total Project Cost: $1,057,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 100084,  Location: 7.9 MI SW JCT RTS 3 & 374 (Lat: 44.638750,  Lng: -73.755772),  Route carried "on" structure: State highway 3,  Year Built: 1997,  Status: Open,  Structure Length: 1.07m (3.51ft),  Average Daily Traffic: 3,070 (year 2020),  Truck Traffic: 9%,  Average Future Daily Traffic: 3,099 (year 2040),  Design Load: HS 25 or greater,  Features Intersected: TRUE BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 16.380,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Skew: 1 degrees,  Material/Design: Concrete,  Design/Construction: Frame,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.7m (31.8ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 12.9m (42.3ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Good,  Channel: Poor,  Operating Rating: 79.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 47.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.06m (3.48ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $601,000,  Roadway Improvement Cost: $352,000,  Total Project Cost: $953,000 ( Estimate for 2021)
Find on map >>   Show street view

Structure Number: 100085,  Location: 5.9 MI SW JCT RTS 3 + 374 (Lat: 44.661950,  Lng: -73.732914),  Route carried "on" structure: State highway 3,  Year Built: 1958,  Status: Open,  Structure Length: 0.82m (2.69ft),  Average Daily Traffic: 3,070 (year 2020),  Truck Traffic: 9%,  Average Future Daily Traffic: 3,099 (year 2040),  Design Load: HS 20,  Features Intersected: CORNERS BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 19.775,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.6m (38.1ft),  Skew: 2 degrees,  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.6m (11.8ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 70.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 42.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.73m (5.68ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $338,000,  Roadway Improvement Cost: $198,000,  Total Project Cost: $535,000 ( Estimate for 2021)
Find on map >>   Show street view

Structure Number: 100086,  Location: 4.8 MI SW JCT RTS 3 + 374 (Lat: 44.668914,  Lng: -73.711361),  Route carried "on" structure: State highway 3,  Year Built: 1958,  Status: Open,  Structure Length: 0.85m (2.79ft),  Average Daily Traffic: 3,947 (year 2020),  Truck Traffic: 9%,  Average Future Daily Traffic: 3,984 (year 2040),  Design Load: HS 20,  Features Intersected: BEHAN BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 21.722,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Skew: 1 degrees,  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.6m (11.8ft)

Condition: Channel: Poor,  Culverts: Satisfactory,  Inventory Rating: 66.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.85m (2.79ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $272,000,  Roadway Improvement Cost: $159,000,  Total Project Cost: $431,000 ( Estimate for 2021)
Find on map >>   Show street view

Structure Number: 226956,  Location: 2.6 MI NORTH OF REDFORD (Lat: 44.648744,  Lng: -73.798897),  Route carried "on" structure: Other road ,  Year Built: 2016,  Status: Open,  Structure Length: 1.40m (4.59ft),  Average Daily Traffic: 173 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 242 (year 2040),  Design Load: HL 93,  Features Intersected: TRUE BROOK,  Facility Carried by Structure: TRUE BROOK ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 10.346,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.0m (23.0ft),  Skew: 3 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 12.5m (41.0ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 8.5m (27.9ft)

Condition: Deck: Very good,  Superstructure: Excellent,  Substructure: Excellent,  Channel: Very good,  Operating Rating: 80.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 42.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Superior to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 1.40m (4.59ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Bridge Improvement Cost: $283,000,  Roadway Improvement Cost: $165,000,  Total Project Cost: $448,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 333569,  Location: .1MI S RTE 3 CLAYBURG (Lat: 44.596189,  Lng: -73.838331),  Route carried "on" structure: County highway ,  Year Built: 1964,  Year Reconstructed: 2008,  Status: Open,  Structure Length: 2.13m (6.99ft),  Truck Traffic: 8%,  Design Load: HS 25 or greater,  Features Intersected: N.BR.SARANAC R.,  Facility Carried by Structure: CR1 SILVERLAKE RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 28.351,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 20.1m (65.9ft),  Curb-To-Curb Width: 8.0m (26.2ft),  Out-to-Out Width: 9.6m (31.5ft)

