Bridge Statistics for Tribbey, Oklahoma (OK)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 28Number of bridges
  • 187ft / 57.0mTotal length
  • $16,508,000Total costs
  • 5,678Total average daily traffic
  • 777Total average daily truck traffic
  • 9,072Total future (year 2040) average daily traffic
  • National Bridge Inventory (NBI) Registered Bridges for Tribbey
  • No street view available for this location

New bridges in Tribbey, OK - historical statistics
  • New bridges - historical statistics
  • 21930-1939
  • 11950-1959
  • 21970-1979
  • 51980-1989
  • 51990-1999
  • 92000-2009
  • 32010-2019
  • 12020-2022
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 13.0%Very good
  • 56.5%Good
  • 17.4%Satisfactory
  • 8.7%Fair
  • 4.3%Poor
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 13.0%Very good
  • 26.1%Good
  • 21.7%Satisfactory
  • 39.1%Fair
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 26.1%Very good
  • 13.0%Good
  • 26.1%Satisfactory
  • 30.4%Fair
  • 4.3%Poor
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 14.3%Very good
  • 3.6%Good
  • 25.0%Satisfactory
  • 50.0%Fair
  • 7.1%Serious
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 40.0%Good
  • 40.0%Satisfactory
  • 20.0%Fair
Find on map >>   Show street view

Structure Number: 5871,  Location: .8 S & .5 E OF TROUSDALE (Lat: 35.029164,  Lng: -97.034256),  Route carried "on" structure: County highway E1370,  Year Built: 1938,  Status: Open,  Structure Length: 0.75m (2.46ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.161,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.3m (10.8ft),  Curb-To-Curb Width: 9.6m (31.5ft),  Out-to-Out Width: 10.2m (33.5ft)

Condition: Channel: Serious,  Culverts: Satisfactory,  Operating Rating: 32.7 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 19.1 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.79m (9.15ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 6002,  Location: 1.2 MI E OF KENWOOD (Lat: 36.316794,  Lng: -94.971092),  Route carried "on" structure: County highway 2142C,  Year Built: 1938,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 384 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 614 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.219,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.4m (21.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 51.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 31.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.72m (8.92ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 7475,  Location: 8. N 1. E WEATHERFORD (Lat: 35.657053,  Lng: -98.685486),  Route carried "on" structure: County highway N2420,  Year Built: 1990,  Year Reconstructed: 1992,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.483,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.7m (22.0ft),  Curb-To-Curb Width: 8.3m (27.2ft),  Out-to-Out Width: 8.5m (27.9ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Good,  Inventory Rating: 69.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.86m (9.38ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $146,000,  Roadway Improvement Cost: $80,000,  Total Project Cost: $231,000 ( Estimate for 2015),  Deck Structure Type: Steel plate,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 11896,  Location: 2 W OF ANDERSON (Lat: 35.087197,  Lng: -97.019642),  Route carried "on" structure: County highway 6330C,  Year Built: 1950,  Status: Open,  Structure Length: 0.67m (2.20ft),  Average Daily Traffic: 120 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 192 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.851,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 1.5m (4.9ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 10.1m (33.1ft)

