Jump to a detailed profile or search site with Google Custom Search

Bridge Statistics for Chesterfield, Missouri (MO)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 66Number of bridges
  • 863ft / 263mTotal length
  • $4,644,000Total costs
  • 1,379,544Total average daily traffic
  • 120,133Total average daily truck traffic
  • National Bridge Inventory (NBI) Registered Bridges for Chesterfield
  • No street view available for this location

New bridges in Chesterfield, MO - historical statistics
  • New bridges - historical statistics
  • 11940-1949
  • 141960-1969
  • 21970-1979
  • 71980-1989
  • 111990-1999
  • 52000-2009
  • 262010-2019
Reconstructed bridges in Chesterfield, MO - Historical Statistics
  • Reconstructed bridges - Historical Statistics
  • 31980-1989
  • 01990-1999
  • 12000-2009
  • 12010-2019
Average Bridge Daily Traffic in Chesterfield, MO
Average Bridge Truck Traffic in Chesterfield, MO
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 9.4%Very good
  • 53.1%Good
  • 28.1%Satisfactory
  • 6.3%Fair
  • 3.1%Poor
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 3.1%Excellent
  • 18.8%Very good
  • 43.8%Good
  • 28.1%Satisfactory
  • 3.1%Fair
  • 3.1%Poor
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 3.1%Excellent
  • 6.3%Very good
  • 56.3%Good
  • 31.3%Satisfactory
  • 3.1%Fair
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 8.8%Very good
  • 32.4%Good
  • 50.0%Satisfactory
  • 8.8%Fair
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 46.2%Good
  • 30.8%Satisfactory
  • 23.1%Fair
Find on map >>   Show street view

Structure Number: 3907,  Location: S 13 T 45 N R 4 E (Lat: 38.645878,  Lng: -90.527372),  Route carried "on" structure: ServiceState highway 64,  Year Built: 1990,  Status: Open,  Structure Length: 5.49m (18.01ft),  Average Daily Traffic: 5,122 (year 2021),  Truck Traffic: 3%,  Average Future Daily Traffic: 7,683 (year 2041),  Design Load: HS 20+Mod,  Features Intersected: CREVE COEUR CR
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 2.097,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Skew: 4 degrees,  Material/Design: Prestressed concrete continuous,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 11.3m (37.1ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 10.6m (34.8ft),  Out-to-Out Width: 11.4m (37.4ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 49.5 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 38.7 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 606,  Location: S 297 T 46 N R 2 E (Lat: 38.745253,  Lng: -90.762069),  Route carried "on" structure: State highway DD,  Year Built: 1943,  Status: Open,  Structure Length: 1.00m (3.28ft),  Average Daily Traffic: 8,840 (year 2021),  Truck Traffic: 10%,  Average Future Daily Traffic: 17,238 (year 2041),  Design Load: H 15,  Features Intersected: BALL RIDGE BR
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.964,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 4 degrees,  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.7m (12.1ft),  Curb-To-Curb Width: 8.7m (28.5ft),  Out-to-Out Width: 9.1m (29.9ft)

Condition: Channel: Fair,  Culverts: Good,  Operating Rating: 93.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 56.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 0.17m (0.56ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021,  Bridge Improvement Cost: $170,000,  Roadway Improvement Cost: $17,000,  Total Project Cost: $255,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 7435,  Location: S 12 T 49 N R 16 W (Lat: 39.050500,  Lng: -92.674975),  Route carried "on" structure: State highway P,  Year Built: 1961,  Year Reconstructed: 2009,  Status: Open,  Structure Length: 4.54m (14.90ft),  Average Daily Traffic: 177 (year 2021),  Truck Traffic: 10%,  Average Future Daily Traffic: 221 (year 2041),  Design Load: H 15,  Features Intersected: SALT CR
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 7.593,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 15.3m (50.2ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 7.5m (24.6ft)

Condition: Deck: Very good,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 56.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 34.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 11831,  Location: S 125 T 45 N R 4 E (Lat: 38.670569,  Lng: -90.599650),  Route carried "under" structure: Interstate 64,  Year Built: 1999,  Structure Length: 0. m,  Average Daily Traffic: 43,820 (year 2021),  Truck Traffic: 11%,  Features Intersected: IS 64,  Facility Carried by Structure: BOONES CROSSING RD
Minimum Vertical Clearance: 5.36m (17.59ft),  Kilometerpoint: 27.600,  Lanes on structure: 7,  Lanes under structure: 3,  Material/Design: Prestressed concrete continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 20.4m (66.9ft)

Find on map >>   Show street view

Structure Number: 11831,  Location: S 125 T 45 N R 4 E (Lat: 38.670569,  Lng: -90.599650),  Route carried "under" structure: Interstate 64,  Year Built: 1999,  Structure Length: 0. m,  Average Daily Traffic: 48,507 (year 2021),  Truck Traffic: 8%,  Features Intersected: IS 64,  Facility Carried by Structure: BOONES CROSSING RD
Minimum Vertical Clearance: 5.44m (17.85ft),  Kilometerpoint: 38.098,  Lanes on structure: 7,  Lanes under structure: 3,  Material/Design: Prestressed concrete continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 20.4m (66.9ft)

Find on map >>   Show street view

Structure Number: 1372,  Location: S 415 T 45 N R 4 E (Lat: 38.652958,  Lng: -90.558458),  Route carried "under" structure: State highway 340,  Year Built: 1968,  Structure Length: 0. m,  Average Daily Traffic: 14,674 (year 2021),  Truck Traffic: 5%,  Features Intersected: MO 340,  Facility Carried by Structure: IS 64 E
Minimum Vertical Clearance: 4.83m (15.85ft),  Kilometerpoint: 7.389,  Lanes on structure: 3,  Lanes under structure: 4,  Material/Design: Concrete continuous,  Design/Construction: Slab,  Length of Maximum Span: 21.3m (69.9ft)

Find on map >>   Show street view

Structure Number: 1372,  Location: S 415 T 45 N R 4 E (Lat: 38.652958,  Lng: -90.558458),  Route carried "under" structure: State highway 340,  Year Built: 1968,  Structure Length: 0. m,  Average Daily Traffic: 9,657 (year 2021),  Truck Traffic: 5%,  Features Intersected: MO 340,  Facility Carried by Structure: IS 64 E
Minimum Vertical Clearance: 4.83m (15.85ft),  Kilometerpoint: 23.632,  Lanes on structure: 3,  Lanes under structure: 2,  Material/Design: Concrete continuous,  Design/Construction: Slab,  Length of Maximum Span: 21.3m (69.9ft)

Find on map >>   Show street view

Structure Number: 1373,  Location: S 415 T 45 N R 4 E (Lat: 38.653053,  Lng: -90.558331),  Route carried "under" structure: State highway 340,  Year Built: 1968,  Structure Length: 0. m,  Average Daily Traffic: 9,171 (year 2021),  Truck Traffic: 5%,  Features Intersected: MO 340,  Facility Carried by Structure: IS 64 W
Minimum Vertical Clearance: 4.83m (15.85ft),  Kilometerpoint: 7.405,  Lanes on structure: 3,  Lanes under structure: 2,  Material/Design: Concrete continuous,  Design/Construction: Slab,  Length of Maximum Span: 21.3m (69.9ft)

Find on map >>   Show street view

Structure Number: 1373,  Location: S 415 T 45 N R 4 E (Lat: 38.653053,  Lng: -90.558331),  Route carried "under" structure: State highway 340,  Year Built: 1968,  Structure Length: 0. m,  Average Daily Traffic: 9,657 (year 2021),  Truck Traffic: 5%,  Features Intersected: MO 340,  Facility Carried by Structure: IS 64 W
Minimum Vertical Clearance: 4.83m (15.85ft),  Kilometerpoint: 23.617,  Lanes on structure: 3,  Lanes under structure: 4,  Material/Design: Concrete continuous,  Design/Construction: Slab,  Length of Maximum Span: 21.3m (69.9ft)

Find on map >>   Show street view

Structure Number: 1852,  Location: S 371 T 45 N R 3 E (Lat: 38.674539,  Lng: -90.645581),  Route carried "under" structure: Interstate 64,  Year Built: 1968,  Structure Length: 0. m,  Average Daily Traffic: 43,658 (year 2021),  Truck Traffic: 11%,  Features Intersected: IS 64,  Facility Carried by Structure: SPIRIT OF ST LOUIS
Minimum Vertical Clearance: 5.03m (16.50ft),  Kilometerpoint: 23.579,  Lanes on structure: 3,  Lanes under structure: 3,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 26.2m (86.0ft)

Find on map >>   Show street view

Structure Number: 1852,  Location: S 371 T 45 N R 3 E (Lat: 38.674539,  Lng: -90.645581),  Route carried "under" structure: Interstate 64,  Year Built: 1968,  Structure Length: 0. m,  Average Daily Traffic: 43,700 (year 2021),  Truck Traffic: 8%,  Features Intersected: IS 64,  Facility Carried by Structure: SPIRIT OF ST LOUIS
Minimum Vertical Clearance: 5.03m (16.50ft),  Kilometerpoint: 42.120,  Lanes on structure: 3,  Lanes under structure: 3,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 26.2m (86.0ft)

Find on map >>   Show street view

Structure Number: 1853,  Location: S 126 T 45 N R 4 E (Lat: 38.671956,  Lng: -90.616992),  Route carried "under" structure: Interstate 64,  Year Built: 1968,  Structure Length: 0. m,  Average Daily Traffic: 43,658 (year 2021),  Truck Traffic: 11%,  Features Intersected: IS 64
Minimum Vertical Clearance: 4.65m (15.26ft),  Kilometerpoint: 26.078,  Lanes on structure: 1,  Lanes under structure: 3,  Material/Design: Concrete continuous,  Design/Construction: Box Beam or Girders - Single/Spread,  Length of Maximum Span: 28.3m (92.8ft)

Find on map >>   Show street view

Structure Number: 1853,  Location: S 126 T 45 N R 4 E (Lat: 38.671956,  Lng: -90.616992),  Route carried "under" structure: Interstate 64,  Year Built: 1968,  Structure Length: 0. m,  Average Daily Traffic: 48,507 (year 2021),  Truck Traffic: 8%,  Features Intersected: IS 64
Minimum Vertical Clearance: 4.60m (15.09ft),  Kilometerpoint: 39.609,  Lanes on structure: 1,  Lanes under structure: 3,  Material/Design: Concrete continuous,  Design/Construction: Box Beam or Girders - Single/Spread,  Length of Maximum Span: 28.3m (92.8ft)

Find on map >>   Show street view

Structure Number: 32944,  Location: S 109 T 45 N R 5 E (Lat: 38.660556,  Lng: -90.504722),  Route carried "under" structure: City street ,  Year Built: 2012,  Structure Length: 0. m,  Average Daily Traffic: 6,171 (year 2021),  Truck Traffic: 4%,  Features Intersected: CST N WOODS MILL RD,  Facility Carried by Structure: RT AB E
Minimum Vertical Clearance: 4.90m (16.08ft),  Kilometerpoint: 2.250,  Lanes on structure: 6,  Lanes under structure: 2,  Material/Design: Prestressed concrete,  Design/Construction: Tee Beam,  Length of Maximum Span: 38.1m (125.0ft)

Find on map >>   Show street view

Structure Number: 32973,  Location: S 367 T 46 N R 5 E (Lat: 38.681358,  Lng: -90.493358),  Route carried "under" structure: State highway 141,  Year Built: 2011,  Structure Length: 0. m,  Average Daily Traffic: 17,817 (year 2021),  Truck Traffic: 5%,  Features Intersected: MO 141,  Facility Carried by Structure: MO 340 E
Minimum Vertical Clearance: 5.49m (18.01ft),  Kilometerpoint: 14.895,  Lanes on structure: 8,  Lanes under structure: 2,  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 28.7m (94.2ft)

Find on map >>   Show street view

Structure Number: 32973,  Location: S 367 T 46 N R 5 E (Lat: 38.681358,  Lng: -90.493358),  Route carried "under" structure: State highway 141,  Year Built: 2011,  Structure Length: 0. m,  Average Daily Traffic: 6,126 (year 2021),  Truck Traffic: 5%,  Features Intersected: MO 141,  Facility Carried by Structure: MO 340 E
Minimum Vertical Clearance: 5.18m (16.99ft),  Kilometerpoint: 34.773,  Lanes on structure: 8,  Lanes under structure: 2,  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 28.7m (94.2ft)

Find on map >>   Show street view

Structure Number: 3449,  Location: S 371 T 45 N R 3 E (Lat: 38.676389,  Lng: -90.656389),  Route carried "under" structure: Interstate 64,  Year Built: 2013,  Structure Length: 0. m,  Average Daily Traffic: 43,658 (year 2021),  Truck Traffic: 11%,  Features Intersected: IS 64,  Facility Carried by Structure: RP CHESTERFIELD AI
Minimum Vertical Clearance: 5.77m (18.93ft),  Kilometerpoint: 22.600,  Lanes on structure: 1,  Lanes under structure: 3,  Material/Design: Prestressed concrete continuous,  Design/Construction: Tee Beam,  Length of Maximum Span: 26.8m (87.9ft)

Find on map >>   Show street view

Structure Number: 3449,  Location: S 371 T 45 N R 3 E (Lat: 38.676389,  Lng: -90.656389),  Route carried "under" structure: Interstate 64,  Year Built: 2013,  Structure Length: 0. m,  Average Daily Traffic: 43,700 (year 2021),  Truck Traffic: 8%,  Features Intersected: IS 64,  Facility Carried by Structure: RP CHESTERFIELD AI
Minimum Vertical Clearance: 5.72m (18.77ft),  Kilometerpoint: 43.097,  Lanes on structure: 1,  Lanes under structure: 3,  Material/Design: Prestressed concrete continuous,  Design/Construction: Tee Beam,  Length of Maximum Span: 26.8m (87.9ft)

Find on map >>   Show street view

Structure Number: 34573,  Location: S 123 T 45 N R 4 E (Lat: 38.658942,  Lng: -90.566889),  Route carried "under" structure: Interstate 64,  Year Built: 2013,  Structure Length: 0. m,  Average Daily Traffic: 43,820 (year 2021),  Truck Traffic: 11%,  Features Intersected: IS 64,  Facility Carried by Structure: CHESTERFIELD PKWY
Minimum Vertical Clearance: 5.27m (17.29ft),  Kilometerpoint: 30.933,  Lanes on structure: 7,  Lanes under structure: 3,  Material/Design: Prestressed concrete continuous,  Design/Construction: Tee Beam,  Length of Maximum Span: 23.2m (76.1ft)

Find on map >>   Show street view

Structure Number: 34573,  Location: S 123 T 45 N R 4 E (Lat: 38.658942,  Lng: -90.566889),  Route carried "under" structure: Interstate 64,  Year Built: 2013,  Structure Length: 0. m,  Average Daily Traffic: 48,507 (year 2021),  Truck Traffic: 8%,  Features Intersected: IS 64,  Facility Carried by Structure: CHESTERFIELD PKWY
Minimum Vertical Clearance: 6.25m (20.51ft),  Kilometerpoint: 34.754,  Lanes on structure: 7,  Lanes under structure: 3,  Material/Design: Prestressed concrete continuous,  Design/Construction: Tee Beam,  Length of Maximum Span: 23.2m (76.1ft)

Find on map >>   Show street view

Structure Number: 3842,  Location: S 10 T 45 N R 4 E (Lat: 38.650703,  Lng: -90.550292),  Route carried "under" structure: Interstate 64,  Year Built: 1990,  Structure Length: 0. m,  Average Daily Traffic: 63,620 (year 2021),  Truck Traffic: 8%,  Features Intersected: IS 64,  Facility Carried by Structure: CHESTERFIELD PKWY
Minimum Vertical Clearance: 5.00m (16.40ft),  Kilometerpoint: 32.993,  Lanes on structure: 6,  Lanes under structure: 4,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 34.1m (111.9ft)

Find on map >>   Show street view

Structure Number: 3842,  Location: S 10 T 45 N R 4 E (Lat: 38.650703,  Lng: -90.550292),  Route carried "under" structure: Interstate 64,  Year Built: 1990,  Structure Length: 0. m,  Average Daily Traffic: 63,579 (year 2021),  Truck Traffic: 11%,  Features Intersected: IS 64,  Facility Carried by Structure: CHESTERFIELD PKWY
Minimum Vertical Clearance: 4.98m (16.34ft),  Kilometerpoint: 32.695,  Lanes on structure: 6,  Lanes under structure: 4,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 34.1m (111.9ft)

Find on map >>   Show street view

Structure Number: 3843,  Location: S 11 T 45 N R 4 E (Lat: 38.646722,  Lng: -90.530339),  Route carried "under" structure: Interstate 64,  Year Built: 1990,  Structure Length: 0. m,  Average Daily Traffic: 63,579 (year 2021),  Truck Traffic: 11%,  Features Intersected: IS 64,  Facility Carried by Structure: TIMBERLAKE MANOR D
Minimum Vertical Clearance: 5.16m (16.93ft),  Kilometerpoint: 34.490,  Lanes on structure: 6,  Lanes under structure: 3,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 29.6m (97.1ft)

Find on map >>   Show street view

Structure Number: 3843,  Location: S 11 T 45 N R 4 E (Lat: 38.646722,  Lng: -90.530339),  Route carried "under" structure: Interstate 64,  Year Built: 1990,  Structure Length: 0. m,  Average Daily Traffic: 63,620 (year 2021),  Truck Traffic: 8%,  Features Intersected: IS 64,  Facility Carried by Structure: TIMBERLAKE MANOR D
Minimum Vertical Clearance: 5.11m (16.77ft),  Kilometerpoint: 31.202,  Lanes on structure: 6,  Lanes under structure: 3,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 29.6m (97.1ft)