Jump to a detailed profile or search site with Google Custom Search

Bridge Statistics for Wellsville, New York (NY)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 21Number of bridges
  • 197ft / 59.9mTotal length
  • $34,568,000Total costs
  • 67,942Total average daily traffic
  • 3,187Total average daily truck traffic
  • National Bridge Inventory (NBI) Registered Bridges for Wellsville
  • No street view available for this location

New bridges in Wellsville, NY - historical statistics
  • New bridges - historical statistics
  • 11920-1929
  • 11940-1949
  • 81970-1979
  • 21980-1989
  • 31990-1999
  • 42000-2009
  • 12010-2019
  • 12020-2022
Reconstructed bridges in Wellsville, NY - Historical Statistics
  • Reconstructed bridges - Historical Statistics
  • 11950-1959
  • 01960-1969
  • 01970-1979
  • 01980-1989
  • 01990-1999
  • 22000-2009
Average Bridge Daily Traffic in Wellsville, NY
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 12.5%Excellent
  • 6.3%Very good
  • 18.8%Good
  • 31.3%Satisfactory
  • 31.3%Fair
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 5.9%Excellent
  • 11.8%Very good
  • 35.3%Good
  • 23.5%Satisfactory
  • 23.5%Fair
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 17.6%Excellent
  • 23.5%Very good
  • 17.6%Good
  • 17.6%Satisfactory
  • 17.6%Fair
  • 5.9%Poor
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 11.1%Excellent
  • 16.7%Very good
  • 22.2%Good
  • 22.2%Satisfactory
  • 27.8%Fair
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 50.0%Good
  • 50.0%Satisfactory
Find on map >>   Show street view

Structure Number: 101243,  Location: 1.6 MI W JCT RTS 19 & 417 (Lat: 42.124722,  Lng: -77.989681),  Route carried "on" structure: State highway 417,  Year Built: 2000,  Status: Open,  Structure Length: 2.13m (6.99ft),  Average Daily Traffic: 3,320 (year 2019),  Truck Traffic: 7%,  Average Future Daily Traffic: 4,033 (year 2040),  Design Load: HS 25 or greater,  Features Intersected: BRIMMER BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 33.001,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Skew: 4 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 19.5m (64.0ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 13.5m (44.3ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 76.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 45.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.13m (6.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Bridge Improvement Cost: $919,000,  Roadway Improvement Cost: $538,000,  Total Project Cost: $1,457,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 101244,  Location: .3 MI W SR 19 & SR 417 (Lat: 42.127044,  Lng: -77.965231),  Route carried "on" structure: State highway 417,  Year Built: 2007,  Status: Open,  Structure Length: 1.04m (3.41ft),  Average Daily Traffic: 9,866 (year 2020),  Truck Traffic: 4%,  Average Future Daily Traffic: 11,985 (year 2040),  Design Load: HS 25 or greater,  Features Intersected: CROWNER BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 35.076,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.5m (41.0ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 10.1m (33.1ft),  Curb or Sidewalk Widths: Left: 2.4m (7.9ft),  Right: 2.0m (6.6ft),  Curb-To-Curb Width: 12.6m (41.3ft),  Out-to-Out Width: 17.0m (55.8ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 70.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 42.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.03m (3.38ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021,  Bridge Improvement Cost: $383,000,  Roadway Improvement Cost: $224,000,  Total Project Cost: $607,000 ( Estimate for 2021)
Find on map >>   Show street view

Structure Number: 101245,  Location: JCT SR 417 & GENESEE RIVE (Lat: 42.128308,  Lng: -77.960656),  Route carried "on" structure: State highway 417,  Year Built: 1988,  Status: Open,  Structure Length: 7.28m (23.88ft),  Average Daily Traffic: 9,866 (year 2020),  Truck Traffic: 4%,  Average Future Daily Traffic: 11,985 (year 2040),  Design Load: HS 20,  Features Intersected: GENESEE RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 35.462,  Lanes on structure: 3,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 28.0m (91.9ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 0.0m,  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 14.4m (47.2ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 50.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 29.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 7.28m (23.88ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $2,709,000,  Roadway Improvement Cost: $1,587,000,  Total Project Cost: $4,296,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 101248,  Location: 1 MI NE SR 19 + SR 417 (Lat: 42.126933,  Lng: -77.925928),  Route carried "on" structure: State highway 417,  Year Built: 1992,  Status: Open,  Structure Length: 5.39m (17.68ft),  Average Daily Traffic: 3,264 (year 2018),  Truck Traffic: 10%,  Average Future Daily Traffic: 3,965 (year 2040),  Design Load: HS 20,  Features Intersected: DYKE CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 39.565,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Skew: 3 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 53.3m (174.9ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 11.6m (38.1ft)