Condition: Channel: Serious,  Culverts: Fair,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.66m (8.73ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 18654,  Location: 9.2 MI N SH 39 (Lat: 35.110817,  Lng: -97.054111),  Route carried "on" structure: State highway 102,  Year Built: 1974,  Status: Open,  Structure Length: 1.01m (3.31ft),  Average Daily Traffic: 590 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 944 (year 2040),  Design Load: HS 20,  Features Intersected: COON CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 23.926,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 7.3m (24.0ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 44.5 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.01m (3.31ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 18695,  Location: 9.7 MI N SH 39 (Lat: 35.117964,  Lng: -97.054117),  Route carried "on" structure: State highway 102,  Year Built: 1974,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 590 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 944 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 15.672,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Fair,  Culverts: Good,  Operating Rating: 90.7 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 55.5 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.70m (2.30ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 19992,  Location: 12.5 MI N SH 39 (Lat: 35.159131,  Lng: -97.054197),  Route carried "on" structure: State highway 102,  Year Built: 1981,  Status: Open,  Structure Length: 6.40m (21.00ft),  Average Daily Traffic: 590 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 944 (year 2040),  Design Load: HS 20,  Features Intersected: LITTLE RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 20.225,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 21.3m (69.9ft),  Curb-To-Curb Width: 9.8m (32.2ft),  Out-to-Out Width: 10.7m (35.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 70.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 34.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 9.23m (30.28ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $747,000,  Roadway Improvement Cost: $1,232,000,  Total Project Cost: $2,092,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 20272,  Location: 1.8 S OF ANDERSON (Lat: 35.061728,  Lng: -96.984378),  Route carried "on" structure: County highway 6372C,  Year Built: 1982,  Status: Open,  Structure Length: 3.67m (12.04ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 160 (year 2040),  Design Load: HS 20,  Features Intersected: COTTONWOOD CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 8.045,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Skew: 6 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 12.2m (40.0ft),  Curb-To-Curb Width: 8.0m (26.2ft),  Out-to-Out Width: 8.5m (27.9ft)

Condition: Deck: Good,  Superstructure: Fair,  Substructure: Fair,  Channel: Fair,  Operating Rating: 63.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 38.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.86m (22.51ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: January 2021,  Other Special Inspection Date: January 2021,  Bridge Improvement Cost: $351,000,  Roadway Improvement Cost: $193,000,  Total Project Cost: $560,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 2052,  Location: .8 S & .8 W OF BURNETT (Lat: 35.145122,  Lng: -97.095333),  Route carried "on" structure: County highway 6359C,  Year Built: 1983,  Status: Posted for load,  Structure Length: 2.76m (9.06ft),  Average Daily Traffic: 200 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 320 (year 2040),  Design Load: HS 20,  Features Intersected: COUNCIL CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.127,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Material/Design: Prestressed concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 9.1m (29.9ft),  Curb-To-Curb Width: 8.0m (26.2ft),  Out-to-Out Width: 8.5m (27.9ft)

Condition: Deck: Poor,  Superstructure: Satisfactory,  Substructure: Poor,  Channel: Fair,  Operating Rating: 46.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 28.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 0.1 - 9.9% below),  Length Of Structure Improvement: 5.89m (19.32ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $301,000,  Roadway Improvement Cost: $165,000,  Total Project Cost: $480,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 21906,  Location: .8 S & .1 W OF TROUSDALE (Lat: 35.029172,  Lng: -97.045686),  Route carried "on" structure: County highway E1370,  Year Built: 1988,  Status: Posted for load,  Structure Length: 1.52m (4.99ft),  Average Daily Traffic: 75 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 120 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.805,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Skew: 3 degrees,  Material/Design: Steel,  Design/Construction: Girder and Floorbeam System,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 13.1m (43.0ft),  Curb-To-Curb Width: 5.7m (18.7ft),  Out-to-Out Width: 5.7m (18.7ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Fair,  Channel: Fair,  Operating Rating: 23.6 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 13.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 4.31m (14.14ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Critical Feature Inspection Date: August 2021,  Bridge Improvement Cost: $220,000,  Roadway Improvement Cost: $121,000,  Total Project Cost: $350,000 ( Estimate for 2015),  Deck Structure Type: Corrugated Steel,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 2198,  Location: 1.0 MI E SH 102 (Lat: 35.145053,  Lng: -97.037064),  Route carried "on" structure: State highway 59B,  Year Built: 1988,  Status: Open,  Structure Length: 3.20m (10.50ft),  Average Daily Traffic: 660 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 1,056 (year 2040),  Design Load: HS 20,  Features Intersected: COON CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.593,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Skew: 4 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 30.5m (100.1ft),  Curb-To-Curb Width: 9.8m (32.2ft),  Out-to-Out Width: 10.4m (34.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Fair,  Operating Rating: 88.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 39.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.39m (20.96ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $545,000,  Roadway Improvement Cost: $899,000,  Total Project Cost: $1,525,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 22633,  Location: 1.2N & 1.3W OF TROUSDALE (Lat: 35.058114,  Lng: -97.065997),  Route carried "on" structure: County highway E1350,  Year Built: 1990,  Status: Open,  Structure Length: 3.67m (12.04ft),  Average Daily Traffic: 50 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 80 (year 2040),  Design Load: HS 20,  Features Intersected: SALT CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.483,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 3 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 15.2m (49.9ft),  Curb-To-Curb Width: 8.0m (26.2ft),  Out-to-Out Width: 8.5m (27.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Fair,  Operating Rating: 55.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.86m (22.51ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $351,000,  Roadway Improvement Cost: $193,000,  Total Project Cost: $560,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 23671,  Location: 0.1 E 192ND AVE SE (Lat: 35.043828,  Lng: -97.157725),  Route carried "on" structure: County highway E1360,  Year Built: 1994,  Status: Posted for load,  Structure Length: 2.33m (7.64ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Design Load: H 15,  Features Intersected: POND CREEK,  Facility Carried by Structure: YORK RD.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.161,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 23.0m (75.5ft),  Curb-To-Curb Width: 6.9m (22.6ft),  Out-to-Out Width: 7.3m (24.0ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Satisfactory,  Channel: Fair,  Operating Rating: 20.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 12.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 20.0 - 29.9% below),  Length Of Structure Improvement: 5.43m (17.81ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 24 months,  Inspection Date: September 2021,  Critical Feature Inspection Date: September 2021,  Other Special Inspection Date: August 2020,  Bridge Improvement Cost: $277,000,  Roadway Improvement Cost: $152,000,  Total Project Cost: $442,000 ( Estimate for 2015),  Deck Structure Type: Other,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 24088,  Location: 3.9 MI N SH 39 (Lat: 35.043403,  Lng: -97.036328),  Route carried "on" structure: State highway 102,  Year Built: 1996,  Status: Open,  Structure Length: 3.69m (12.11ft),  Average Daily Traffic: 400 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 640 (year 2040),  Design Load: HS 20,  Features Intersected: SALT CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 6.387,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 15.2m (49.9ft),  Curb-To-Curb Width: 9.8m (32.2ft),  Out-to-Out Width: 10.4m (34.1ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Very good,  Channel: Satisfactory,  Operating Rating: 52.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 31.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.89m (22.60ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $581,000,  Roadway Improvement Cost: $959,000,  Total Project Cost: $1,627,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 24091,  Location: 3.5 MI N SH 39 (Lat: 35.036847,  Lng: -97.036286),  Route carried "on" structure: State highway 102,  Year Built: 1996,  Status: Open,  Structure Length: 3.72m (12.20ft),  Average Daily Traffic: 400 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 640 (year 2040),  Design Load: HS 20,  Features Intersected: WOLF CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 9.115,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Skew: 3 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 36.6m (120.1ft),  Curb-To-Curb Width: 9.8m (32.2ft),  Out-to-Out Width: 10.4m (34.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Very good,  Channel: Satisfactory,  Inventory Rating: 41.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.92m (22.70ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $583,000,  Roadway Improvement Cost: $962,000,  Total Project Cost: $1,633,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 2635,  Location: .2 N & 3.4 W OF TRIBBEY (Lat: 35.116203,  Lng: -97.114006),  Route carried "on" structure: County highway E1310,  Year Built: 2000,  Status: Open,  Structure Length: 1.54m (5.05ft),  Average Daily Traffic: 50 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 80 (year 2040),  Design Load: HS 20,  Features Intersected: COUNCIL CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.805,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 14.9m (48.9ft),  Curb-To-Curb Width: 6.9m (22.6ft),  Out-to-Out Width: 7.2m (23.6ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Fair,  Channel: Fair,  Operating Rating: 65.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 39.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.36m (14.30ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $223,000,  Roadway Improvement Cost: $122,000,  Total Project Cost: $354,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 26387,  Location: .5 W OF ANDERSON (Lat: 35.087300,  Lng: -96.994169),  Route carried "on" structure: County highway 6330C,  Year Built: 2000,  Status: Posted for load,  Structure Length: 2.13m (6.99ft),  Average Daily Traffic: 300 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 480 (year 2040),  Design Load: HS 20,  Features Intersected: E. COTTONWOOD CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.265,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 20.7m (67.9ft),  Curb-To-Curb Width: 8.1m (26.6ft),  Out-to-Out Width: 8.5m (27.9ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Fair,  Operating Rating: 40.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 24.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 0.1 - 9.9% below),  Length Of Structure Improvement: 5.16m (16.93ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021,  Bridge Improvement Cost: $263,000,  Roadway Improvement Cost: $145,000,  Total Project Cost: $420,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 26397,  Location: .9N & 1.6W OF TROUSDALE (Lat: 35.056217,  Lng: -97.071619),  Route carried "on" structure: County highway N3330,  Year Built: 2000,  Status: Open,  Structure Length: 1.49m (4.89ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Design Load: HS 20,  Features Intersected: AURORA CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.483,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 14.3m (46.9ft),  Curb-To-Curb Width: 7.2m (23.6ft),  Out-to-Out Width: 7.3m (24.0ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 71.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 42.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 4.27m (14.01ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2021,  Bridge Improvement Cost: $218,000,  Roadway Improvement Cost: $120,000,  Total Project Cost: $347,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 264,  Location: 1.2N & .3W OF TROUSDALE (Lat: 35.058008,  Lng: -97.050506),  Route carried "on" structure: County highway E1350,  Year Built: 2000,  Status: Open,  Structure Length: 1.29m (4.23ft),  Average Daily Traffic: 75 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 120 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.483,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 12.4m (40.7ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 7.5m (24.6ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Fair,  Operating Rating: 48.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 28.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.95m (12.96ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $202,000,  Roadway Improvement Cost: $111,000,  Total Project Cost: $321,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 27456,  Location: .8 S & .5 W OF TROUSDALE (Lat: 35.029178,  Lng: -97.052236),  Route carried "on" structure: County highway E1370,  Year Built: 2003,  Status: Open,  Structure Length: 0.94m (3.08ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.161,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.8m (28.9ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 7.5m (24.6ft)

Condition: Deck: Good,  Superstructure: Fair,  Substructure: Satisfactory,  Channel: Fair,  Operating Rating: 56.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.05m (10.01ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $188,000,  Roadway Improvement Cost: $94,000,  Total Project Cost: $313,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 28044,  Location: .2N & .1W OF TROUSDALE (Lat: 35.043614,  Lng: -97.045403),  Route carried "on" structure: County highway E1360,  Year Built: 2002,  Status: Open,  Structure Length: 0.96m (3.15ft),  Average Daily Traffic: 24 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 38 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.805,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.1m (29.9ft),  Curb-To-Curb Width: 8.4m (27.6ft),  Out-to-Out Width: 8.5m (27.9ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Fair,  Operating Rating: 69.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 41.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.41m (11.19ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $196,000,  Roadway Improvement Cost: $293,000,  Total Project Cost: $562,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 28085,  Location: 3.1 S & .9 W OF TRIBBEY (Lat: 35.067625,  Lng: -97.071706),  Route carried "on" structure: County highway N3330,  Year Built: 2003,  Status: Open,  Structure Length: 1.19m (3.90ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.483,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 11.3m (37.1ft),  Curb-To-Curb Width: 8.2m (26.9ft),  Out-to-Out Width: 8.3m (27.2ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 58.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 34.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.32m (4.33ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2021,  Bridge Improvement Cost: $140,000,  Roadway Improvement Cost: $70,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 2946,  Location: 2.7S 3.1E OF TRIBBEY (Lat: 35.074167,  Lng: -97.001944),  Route carried "on" structure: County highway N3370,  Year Built: 2008,  Status: Open,  Structure Length: 1.52m (4.99ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Design Load: HS 20,  Features Intersected: COTTONWOOD CREEK,  Facility Carried by Structure: NS3370
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.448,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Skew: 3 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 14.7m (48.2ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 8.1m (26.6ft)

Condition: Deck: Good,  Superstructure: Fair,  Substructure: Fair,  Channel: Fair,  Operating Rating: 57.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 34.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021,  Bridge Improvement Cost: $174,000,  Roadway Improvement Cost: $87,000,  Total Project Cost: $278,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 29461,  Location: 3S .5W OF ANDERSON (Lat: 35.043911,  Lng: -96.990761),  Route carried "on" structure: County highway E1360,  Year Built: 2008,  Status: Open,  Structure Length: 1.04m (3.41ft),  Average Daily Traffic: 50 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 80 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.805,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 10.1m (33.1ft),  Curb-To-Curb Width: 8.1m (26.6ft),  Out-to-Out Width: 8.2m (26.9ft)

Condition: Deck: Good,  Superstructure: Fair,  Substructure: Satisfactory,  Channel: Fair,  Operating Rating: 65.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 39.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021,  Bridge Improvement Cost: $119,000,  Roadway Improvement Cost: $60,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 29615,  Location: .2 N & .4 E OF TRIBBEY (Lat: 35.116111,  Lng: -97.049722),  Route carried "on" structure: County highway 6326C,  Year Built: 2010,  Status: Open,  Structure Length: 2.67m (8.76ft),  Average Daily Traffic: 60 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 90 (year 2040),  Design Load: HS 20,  Features Intersected: COON CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.483,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 25.9m (85.0ft),  Curb-To-Curb Width: 8.2m (26.9ft),  Out-to-Out Width: 8.7m (28.5ft)

Condition: Deck: Very good,  Superstructure: Good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 98.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 46.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 29616,  Location: .2 N & .5 E OF TRIBBEY (Lat: 35.116111,  Lng: -97.048611),  Route carried "on" structure: County highway 6326C,  Year Built: 2010,  Status: Open,  Structure Length: 2.98m (9.78ft),  Average Daily Traffic: 60 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 90 (year 2040),  Design Load: HS 20,  Features Intersected: COON CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.644,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 3 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 29.0m (95.1ft),  Curb-To-Curb Width: 8.0m (26.2ft),  Out-to-Out Width: 8.5m (27.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 99.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 41.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 31729,  Location: .4E 192ND AVE SE (Lat: 35.029328,  Lng: -97.153161),  Route carried "on" structure: County highway E1370,  Year Built: 2017,  Status: Open,  Structure Length: 1.98m (6.50ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Design Load: H 20,  Features Intersected: POND CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.644,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 19.8m (65.0ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 8.1m (26.6ft),  Out-to-Out Width: 8.4m (27.6ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 44.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 26.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.05m (10.01ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021,  Bridge Improvement Cost: $1,000,000,  Roadway Improvement Cost: $500,000,  Total Project Cost: $2,000,000 ( Estimate for 2017),  Deck Structure Type: Corrugated Steel,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 32448,  Location: .1W 192ND AVE SE (Lat: 35.058258,  Lng: -97.161886),  Route carried "on" structure: County highway E1350,  Year Built: 2021,  Status: Open,  Structure Length: 1.74m (5.71ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Design Load: HS 20,  Features Intersected: POND CREEK
Minimum Vertical Clearance: 30.45m (99.90ft),  Kilometerpoint: 2.330,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 4.9m (16.1ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 17.2m (56.4ft),  Curb-To-Curb Width: 8.2m (26.9ft),  Out-to-Out Width: 8.2m (26.9ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 64.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 38.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021,  Deck Structure Type: Concrete Cast-file-Place
Discuss Tribbey, Oklahoma (OK) on our hugely popular Oklahoma forum.


City-data.com does not guarantee the accuracy or timeliness of any information on this site.  Use at your own risk.
Some parts © 2024 Advameg, Inc.