  • 83Number of bridges
  • 1,142ft / 348mTotal length
  • $71,648,000Total costs
  • 129,812Total average daily traffic
  • 22,073Total average daily truck traffic
  • 207,699Total future (year 2040) average daily traffic
  • National Bridge Inventory (NBI) Registered Bridges for Asher
  • No street view available for this location

New bridges in Asher, OK - historical statistics
  • New bridges - historical statistics
  • 31910-1919
  • 201920-1929
  • 71930-1939
  • 231940-1949
  • 111950-1959
  • 91960-1969
  • 11970-1979
  • 11980-1989
  • 41990-1999
  • 42010-2019
Reconstructed bridges in Asher, OK - Historical Statistics
  • Reconstructed bridges - Historical Statistics
  • 31940-1949
  • 31950-1959
  • 11960-1969
  • 11970-1979
  • 01980-1989
  • 31990-1999
  • 32000-2009
Average Bridge Daily Traffic in Asher, OK
Average Bridge Truck Traffic in Asher, OK
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 6.7%Very good
  • 11.1%Good
  • 37.8%Satisfactory
  • 31.1%Fair
  • 8.9%Poor
  • 4.4%Failed
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 4.3%Very good
  • 21.3%Good
  • 21.3%Satisfactory
  • 29.8%Fair
  • 17.0%Poor
  • 2.1%Serious
  • 4.3%Failed
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 2.1%Very good
  • 14.9%Good
  • 25.5%Satisfactory
  • 40.4%Fair
  • 8.5%Poor
  • 4.3%Serious
  • 4.3%Failed
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 3.8%Very good
  • 26.9%Good
  • 26.9%Satisfactory
  • 29.5%Fair
  • 9.0%Poor
  • 3.8%Serious
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 5.6%Very good
  • 36.1%Good
  • 38.9%Satisfactory
  • 16.7%Fair
  • 2.8%Serious
Find on map >>   Show street view

Structure Number: 629,  Location: 2N10W2N1.6W OF BUFFALO (Lat: 36.899733,  Lng: -99.827489),  Route carried "on" structure: County highway E0080,  Year Built: 1918,  Status: Open,  Structure Length: 1.34m (4.40ft),  Average Daily Traffic: 25 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 40 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.644,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 6.1m (20.0ft),  Curb-To-Curb Width: 5.4m (17.7ft),  Out-to-Out Width: 6.1m (20.0ft)

Condition: Deck: Poor,  Superstructure: Fair,  Substructure: Fair,  Channel: Poor,  Operating Rating: 32.7 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 19.1 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.03m (13.22ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2021,  Bridge Improvement Cost: $206,000,  Roadway Improvement Cost: $113,000,  Total Project Cost: $327,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Other
Find on map >>   Show street view

Structure Number: 63,  Location: 1S 1.4E OF MILL CREEK (Lat: 34.390272,  Lng: -96.804269),  Route carried "on" structure: County highway 3544C,  Year Built: 1918,  Status: Posted for load,  Structure Length: 1.40m (4.59ft),  Average Daily Traffic: 120 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 192 (year 2040),  Design Load: HS 20,  Features Intersected: ROCK CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.644,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Arch - Deck,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 6.7m (22.0ft),  Curb-To-Curb Width: 5.6m (18.4ft),  Out-to-Out Width: 6.0m (19.7ft)

Condition: Superstructure: Poor,  Substructure: Fair,  Channel: Fair,  Operating Rating: 12.7 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 7.3 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: High priority of replacement,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 4.22m (13.85ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $216,000,  Roadway Improvement Cost: $119,000,  Total Project Cost: $343,000 ( Estimate for 2015),  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 645,  Location: .4 MI S JCT SH7 (Lat: 34.504467,  Lng: -96.969211),  Route carried "on" structure: US 177,  Year Built: 1940,  Status: Open,  Structure Length: 1.43m (4.69ft),  Average Daily Traffic: 3,000 (year 2020),  Truck Traffic: 16%,  Average Future Daily Traffic: 4,800 (year 2040),  Design Load: H 15,  Features Intersected: TRAVERTINE CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 19.565,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Skew: 6 degrees,  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 4.3m (14.1ft),  Curb-To-Curb Width: 8.8m (28.9ft),  Out-to-Out Width: 9.4m (30.8ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 32.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 19.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.17m (13.68ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2020,  Bridge Improvement Cost: $400,000,  Roadway Improvement Cost: $660,000,  Total Project Cost: $1,120,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 699,  Location: 2S .6W JCT SH10/SH137 (Lat: 36.842222,  Lng: -94.800000),  Route carried "on" structure: County highway E0120,  Year Built: 1919,  Status: Posted for load,  Structure Length: 0.85m (2.79ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.644,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 5.0m (16.4ft),  Material/Design: Concrete,  Design/Construction: Arch - Deck,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 1.8m (5.9ft),  Curb-To-Curb Width: 5.7m (18.7ft),  Out-to-Out Width: 6.0m (19.7ft)

Condition: Superstructure: Poor,  Substructure: Serious,  Channel: Serious,  Operating Rating: 14.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 8.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: High priority of replacement,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: High priority of corrective action,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 3.17m (10.40ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 24 months,  Inspection Date: September 2021,  Other Special Inspection Date: October 2020,  Bridge Improvement Cost: $162,000,  Roadway Improvement Cost: $89,000,  Total Project Cost: $256,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 972,  Location: 4.3S OF SHAMROCK (Lat: 35.847022,  Lng: -96.583542),  Route carried "on" structure: County highway N3610,  Year Built: 1920,  Status: Posted for load,  Structure Length: 1.58m (5.18ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Features Intersected: LITTLE DEEP FORK CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.127,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 15.5m (50.9ft),  Curb-To-Curb Width: 4.8m (15.7ft),  Out-to-Out Width: 4.8m (15.7ft)

Condition: Deck: Fair,  Superstructure: Serious,  Substructure: Fair,  Channel: Fair,  Operating Rating: 12.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 7.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: High priority of replacement,  Deck Geometry: Equal to present desirable criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 4.40m (14.44ft),  Designated Inspection Frequency: Every 12 months,  Critical Feature Inspection Frequency: Every 12 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: September 2021,  Critical Feature Inspection Date: September 2021,  Other Special Inspection Date: March 2021,  Bridge Improvement Cost: $112,000,  Roadway Improvement Cost: $62,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 1083,  Location: 9TH ST\AGRA RD .9E (Lat: 35.971275,  Lng: -96.858031),  Route carried "on" structure: County highway E0720,  Year Built: 1920,  Year Reconstructed: 1999,  Status: Open,  Structure Length: 1.74m (5.71ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Design Load: H 20,  Features Intersected: BIG CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.448,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 16.2m (53.1ft),  Curb-To-Curb Width: 8.1m (26.6ft),  Out-to-Out Width: 8.1m (26.6ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Poor,  Channel: Satisfactory,  Operating Rating: 77.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 46.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.63m (15.19ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2021,  Bridge Improvement Cost: $236,000,  Roadway Improvement Cost: $130,000,  Total Project Cost: $376,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 1107,  Location: .9N .7E OF KENDRICK (Lat: 35.796489,  Lng: -96.765086),  Route carried "on" structure: County highway E0840,  Year Built: 1920,  Status: Posted for load,  Structure Length: 2.84m (9.32ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Features Intersected: NORTH BRANCH CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.483,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Number Of Approach Spans: 2,  Length of Maximum Span: 18.6m (61.0ft),  Curb-To-Curb Width: 4.2m (13.8ft),  Out-to-Out Width: 5.0m (16.4ft)

Condition: Deck: Fair,  Superstructure: Poor,  Substructure: Fair,  Channel: Fair,  Operating Rating: 4.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 2.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: High priority of replacement,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: High priority of corrective action,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 5.99m (19.65ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2021,  Critical Feature Inspection Date: Febuary 2021,  Other Special Inspection Date: Febuary 2020,  Bridge Improvement Cost: $153,000,  Roadway Improvement Cost: $84,000,  Total Project Cost: $242,000 ( Estimate for 2015),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>   Show street view

Structure Number: 1273,  Location: 6.1N OF MUSKOGEE CO (Lat: 36.567764,  Lng: -96.096269),  Route carried "on" structure: County highway 72,  Year Built: 1922,  Status: Posted for load,  Structure Length: 1.95m (6.40ft),  Average Daily Traffic: 3,440 (year 2020),  Truck Traffic: 5%,  Average Future Daily Traffic: 5,504 (year 2040),  Design Load: H 20,  Features Intersected: COWETA CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 9.880,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 18.3m (60.0ft),  Curb-To-Curb Width: 5.3m (17.4ft),  Out-to-Out Width: 5.5m (18.0ft)

Condition: Deck: Fair,  Superstructure: Poor,  Substructure: Fair,  Channel: Fair,  Operating Rating: 22.5 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 14.2 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Meets minimum limits,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 20.0 - 29.9% below),  Length Of Structure Improvement: 4.92m (16.14ft),  Designated Inspection Frequency: Every 12 months,  Critical Feature Inspection Frequency: Every 12 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: October 2021,  Critical Feature Inspection Date: October 2021,  Other Special Inspection Date: Febuary 2021,  Bridge Improvement Cost: $251,000,  Roadway Improvement Cost: $138,000,  Total Project Cost: $400,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1323,  Location: 3.6N OF IDABEL (Lat: 33.951944,  Lng: -94.826133),  Route carried "on" structure: County highway 4560C,  Year Built: 1923,  Year Reconstructed: 1940,  Status: Posted for load,  Structure Length: 1.22m (4.00ft),  Average Daily Traffic: 1,000 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 1,600 (year 2040),  Design Load: H 15,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 35.398,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 5.8m (19.0ft),  Material/Design: Concrete continuous,  Design/Construction: Slab,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 6.1m (20.0ft),  Curb-To-Curb Width: 6.1m (20.0ft),  Out-to-Out Width: 6.8m (22.3ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 32.7 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 19.1 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 3.83m (12.57ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $196,000,  Roadway Improvement Cost: $108,000,  Total Project Cost: $311,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1327,  Location: 167ST S. .5 E. 161ST E. (Lat: 35.923717,  Lng: -95.789317),  Route carried "on" structure: County highway E0754,  Year Built: 1923,  Status: Open,  Structure Length: 1.37m (4.49ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.805,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 5.3m (17.4ft),  Material/Design: Concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 12.5m (41.0ft),  Curb-To-Curb Width: 5.8m (19.0ft),  Out-to-Out Width: 6.7m (22.0ft)

Condition: Deck: Fair,  Superstructure: Poor,  Substructure: Fair,  Channel: Fair,  Operating Rating: 38.1 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 27.2 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.03m (13.22ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2021,  Bridge Improvement Cost: $206,000,  Roadway Improvement Cost: $113,000,  Total Project Cost: $327,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1369,  Location: 2.6 E 2.3 S CAMERON (Lat: 35.104128,  Lng: -94.487372),  Route carried "on" structure: County highway N4800,  Year Built: 1924,  Year Reconstructed: 2006,  Status: Posted for load,  Structure Length: 1.08m (3.54ft),  Average Daily Traffic: 50 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 80 (year 2040),  Design Load: H 20,  Features Intersected: RIDDLE CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 4.6m (15.1ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 10.1m (33.1ft),  Curb-To-Curb Width: 4.9m (16.1ft),  Out-to-Out Width: 4.9m (16.1ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 34.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 20.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: High priority of corrective action,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 3.63m (11.91ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2021,  Bridge Improvement Cost: $93,000,  Roadway Improvement Cost: $51,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>   Show street view

Structure Number: 1391,  Location: 3 S 1.1 E OF WILZETTA (Lat: 35.506261,  Lng: -96.716244),  Route carried "on" structure: County highway E1040,  Year Built: 1924,  Status: Open,  Structure Length: 1.77m (5.81ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Design Load: H 10,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.161,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Material/Design: Concrete,  Design/Construction: Arch - Deck,  Number Of Spans In Main Unit: 1,  Number Of Approach Spans: 1,  Length of Maximum Span: 17.7m (58.1ft),  Curb-To-Curb Width: 4.9m (16.1ft),  Out-to-Out Width: 5.5m (18.0ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Channel: Fair,  Operating Rating: 32.7 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 19.1 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.67m (15.32ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2020,  Bridge Improvement Cost: $239,000,  Roadway Improvement Cost: $131,000,  Total Project Cost: $380,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 1432,  Location: 6.0 E 2.8 S OF ROCKY (Lat: 35.119114,  Lng: -98.955111),  Route carried "on" structure: County highway 7501,  Year Built: 1925,  Status: Posted for load,  Structure Length: 0.91m (2.99ft),  Average Daily Traffic: 50 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 80 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.322,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.5m (27.9ft),  Curb-To-Curb Width: 5.0m (16.4ft),  Out-to-Out Width: 5.5m (18.0ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 32.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 19.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.28m (10.76ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $168,000,  Roadway Improvement Cost: $92,000,  Total Project Cost: $265,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1442,  Location: 3. E 10.9 S OF US62-SH115 (Lat: 34.482928,  Lng: -98.574831),  Route carried "on" structure: County highway N2470,  Year Built: 1925,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.127,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.1m (20.0ft),  Curb-To-Curb Width: 5.5m (18.0ft),  Out-to-Out Width: 6.4m (21.0ft)

Condition: Deck: Poor,  Superstructure: Poor,  Substructure: Satisfactory,  Channel: Poor,  Operating Rating: 37.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 22.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.86m (9.38ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2021,  Bridge Improvement Cost: $146,000,  Roadway Improvement Cost: $80,000,  Total Project Cost: $230,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 145,  Location: 10.0 MI W COWDEN (Lat: 35.247806,  Lng: -98.881775),  Route carried "on" structure: County highway 7514,  Year Built: 1925,  Status: Open,  Structure Length: 0.79m (2.59ft),  Average Daily Traffic: 25 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 40 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 7.080,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.3m (24.0ft),  Curb-To-Curb Width: 5.2m (17.1ft),  Out-to-Out Width: 5.5m (18.0ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Channel: Good,  Operating Rating: 37.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 27.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.05m (10.01ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2021,  Bridge Improvement Cost: $156,000,  Roadway Improvement Cost: $86,000,  Total Project Cost: $246,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 1501,  Location: 1. S 5.7 W OF DILL CITY (Lat: 35.262308,  Lng: -99.236356),  Route carried "on" structure: County highway E1210,  Year Built: 1925,  Status: Open,  Structure Length: 0.91m (2.99ft),  Average Daily Traffic: 25 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 40 (year 2040),  Features Intersected: SPRING CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.483,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.5m (27.9ft),  Curb-To-Curb Width: 5.0m (16.4ft),  Out-to-Out Width: 5.7m (18.7ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 32.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 19.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.28m (10.76ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $168,000,  Roadway Improvement Cost: $92,000,  Total Project Cost: $265,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 1628,  Location: 2.2S OF SH51/SH74E (Lat: 36.083025,  Lng: -97.621694),  Route carried "on" structure: County highway N3020,  Year Built: 1925,  Status: Posted for load,  Structure Length: 5.24m (17.19ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 160 (year 2040),  Design Load: H 15,  Features Intersected: SKELETON CREEK
Minimum Vertical Clearance: 4.91m (16.11ft),  Kilometerpoint: 15.446,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Number Of Approach Spans: 2,  Length of Maximum Span: 29.9m (98.1ft),  Curb-To-Curb Width: 5.5m (18.0ft),  Out-to-Out Width: 5.8m (19.0ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Channel: Fair,  Operating Rating: 33.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 20.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 0.1 - 9.9% below),  Length Of Structure Improvement: 8.30m (27.23ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Critical Feature Inspection Date: May 2021,  Other Special Inspection Date: May 2021,  Bridge Improvement Cost: $424,000,  Roadway Improvement Cost: $233,000,  Total Project Cost: $659,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 1784,  Location: .2 N & 1.4 E OF LIMA (Lat: 35.175781,  Lng: -96.571917),  Route carried "on" structure: County highway 6718C,  Year Built: 1927,  Status: Open,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 740 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 1,184 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.644,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Serious,  Culverts: Fair,  Operating Rating: 44.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.86m (9.38ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1788,  Location: 0.2 MI E JCT S.H. 30 (Lat: 34.681686,  Lng: -99.908789),  Route carried "on" structure: US 62,  Year Built: 1927,  Year Reconstructed: 1977,  Status: Open,  Structure Length: 0.82m (2.69ft),  Average Daily Traffic: 2,300 (year 2020),  Truck Traffic: 25%,  Average Future Daily Traffic: 3,680 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.338,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 2.4m (7.9ft),  Curb-To-Curb Width: 13.7m (44.9ft),  Out-to-Out Width: 14.3m (46.9ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 37.2 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor (LRFR),  Inventory Rating: 28.7 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor (LRFR),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.82m (2.69ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2021,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 1801,  Location: 3.30 E JCT US-259 (Lat: 34.708014,  Lng: -94.544747),  Route carried "on" structure: US 59,  Year Built: 1927,  Year Reconstructed: 1957,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 870 (year 2020),  Truck Traffic: 16%,  Average Future Daily Traffic: 1,392 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 8.238,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 12.8m (42.0ft),  Out-to-Out Width: 13.4m (44.0ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 48.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 29.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.74m (2.43ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2020,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 1809,  Location: 3.1 E JCT SH-82 (Lat: 35.260672,  Lng: -95.073117),  Route carried "on" structure: State highway 9,  Year Built: 1927,  Year Reconstructed: 2002,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 6,100 (year 2020),  Truck Traffic: 16%,  Average Future Daily Traffic: 9,760 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 15.430,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 18.6m (61.0ft),  Out-to-Out Width: 19.2m (63.0ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 44.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 26.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.70m (2.30ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 1884,  Location: 2.6S 2W OF SHAMROCK (Lat: 35.872358,  Lng: -96.618997),  Route carried "on" structure: County highway E0790,  Year Built: 1927,  Status: Posted for load,  Structure Length: 2.04m (6.69ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Features Intersected: LITTLE DEEP FORK CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Number Of Approach Spans: 1,  Length of Maximum Span: 16.2m (53.1ft),  Curb-To-Curb Width: 4.9m (16.1ft),  Out-to-Out Width: 4.9m (16.1ft)

Condition: Deck: Fair,  Superstructure: Poor,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 5.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 3.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: High priority of replacement,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: High priority of corrective action,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 5.04m (16.54ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Critical Feature Inspection Date: March 2021,  Bridge Improvement Cost: $129,000,  Roadway Improvement Cost: $71,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>   Show street view

Structure Number: 2151,  Location: 3.4 MI E JCT US-283. (Lat: 35.291303,  Lng: -99.581817),  Route carried "on" structure: State highway 152,  Year Built: 1928,  Year Reconstructed: 1972,  Status: Open,  Structure Length: 4.60m (15.09ft),  Average Daily Traffic: 1,200 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 1,920 (year 2040),  Design Load: H 20,  Features Intersected: TIMBER CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 5.309,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Number Of Approach Spans: 2,  Length of Maximum Span: 24.4m (80.1ft),  Curb-To-Curb Width: 9.8m (32.2ft),  Out-to-Out Width: 10.7m (35.1ft)

Condition: Deck: Good,  Superstructure: Fair,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 53.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 7.75m (25.43ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021,  Bridge Improvement Cost: $643,000,  Roadway Improvement Cost: $1,060,000,  Total Project Cost: $1,799,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 2253,  Location: 3.0 MI NE SH51 (Lat: 35.960569,  Lng: -94.817292),  Route carried "on" structure: US 62,  Year Built: 1929,  Status: Open,  Structure Length: 1.04m (3.41ft),  Average Daily Traffic: 1,100 (year 2020),  Truck Traffic: 16%,  Average Future Daily Traffic: 1,760 (year 2040),  Design Load: H 20,  Features Intersected: EGAN CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 7.483,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Good,  Culverts: Fair,  Operating Rating: 44.5 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.04m (3.41ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 4085,  Location: CADDO CANADIAN CL (Lat: 35.540278,  Lng: -98.322778),  Route carried "on" structure: US 281,  Year Built: 1933,  Status: Posted for load,  Structure Length: 120.00m (393.70ft),  Average Daily Traffic: 1,100 (year 2020),  Truck Traffic: 16%,  Average Future Daily Traffic: 1,760 (year 2040),  Design Load: H 15,  Features Intersected: S. CANADIAN RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 38,  Number Of Approach Spans: 2,  Length of Maximum Span: 30.5m (100.1ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 7.9m (25.9ft)

Condition: Deck: Poor,  Superstructure: Poor,  Substructure: Fair,  Channel: Fair,  Operating Rating: 8.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 7.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: High priority of replacement,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 30.0 - 39.9% below),  Length Of Structure Improvement: 120.00m (393.70ft),  Designated Inspection Frequency: Every 12 months,  Critical Feature Inspection Frequency: Every 12 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: October 2021,  Critical Feature Inspection Date: October 2021,  Other Special Inspection Date: April 2021,  Bridge Improvement Cost: $6,782,000,  Roadway Improvement Cost: $4,500,000,  Total Project Cost: $11,920,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 4125,  Location: 12 MI N JCT SH 3 (Lat: 36.786975,  Lng: -101.316211),  Route carried "on" structure: US 54,  Year Built: 1934,  Year Reconstructed: 2000,  Status: Open,  Structure Length: 0.73m (2.40ft),  Average Daily Traffic: 6,200 (year 2020),  Truck Traffic: 25%,  Average Future Daily Traffic: 9,920 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 19.422,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 23.8m (78.1ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 30.5m (100.1ft),  Out-to-Out Width: 65.5m (214.9ft)

Condition: Channel: Good,  Culverts: Very good,  Operating Rating: 53.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.73m (2.40ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 4126,  Location: 3.3 MI S ROGER MILLS C/L (Lat: 35.373883,  Lng: -99.911406),  Route carried "on" structure: State highway 30,  Year Built: 1934,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 770 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 1,232 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 19.454,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 9.8m (32.2ft),  Out-to-Out Width: 10.4m (34.1ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 54.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 0.70m (2.30ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 5279,  Location: 2.5 N & 2.8 E OF WANETTE (Lat: 34.998864,  Lng: -96.984172),  Route carried "on" structure: County highway 6372C,  Year Built: 1937,  Status: Open,  Structure Length: 0.87m (2.85ft),  Average Daily Traffic: 50 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 80 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.529,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.0m (13.1ft),  Curb-To-Curb Width: 8.9m (29.2ft),  Out-to-Out Width: 9.5m (31.2ft)

Condition: Channel: Poor,  Culverts: Satisfactory,  Operating Rating: 44.5 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.41m (11.19ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 627,  Location: 2.3W 0.5N OF MIAMI (Lat: 36.928911,  Lng: -94.920069),  Route carried "on" structure: County highway E0060,  Year Built: 1938,  Status: Posted for load,  Structure Length: 1.10m (3.61ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.127,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 8.5m (27.9ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Channel: Poor,  Operating Rating: 33.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 20.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 10.0 - 19.9% below),  Length Of Structure Improvement: 3.68m (12.07ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2021,  Bridge Improvement Cost: $188,000,  Roadway Improvement Cost: $103,000,  Total Project Cost: $298,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 636,  Location: .9 W & 2. N COGAR (Lat: 35.362894,  Lng: -98.146575),  Route carried "on" structure: County highway E1140,  Year Built: 1938,  Status: Posted for load,  Structure Length: 1.40m (4.59ft),  Average Daily Traffic: 50 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 80 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.161,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 8.5m (27.9ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Poor,  Operating Rating: 36.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 20.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 0.1 - 9.9% below),  Length Of Structure Improvement: 4.12m (13.52ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2020,  Bridge Improvement Cost: $211,000,  Roadway Improvement Cost: $116,000,  Total Project Cost: $335,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Other
Find on map >>   Show street view

Structure Number: 6804,  Location: .8 N & 1.6 W OF ASHER (Lat: 35.000356,  Lng: -96.956014),  Route carried "on" structure: County highway E1390,  Year Built: 1939,  Year Reconstructed: 1995,  Status: Temporarily open,  Structure Length: 0.67m (2.20ft),  Average Daily Traffic: 50 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 80 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.127,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Skew: 1 degrees,  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.2m (20.3ft),  Curb-To-Curb Width: 4.9m (16.1ft),  Out-to-Out Width: 4.9m (16.1ft)

Condition: Deck: Failed,  Superstructure: Failed,  Substructure: Failed,  Channel: Serious,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 2.79m (9.15ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021,  Bridge Improvement Cost: $80,000,  Roadway Improvement Cost: $40,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>   Show street view

Structure Number: 8,  Location: .7 N & 2.2 E OF ASHER (Lat: 35.000206,  Lng: -96.887656),  Route carried "on" structure: County highway E1390,  Year Built: 1992,  Status: Temporarily open,  Structure Length: 0.91m (2.99ft),  Average Daily Traffic: 50 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 80 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.805,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.5m (27.9ft),  Curb-To-Curb Width: 6.1m (20.0ft),  Out-to-Out Width: 6.1m (20.0ft)

Condition: Deck: Failed,  Superstructure: Failed,  Substructure: Failed,  Channel: Satisfactory,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: High priority of corrective action,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 3.28m (10.76ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021,  Bridge Improvement Cost: $168,000,  Roadway Improvement Cost: $92,000,  Total Project Cost: $265,000 ( Estimate for 2015),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>   Show street view

Structure Number: 8176,  Location: 0.8 MI E JCT US 177 (Lat: 34.985850,  Lng: -96.915133),  Route carried "on" structure: State highway 39,  Year Built: 1940,  Year Reconstructed: 1952,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 1,500 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 2,400 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.368,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 7.3m (24.0ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 37.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 22.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.70m (2.30ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Other Special Inspection Date: November 2021,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 8182,  Location: 2.24 MI E JCT US 177 (Lat: 34.985689,  Lng: -96.890606),  Route carried "on" structure: State highway 39,  Year Built: 1940,  Year Reconstructed: 1952,  Status: Open,  Structure Length: 0.67m (2.20ft),  Average Daily Traffic: 1,500 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 2,400 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.603,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 7.3m (24.0ft)

Condition: Channel: Fair,  Culverts: Satisfactory,  Operating Rating: 57.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 34.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.67m (2.20ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 8183,  Location: 2.65 MI E JCT US 177 (Lat: 34.985700,  Lng: -96.883514),  Route carried "on" structure: State highway 39,  Year Built: 1940,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 1,500 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 2,400 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 6.862,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 7.3m (24.0ft)

Condition: Channel: Fair,  Culverts: Satisfactory,  Operating Rating: 50.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 30.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.70m (2.30ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 8189,  Location: 3.7 MI E JCT US 177 (Lat: 34.985633,  Lng: -96.864772),  Route carried "on" structure: State highway 39,  Year Built: 1940,  Status: Open,  Structure Length: 0.67m (2.20ft),  Average Daily Traffic: 1,500 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 2,400 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 5.969,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Poor,  Culverts: Satisfactory,  Operating Rating: 32.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 19.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.67m (2.20ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 8708,  Location: 2.3 MI E JCT US 177 (Lat: 34.985683,  Lng: -96.889833),  Route carried "on" structure: State highway 39,  Year Built: 1940,  Status: Open,  Structure Length: 1.01m (3.31ft),  Average Daily Traffic: 1,500 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 2,400 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.685,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 7.3m (24.0ft)

Condition: Channel: Poor,  Culverts: Fair,  Operating Rating: 35.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 25.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.01m (3.31ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Other Special Inspection Date: November 2021,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 10828,  Location: 2.6 MI N JCT U.S. 70 (Lat: 34.285247,  Lng: -98.871228),  Route carried "on" structure: State highway 54,  Year Built: 1948,  Year Reconstructed: 1962,  Status: Open,  Structure Length: 0.67m (2.20ft),  Average Daily Traffic: 170 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 272 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.233,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 11.6m (38.1ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 49.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 29.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present desirable criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.67m (2.20ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 10829,  Location: 4.02 E JCT US-271 (Lat: 34.482542,  Lng: -95.218322),  Route carried "on" structure: State highway 144,  Year Built: 1948,  Status: Open,  Structure Length: 0.82m (2.69ft),  Average Daily Traffic: 310 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 496 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 6.468,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 2.4m (7.9ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 90.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 66.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.79m (2.59ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2020,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Discuss Asher, Oklahoma (OK) on our hugely popular Oklahoma forum.