Condition: Deck: Fair,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Fair,  Operating Rating: 83.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 39.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 5.39m (17.68ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2020,  Bridge Improvement Cost: $1,881,000,  Roadway Improvement Cost: $1,102,000,  Total Project Cost: $2,983,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 101249,  Location: 2 MI NE JCT SR19 & SR417 (Lat: 42.133656,  Lng: -77.913006),  Route carried "on" structure: State highway 417,  Year Built: 2012,  Status: Open,  Structure Length: 1.28m (4.20ft),  Average Daily Traffic: 4,337 (year 2018),  Truck Traffic: 8%,  Average Future Daily Traffic: 5,268 (year 2040),  Design Load: HL 93,  Features Intersected: WIGHTMAN HOLLW CK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 40.933,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Material/Design: Concrete,  Design/Construction: Frame,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 11.7m (38.4ft),  Curb-To-Curb Width: 10.4m (34.1ft),  Out-to-Out Width: 11.7m (38.4ft)

Condition: Superstructure: Very good,  Substructure: Very good,  Channel: Satisfactory,  Operating Rating: 76.5 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 59.0 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.28m (4.20ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Bridge Improvement Cost: $602,000,  Roadway Improvement Cost: $353,000,  Total Project Cost: $955,000 ( Estimate for 2021)
Find on map >>   Show street view

Structure Number: 10125,  Location: 1.2 MI SW OF ELM VALLEY (Lat: 42.146550,  Lng: -77.879469),  Route carried "on" structure: State highway 417,  Year Built: 1948,  Year Reconstructed: 1964,  Status: Open,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 4,337 (year 2018),  Truck Traffic: 8%,  Average Future Daily Traffic: 4,363 (year 2040),  Design Load: H 20,  Features Intersected: DUFFY HOLLOW CRK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 44.071,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.3m (37.1ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.1m (29.9ft),  Curb-To-Curb Width: 11.3m (37.1ft),  Out-to-Out Width: 11.7m (38.4ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Channel: Fair,  Operating Rating: 47.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 28.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.97m (3.18ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $557,000,  Roadway Improvement Cost: $326,000,  Total Project Cost: $883,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>   Show street view