Condition: Deck: Very good,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Satisfactory,  Inventory Rating: 67.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 2.13m (6.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Bridge Improvement Cost: $744,000,  Roadway Improvement Cost: $436,000,  Total Project Cost: $1,179,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 333571,  Location: 1 MILE S W OF REDFORD (Lat: 44.605228,  Lng: -73.802292),  Route carried "on" structure: County highway ,  Year Built: 1993,  Status: Open,  Structure Length: 3.66m (12.01ft),  Average Daily Traffic: 503 (year 2017),  Truck Traffic: 2%,  Average Future Daily Traffic: 704 (year 2037),  Design Load: HS 20,  Features Intersected: SARANAC RIVER,  Facility Carried by Structure: ORE BED ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 22.606,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 36.2m (118.8ft),  Curb-To-Curb Width: 9.8m (32.2ft),  Out-to-Out Width: 10.4m (34.1ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Good,  Operating Rating: 84.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 50.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: High priority of corrective action,  Length Of Structure Improvement: 3.65m (11.98ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $943,000,  Roadway Improvement Cost: $552,000,  Total Project Cost: $1,496,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 333572,  Location: 0.6 MI NE REDFORD (Lat: 44.611056,  Lng: -73.791128),  Route carried "on" structure: Alternate County highway ,  Year Built: 1988,  Status: Posted for load,  Structure Length: 6.10m (20.01ft),  Average Daily Traffic: 192 (year 2016),  Truck Traffic: 7%,  Average Future Daily Traffic: 269 (year 2036),  Features Intersected: SARANAC RIVER,  Facility Carried by Structure: PUP HILL ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.016,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 4.6m (15.1ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 60.7m (199.1ft),  Curb-To-Curb Width: 4.0m (13.1ft),  Out-to-Out Width: 4.2m (13.8ft)

Condition: Deck: Critical,  Superstructure: Good,  Substructure: Good,  Channel: Very good,  Operating Rating: 22.7 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 22.7 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Meets minimum limits,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 30.0 - 39.9% below),  Length Of Structure Improvement: 6.09m (19.98ft),  Designated Inspection Frequency: Every 12 months,  Critical Feature Inspection Frequency: Every 12 months,  Inspection Date: September 2021,  Critical Feature Inspection Date: September 2021,  Bridge Improvement Cost: $1,681,000,  Roadway Improvement Cost: $984,000,  Total Project Cost: $2,665,000 ( Estimate for 2021),  Deck Structure Type: Steel plate,  Wearing Surface/Protective System: Wearing Surface: Other
Find on map >>   Show street view

Structure Number: 333574,  Location: .1 MI SE SH 3 IN SARANAC (Lat: 44.647431,  Lng: -73.747189),  Route carried "on" structure: County highway ,  Year Built: 1960,  Year Reconstructed: 2015,  Status: Open,  Structure Length: 5.43m (17.81ft),  Average Daily Traffic: 405 (year 2017),  Truck Traffic: 3%,  Average Future Daily Traffic: 567 (year 2037),  Design Load: HL 93,  Features Intersected: SARANAC RIVER,  Facility Carried by Structure: HARDSCRABBLE ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.032,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 21.0m (68.9ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 9.5m (31.2ft)

Condition: Deck: Very good,  Superstructure: Excellent,  Substructure: Good,  Channel: Good,  Operating Rating: 82.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 49.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 5.42m (17.78ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $1,259,000,  Roadway Improvement Cost: $737,000,  Total Project Cost: $1,996,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 333575,  Location: .2 MI SE PICKETTS CORNERS (Lat: 44.658811,  Lng: -73.732653),  Route carried "on" structure: Other road ,  Year Built: 1999,  Status: Open,  Structure Length: 4.57m (14.99ft),  Average Daily Traffic: 674 (year 2016),  Truck Traffic: 5%,  Average Future Daily Traffic: 944 (year 2036),  Design Load: HS 25 or greater,  Features Intersected: SARANAC RIVER,  Facility Carried by Structure: BOWEN ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.352,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 44.0m (144.4ft),  Curb-To-Curb Width: 8.0m (26.2ft),  Out-to-Out Width: 8.6m (28.2ft)

Condition: Deck: Fair,  Superstructure: Excellent,  Substructure: Excellent,  Channel: Satisfactory,  Operating Rating: 75.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 44.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Superior to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.57m (14.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $923,000,  Roadway Improvement Cost: $541,000,  Total Project Cost: $1,464,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 333576,  Location: 1.8 M SW CADYVILLE (Lat: 44.686989,  Lng: -73.667108),  Route carried "on" structure: Other road ,  Year Built: 1997,  Status: Open,  Structure Length: 5.03m (16.50ft),  Average Daily Traffic: 642 (year 2020),  Truck Traffic: 6%,  Average Future Daily Traffic: 899 (year 2040),  Design Load: HS 25 or greater,  Features Intersected: SARANAC RIVER,  Facility Carried by Structure: DUQUETTE ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 2.896,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 48.7m (159.8ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 8.5m (27.9ft)

Condition: Deck: Very good,  Superstructure: Excellent,  Substructure: Excellent,  Channel: Very good,  Operating Rating: 89.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 59.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Superior to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 5.02m (16.47ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $1,008,000,  Roadway Improvement Cost: $590,000,  Total Project Cost: $1,598,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 333605,  Location: .2MI W PICKETTS CORNERS (Lat: 44.662489,  Lng: -73.737139),  Route carried "on" structure: County highway ,  Year Built: 2007,  Status: Open,  Structure Length: 0.94m (3.08ft),  Average Daily Traffic: 757 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 1,060 (year 2040),  Design Load: HS 25 or greater,  Features Intersected: CORNERS BROOK,  Facility Carried by Structure: CHAZY LAKE ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.322,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Frame,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.1m (29.9ft),  Curb-To-Curb Width: 8.7m (28.5ft),  Out-to-Out Width: 9.9m (32.5ft)

Condition: Superstructure: Very good,  Substructure: Very good,  Channel: Fair,  Operating Rating: 86.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 52.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.94m (3.08ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $187,000,  Roadway Improvement Cost: $110,000,  Total Project Cost: $297,000 ( Estimate for 2021)
Find on map >>   Show street view

Structure Number: 333678,  Location: STANDISH RD OVER COLD BK (Lat: 44.620700,  Lng: -73.904119),  Route carried "on" structure: County highway ,  Year Built: 2005,  Status: Open,  Structure Length: 1.16m (3.81ft),  Average Daily Traffic: 276 (year 2020),  Truck Traffic: 11%,  Average Future Daily Traffic: 386 (year 2040),  Design Load: HS 25 or greater,  Features Intersected: COLD BROOK,  Facility Carried by Structure: CR1 STANDISH ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 35.076,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 9.4m (30.8ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Frame,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 11.4m (37.4ft),  Curb-To-Curb Width: 9.6m (31.5ft),  Out-to-Out Width: 10.9m (35.8ft)

Condition: Deck: Excellent,  Superstructure: Excellent,  Substructure: Excellent,  Channel: Good,  Inventory Rating: 72.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Superior to present desirable criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.15m (3.77ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $271,000,  Roadway Improvement Cost: $159,000,  Total Project Cost: $429,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Other
Find on map >>   Show street view

Structure Number: 333679,  Location: 2.5 MI N RIVERVIEW (Lat: 44.619614,  Lng: -73.902950),  Route carried "on" structure: County highway ,  Year Built: 2005,  Status: Open,  Structure Length: 1.19m (3.90ft),  Average Daily Traffic: 276 (year 2020),  Truck Traffic: 11%,  Average Future Daily Traffic: 386 (year 2040),  Design Load: HS 25 or greater,  Features Intersected: COLD BROOK,  Facility Carried by Structure: CR10 STANDISH RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 34.915,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 9.4m (30.8ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Frame,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 11.6m (38.1ft),  Curb-To-Curb Width: 9.6m (31.5ft),  Out-to-Out Width: 10.7m (35.1ft)