Structure Number: 106977,  Location: IN WELLSVILLE (Lat: 42.117131,  Lng: -77.943678),  Route carried "on" structure: State highway 19,  Year Built: 1975,  Year Reconstructed: 2008,  Status: Open,  Structure Length: 4.30m (14.11ft),  Average Daily Traffic: 6,423 (year 2018),  Truck Traffic: 9%,  Average Future Daily Traffic: 6,453 (year 2040),  Design Load: HS 20,  Features Intersected: DYKE CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 14.980,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 20.7m (67.9ft),  Skew: 22 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 20.7m (67.9ft),  Curb-To-Curb Width: 17.7m (58.1ft),  Out-to-Out Width: 18.6m (61.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Very good,  Operating Rating: 68.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 46.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.29m (14.07ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $2,194,000,  Roadway Improvement Cost: $1,285,000,  Total Project Cost: $3,478,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 221508,  Location: IN WELLSVILLE (Lat: 42.123808,  Lng: -77.966747),  Route carried "on" structure: Other road ,  Year Built: 1970,  Status: Open,  Structure Length: 0.91m (2.99ft),  Average Daily Traffic: 994 (year 2020),  Truck Traffic: 3%,  Average Future Daily Traffic: 1,392 (year 2040),  Features Intersected: CROWNER BROOK,  Facility Carried by Structure: FASSETT LANE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.209,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.5m (27.9ft),  Curb-To-Curb Width: 7.1m (23.3ft),  Out-to-Out Width: 7.3m (24.0ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Good,  Channel: Fair,  Operating Rating: 84.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 50.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 0.91m (2.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $293,000,  Roadway Improvement Cost: $171,000,  Total Project Cost: $464,000 ( Estimate for 2021),  Deck Structure Type: Corrugated Steel,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 221511,  Location: 1.5 MI NE OF WELLSVILLE (Lat: 42.126358,  Lng: -77.917892),  Route carried "on" structure: Other road ,  Year Built: 1973,  Status: Open,  Structure Length: 1.34m (4.40ft),  Average Daily Traffic: 112 (year 2020),  Average Future Daily Traffic: 157 (year 2040),  Design Load: HS 20,  Features Intersected: TRAPPING BROOK,  Facility Carried by Structure: Proctor Road
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.241,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 4.2m (13.8ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 8.2m (26.9ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 32.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 22.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 1.34m (4.40ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Bridge Improvement Cost: $327,000,  Roadway Improvement Cost: $191,000,  Total Project Cost: $518,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 221512,  Location: 1.4 MI NE OF WELLSVILLE (Lat: 42.127717,  Lng: -77.918656),  Route carried "on" structure: Other road ,  Year Built: 1997,  Status: Open,  Structure Length: 0.91m (2.99ft),  Average Daily Traffic: 442 (year 2020),  Truck Traffic: 5%,  Average Future Daily Traffic: 619 (year 2040),  Design Load: HS 25 or greater,  Features Intersected: TRAPPING BROOK,  Facility Carried by Structure: BALDWIN ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.949,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 6.4m (21.0ft),  Material/Design: Wood or Timber,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.8m (28.9ft),  Curb-To-Curb Width: 7.2m (23.6ft),  Out-to-Out Width: 7.9m (25.9ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Very good,  Channel: Satisfactory,  Operating Rating: 83.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 59.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.91m (2.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $413,000,  Roadway Improvement Cost: $242,000,  Total Project Cost: $654,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Other
Find on map >>   Show street view

Structure Number: 221513,  Location: 1.6 MI NE OF WELLSVILLE (Lat: 42.129600,  Lng: -77.917378),  Route carried "on" structure: Other road ,  Year Built: 2008,  Status: Open,  Structure Length: 3.14m (10.30ft),  Average Daily Traffic: 694 (year 2020),  Truck Traffic: 9%,  Average Future Daily Traffic: 858 (year 2040),  Design Load: HL 93,  Features Intersected: DYKE CREEK,  Facility Carried by Structure: TRUAX ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.756,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Material/Design: Concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 30.5m (100.1ft),  Curb-To-Curb Width: 9.9m (32.5ft),  Out-to-Out Width: 10.9m (35.8ft)

Condition: Deck: Excellent,  Superstructure: Good,  Substructure: Excellent,  Channel: Very good,  Inventory Rating: 51.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 3.13m (10.27ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Bridge Improvement Cost: $968,000,  Roadway Improvement Cost: $567,000,  Total Project Cost: $1,535,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Other
Find on map >>   Show street view

Structure Number: 22155,  Location: IN WELLSVILLE (Lat: 42.119108,  Lng: -77.940167),  Route carried "on" structure: Other road ,  Year Built: 1973,  Year Reconstructed: 2000,  Status: Open,  Structure Length: 3.69m (12.11ft),  Average Daily Traffic: 350 (year 2020),  Truck Traffic: 3%,  Average Future Daily Traffic: 490 (year 2040),  Design Load: HS 20+Mod,  Features Intersected: DYKE CREEK,  Facility Carried by Structure: SOUTH BROAD ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.241,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 2 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 18.2m (59.7ft),  Curb or Sidewalk Widths: Left: 0.0m,  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 8.9m (29.2ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 53.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 35.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Meets minimum limits,  Length Of Structure Improvement: 3.68m (12.07ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2020,  Bridge Improvement Cost: $964,000,  Roadway Improvement Cost: $565,000,  Total Project Cost: $1,529,000 ( Estimate for 2021),  Deck Structure Type: Other,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 221551,  Location: IN WELLSVILLE (Lat: 42.118883,  Lng: -77.946778),  Route carried "on" structure: Other road ,  Year Built: 2002,  Status: Open,  Structure Length: 6.37m (20.90ft),  Average Daily Traffic: 2,801 (year 2018),  Truck Traffic: 3%,  Average Future Daily Traffic: 3,465 (year 2040),  Features Intersected: GENESEE RIVER,  Facility Carried by Structure: WEST STATE ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.177,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 10.1m (33.1ft),  Skew: 1 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 31.3m (102.7ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 10.2m (33.5ft),  Out-to-Out Width: 14.2m (46.6ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Excellent,  Channel: Excellent,  Operating Rating: 94.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 56.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.37m (20.90ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Bridge Improvement Cost: $2,467,000,  Roadway Improvement Cost: $1,444,000,  Total Project Cost: $3,911,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 221552,  Location: IN WELLSVILLE (Lat: 42.120600,  Lng: -77.949503),  Route carried "on" structure: Other road ,  Year Built: 1974,  Status: Open,  Structure Length: 6.49m (21.29ft),  Average Daily Traffic: 2,300 (year 2018),  Truck Traffic: 4%,  Average Future Daily Traffic: 2,845 (year 2040),  Features Intersected: GENESEE RIVER,  Facility Carried by Structure: STEVENS STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.161,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Skew: 2 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 31.3m (102.7ft),  Curb or Sidewalk Widths: Left: 1.6m (5.2ft),  Right: 1.6m (5.2ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 12.3m (40.4ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Fair,  Channel: Good,  Operating Rating: 63.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 38.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.49m (21.29ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021,  Bridge Improvement Cost: $2,336,000,  Roadway Improvement Cost: $1,368,000,  Total Project Cost: $3,703,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete
Find on map >>   Show street view

Structure Number: 22544,  Location: 1.5 MI S OF WELLSVILLE (Lat: 42.100717,  Lng: -77.938978),  Route carried "on" structure: Other road ,  Year Built: 2021,  Status: Open,  Structure Length: 3.57m (11.71ft),  Average Daily Traffic: 936 (year 2018),  Truck Traffic: 5%,  Average Future Daily Traffic: 945 (year 2040),  Design Load: HL 93,  Features Intersected: GENESEE RIVER,  Facility Carried by Structure: WEIDRICK ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.094,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 35.1m (115.2ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 10.1m (33.1ft)

Condition: Deck: Excellent,  Superstructure: Excellent,  Substructure: Excellent,  Channel: Excellent,  Inventory Rating: 61.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Superior to present desirable criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.13m (10.27ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2021,  Bridge Improvement Cost: $1,487,000,  Roadway Improvement Cost: $871,000,  Total Project Cost: $2,358,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Galvanized Reinforcing
Find on map >>   Show street view

Structure Number: 225462,  Location: IN WELLSVILLE (Lat: 42.117864,  Lng: -77.941292),  Route carried "on" structure: City street ,  Year Built: 1991,  Status: Open,  Structure Length: 3.75m (12.30ft),  Average Daily Traffic: 3,233 (year 2020),  Truck Traffic: 4%,  Average Future Daily Traffic: 3,927 (year 2040),  Design Load: HS 20,  Features Intersected: DYKE CREEK,  Facility Carried by Structure: SOUTH MAIN STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.306,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Skew: 2 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 17.6m (57.7ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 14.6m (47.9ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Very good,  Channel: Good,  Operating Rating: 26.9 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 18.5 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.74m (12.27ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $1,317,000,  Roadway Improvement Cost: $771,000,  Total Project Cost: $2,088,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 225464,  Location: 3 MILES NE OF WELLSVILLE (Lat: 42.142494,  Lng: -77.885081),  Route carried "on" structure: Other road ,  Year Built: 1974,  Status: Posted for load,  Structure Length: 2.83m (9.28ft),  Average Daily Traffic: 14 (year 2019),  Average Future Daily Traffic: 20 (year 2039),  Features Intersected: DYKE CREEK,  Facility Carried by Structure: WILLIAMS GROVE RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.177,  Lanes on structure: 1,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 3.7m (12.1ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 14.0m (45.9ft),  Curb-To-Curb Width: 3.7m (12.1ft),  Out-to-Out Width: 3.8m (12.5ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Poor,  Channel: Fair,  Operating Rating: 20.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 11.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 2.83m (9.28ft),  Designated Inspection Frequency: Every 12 months,  Critical Feature Inspection Frequency: Every 12 months,  Inspection Date: September 2021,  Critical Feature Inspection Date: September 2021,  Bridge Improvement Cost: $417,000,  Roadway Improvement Cost: $244,000,  Total Project Cost: $662,000 ( Estimate for 2021),  Deck Structure Type: Open Grating,  Wearing Surface/Protective System: Wearing Surface: Other
Find on map >>   Show street view

Structure Number: 225516,  Location: IN WELLSVILLE (Lat: 42.122614,  Lng: -77.946864),  Route carried "on" structure: Other road ,  Year Built: 1970,  Status: Open,  Structure Length: 3.47m (11.38ft),  Average Daily Traffic: 1,502 (year 2017),  Truck Traffic: 3%,  Average Future Daily Traffic: 1,858 (year 2040),  Design Load: HS 20+Mod,  Features Intersected: Norfolk-Southern Railroa,  Facility Carried by Structure: MADISON STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.113,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 11.5m (37.7ft),  Curb or Sidewalk Widths: Left: 1.6m (5.2ft),  Right: 1.6m (5.2ft),  Curb-To-Curb Width: 8.6m (28.2ft),  Out-to-Out Width: 12.4m (40.7ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Operating Rating: 46.0 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 35.3 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Meets minimum limits,  Length Of Structure Improvement: 3.47m (11.38ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $1,066,000,  Roadway Improvement Cost: $624,000,  Total Project Cost: $1,690,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 335762,  Location: 1.8 MI E OF WELLSVILLE (Lat: 42.120675,  Lng: -77.907533),  Route carried "on" structure: County highway ,  Year Built: 1985,  Status: Open,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 659 (year 2020),  Truck Traffic: 8%,  Average Future Daily Traffic: 815 (year 2040),  Features Intersected: TRAPPING BROOK,  Facility Carried by Structure: COUNTY ROAD 30
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.818,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.4m (21.0ft),  Skew: 3 degrees,  Material/Design: Wood or Timber,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.4m (30.8ft),  Curb-To-Curb Width: 9.2m (30.2ft),  Out-to-Out Width: 10.0m (32.8ft)

Condition: Deck: Fair,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Fair,  Operating Rating: 35.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 25.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.97m (3.18ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $503,000,  Roadway Improvement Cost: $294,000,  Total Project Cost: $797,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Other
Find on map >>   Show street view

Structure Number: 106945,  Location: IN WELLSVILLE (Lat: 42.118250,  Lng: -77.945144),  Route carried "under" structure: State highway ,  Year Built: 1977,  Structure Length: 0. m,  Average Daily Traffic: 9,700 (year 1975),  Features Intersected: 19 19 61011595, DYKE CRE,  Facility Carried by Structure: PEDESTRIAN BRIDGE
Minimum Vertical Clearance: 4.47m (14.67ft),  Kilometerpoint: 95.623,  Lanes under structure: 4,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 40.8m (133.9ft)

Find on map >>   Show street view

Structure Number: 701247,  Location: 0.7 MI NE JCT RTS 417&19 (Lat: 42.122303,  Lng: -77.928983),  Route carried "under" structure: State highway 417,  Year Built: 1929,  Structure Length: 0. m,  Average Daily Traffic: 2,792 (year 2002),  Features Intersected: RTE 417,  Facility Carried by Structure: WNYP
Minimum Vertical Clearance: 4.52m (14.83ft),  Kilometerpoint: 39.067,  Lanes under structure: 2,  Material/Design: Steel,  Design/Construction: Girder and Floorbeam System,  Length of Maximum Span: 24.3m (79.7ft)

Discuss Wellsville, New York (NY) on our hugely popular New York forum.


City-data.com does not guarantee the accuracy or timeliness of any information on this site.  Use at your own risk.