Condition: Deck: Excellent,  Superstructure: Excellent,  Substructure: Excellent,  Channel: Good,  Operating Rating: 95.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 57.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Superior to present desirable criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.18m (3.87ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $272,000,  Roadway Improvement Cost: $160,000,  Total Project Cost: $432,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Other
Find on map >>   Show street view

Structure Number: 335832,  Location: .7MI W MOFFITSVILLE (Lat: 44.637181,  Lng: -73.769789),  Route carried "on" structure: Other road ,  Year Built: 1971,  Status: Open,  Structure Length: 0.85m (2.79ft),  Average Daily Traffic: 213 (year 2020),  Truck Traffic: 6%,  Average Future Daily Traffic: 298 (year 2040),  Features Intersected: TRUE BROOK,  Facility Carried by Structure: TRUE BROOK ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 13.355,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 4.6m (15.1ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.9m (25.9ft),  Curb-To-Curb Width: 5.5m (18.0ft),  Out-to-Out Width: 6.3m (20.7ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Poor,  Operating Rating: 54.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 31.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 0.85m (2.79ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: June 2020,  Critical Feature Inspection Date: June 2020,  Bridge Improvement Cost: $172,000,  Roadway Improvement Cost: $101,000,  Total Project Cost: $273,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 335833,  Location: 2.2MI W MOFFITSVILLE (Lat: 44.640869,  Lng: -73.793028),  Route carried "on" structure: Other road ,  Year Built: 2016,  Status: Open,  Structure Length: 2.13m (6.99ft),  Average Daily Traffic: 153 (year 2020),  Truck Traffic: 2%,  Average Future Daily Traffic: 214 (year 2040),  Design Load: HL 93,  Features Intersected: TRUE BROOK,  Facility Carried by Structure: TRUE BROOK ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 11.231,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Skew: 3 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Single/Spread,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 20.4m (66.9ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 8.7m (28.5ft)

Condition: Deck: Good,  Superstructure: Excellent,  Substructure: Critical,  Channel: Good,  Inventory Rating: 38.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: High priority of replacement,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 2.13m (6.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Bridge Improvement Cost: $330,000,  Roadway Improvement Cost: $193,000,  Total Project Cost: $523,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 335993,  Location: 1.3 MI W OF MOFFITSVILLE (Lat: 44.637900,  Lng: -73.775989),  Route carried "on" structure: Other road ,  Year Built: 1969,  Status: Open,  Structure Length: 0.88m (2.89ft),  Average Daily Traffic: 213 (year 2020),  Truck Traffic: 6%,  Average Future Daily Traffic: 298 (year 2040),  Features Intersected: TRUE BROOK,  Facility Carried by Structure: REYELL ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 12.824,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 3.0m (9.8ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.6m (24.9ft),  Curb-To-Curb Width: 4.1m (13.5ft),  Out-to-Out Width: 4.3m (14.1ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Fair,  Channel: Fair,  Operating Rating: 52.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 30.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Meets minimum limits,  Length Of Structure Improvement: 0.88m (2.89ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $126,000,  Roadway Improvement Cost: $74,000,  Total Project Cost: $200,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete
Find on map >>   Show street view

Structure Number: 335994,  Location: TRUE BROOK RD 1.4M N RT 3 (Lat: 44.640700,  Lng: -73.779983),  Route carried "on" structure: Other road ,  Year Built: 2001,  Status: Open,  Structure Length: 1.25m (4.10ft),  Average Daily Traffic: 153 (year 2020),  Truck Traffic: 2%,  Average Future Daily Traffic: 214 (year 2040),  Design Load: HS 25 or greater,  Features Intersected: TRUE BROOK,  Facility Carried by Structure: TRUE BROOK ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 12.357,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.6m (24.9ft),  Skew: 1 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 11.5m (37.7ft),  Curb-To-Curb Width: 8.1m (26.6ft),  Out-to-Out Width: 9.0m (29.5ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Excellent,  Channel: Good,  Operating Rating: 79.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 57.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.24m (4.07ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $213,000,  Roadway Improvement Cost: $125,000,  Total Project Cost: $338,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing