Bridge Statistics for Dothan, Alabama (AL)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 97Number of bridges
  • 807ft / 246mTotal length
  • $108,836,000Total costs
  • 609,951Total average daily traffic
  • 46,663Total average daily truck traffic
  • National Bridge Inventory (NBI) Registered Bridges for Dothan
  • No street view available for this location

New bridges in Dothan, AL - historical statistics
  • New bridges - historical statistics
  • 61920-1929
  • 51930-1939
  • 11940-1949
  • 151950-1959
  • 171960-1969
  • 201970-1979
  • 91980-1989
  • 71990-1999
  • 132000-2009
  • 42010-2019
Reconstructed bridges in Dothan, AL - Historical Statistics
  • Reconstructed bridges - Historical Statistics
  • 11960-1969
  • 21970-1979
  • 11980-1989
  • 01990-1999
  • 12000-2009
  • 22010-2019
Average Bridge Daily Traffic in Dothan, AL
Average Bridge Truck Traffic in Dothan, AL
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 17.0%Excellent
  • 12.8%Very good
  • 19.1%Good
  • 21.3%Satisfactory
  • 29.8%Fair
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 19.1%Excellent
  • 12.8%Very good
  • 14.9%Good
  • 36.2%Satisfactory
  • 17.0%Fair
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 17.0%Excellent
  • 12.8%Very good
  • 23.4%Good
  • 29.8%Satisfactory
  • 17.0%Fair
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 6.3%Excellent
  • 10.0%Very good
  • 31.3%Good
  • 38.8%Satisfactory
  • 13.8%Fair
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 2.2%Excellent
  • 2.2%Very good
  • 30.4%Good
  • 41.3%Satisfactory
  • 23.9%Fair
Find on map >>   Show street view

Structure Number: 1998,  Location: DOTHAN (Lat: 31.245000,  Lng: -85.420000),  Route carried "on" structure: City street ,  Year Built: 2008,  Status: Open,  Structure Length: 0.72m (2.36ft),  Average Daily Traffic: 640 (year 1999),  Truck Traffic: 1%,  Average Future Daily Traffic: 989 (year 2040),  Design Load: HS 20,  Features Intersected: STREAM,  Facility Carried by Structure: N. ENGLEWOOD AVE.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.009,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 8.2m (26.9ft),  Out-to-Out Width: 10.6m (34.8ft)

Condition: Channel: Very good,  Culverts: Very good,  Operating Rating: 88.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 66.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.35m (4.43ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Bridge Improvement Cost: $305,000,  Roadway Improvement Cost: $31,000,  Total Project Cost: $336,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 19981,  Location: DOTHAN (Lat: 31.220900,  Lng: -85.409000),  Route carried "on" structure: City street ,  Year Built: 2007,  Status: Open,  Structure Length: 0.73m (2.40ft),  Average Daily Traffic: 9,030 (year 1999),  Average Future Daily Traffic: 9,500 (year 2040),  Design Load: HS 20,  Features Intersected: FOLKES BRANCH,  Facility Carried by Structure: SOUTH PARK AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.780,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.5m (11.5ft),  Curb or Sidewalk Widths: Left: 0.6m (2.0ft),  Right: 0.6m (2.0ft),  Curb-To-Curb Width: 9.3m (30.5ft),  Out-to-Out Width: 12.5m (41.0ft)

Condition: Channel: Very good,  Culverts: Good,  Operating Rating: 55.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.37m (4.49ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2020,  Bridge Improvement Cost: $378,000,  Roadway Improvement Cost: $38,000,  Total Project Cost: $416,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 20003,  Location: .25 MI.S FLOWERS CHPL RD (Lat: 31.217533,  Lng: -85.486539),  Route carried "on" structure: State highway 605,  Year Built: 2008,  Status: Open,  Structure Length: 6.22m (20.41ft),  Average Daily Traffic: 10,260 (year 2013),  Truck Traffic: 3%,  Average Future Daily Traffic: 12,519 (year 2033),  Design Load: HS 20,  Features Intersected: BEAVER CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 27.005,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 19.5m (64.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 6,  Length of Maximum Span: 10.4m (34.1ft),  Curb-To-Curb Width: 19.5m (64.0ft),  Out-to-Out Width: 20.3m (66.6ft)

Condition: Deck: Excellent,  Superstructure: Excellent,  Substructure: Excellent,  Channel: Good,  Operating Rating: 71.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 42.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Superior to present desirable criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 7.26m (23.82ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2021,  Bridge Improvement Cost: $3,284,000,  Roadway Improvement Cost: $328,000,  Total Project Cost: $3,612,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 20209,  Location: DOTHAN (Lat: 31.250000,  Lng: -85.433333),  Route carried "on" structure: City street ,  Year Built: 2009,  Status: Open,  Structure Length: 3.11m (10.20ft),  Average Daily Traffic: 13,813 (year 2010),  Truck Traffic: 20%,  Average Future Daily Traffic: 21,272 (year 2040),  Design Load: HS 20,  Features Intersected: LITTLE CHOCTAWHATCHEE,  Facility Carried by Structure: DENTON RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.309,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Concrete,  Design/Construction: Channel Beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 10.4m (34.1ft),  Curb-To-Curb Width: 11.1m (36.4ft),  Out-to-Out Width: 11.5m (37.7ft)

Condition: Deck: Excellent,  Superstructure: Excellent,  Substructure: Excellent,  Channel: Excellent,  Operating Rating: 71.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 43.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Superior to present desirable criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Superior to present desirable criteria,  Length Of Structure Improvement: 3.96m (12.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2020,  Bridge Improvement Cost: $1,005,000,  Roadway Improvement Cost: $101,000,  Total Project Cost: $1,106,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels
Find on map >>   Show street view

Structure Number: 20224,  Location: CIRCLE TO PILGRAM REST CH (Lat: 31.211400,  Lng: -85.431200),  Route carried "on" structure: County highway 40,  Year Built: 2010,  Status: Open,  Structure Length: 1.38m (4.53ft),  Average Daily Traffic: 1,150 (year 2003),  Truck Traffic: 5%,  Average Future Daily Traffic: 1,799 (year 2040),  Design Load: HS 20,  Features Intersected: BEAVER CREEK,  Facility Carried by Structure: FORTNER SREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.966,  Lanes on structure: 3,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 4.3m (14.1ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 23.8m (78.1ft)

Condition: Channel: Very good,  Culverts: Excellent,  Operating Rating: 50.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 30.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Superior to present desirable criteria,  Length Of Structure Improvement: 2.06m (6.76ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Bridge Improvement Cost: $928,000,  Roadway Improvement Cost: $93,000,  Total Project Cost: $1,021,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 2026,  Location: US 231 S TO CO RD 203 (Lat: 31.159514,  Lng: -85.405450),  Route carried "on" structure: County highway ,  Year Built: 1960,  Status: Open,  Structure Length: 0.75m (2.46ft),  Average Daily Traffic: 1,654 (year 2009),  Truck Traffic: 3%,  Average Future Daily Traffic: 2,557 (year 2033),  Design Load: HS 20,  Features Intersected: SAUNDERS BRANCH,  Facility Carried by Structure: W. SAUNDERS RD.
Minimum Vertical Clearance: 0.00m,  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.7m (12.1ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 52.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 31.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.39m (4.56ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $273,000,  Roadway Improvement Cost: $27,000,  Total Project Cost: $300,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 20261,  Location: CO.RD.59 TO CAMPBELLTONH (Lat: 31.185375,  Lng: -85.418642),  Route carried "on" structure: County highway ,  Year Built: 1958,  Status: Open,  Structure Length: 0.62m (2.03ft),  Average Daily Traffic: 5,418 (year 2009),  Truck Traffic: 17%,  Average Future Daily Traffic: 9,026 (year 2033),  Design Load: HS 20,  Features Intersected: LIMESTONE CREEK,  Facility Carried by Structure: TAYLOR RD.
Minimum Vertical Clearance: 0.00m,  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.0m (23.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Good,  Culverts: Fair,  Operating Rating: 39.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 23.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.24m (4.07ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $215,000,  Roadway Improvement Cost: $22,000,  Total Project Cost: $237,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 20493,  Location: 6 MILE SOUTH DOTHAN CIRCL (Lat: 31.119467,  Lng: -85.328450),  Route carried "on" structure: State highway 53,  Year Built: 1940,  Status: Open,  Structure Length: 0.63m (2.07ft),  Average Daily Traffic: 3,550 (year 2013),  Truck Traffic: 8%,  Average Future Daily Traffic: 4,615 (year 2033),  Design Load: HS 20,  Features Intersected: BUCK CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 20.059,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 43.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 25.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.25m (4.10ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $375,000,  Roadway Improvement Cost: $38,000,  Total Project Cost: $413,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 20825,  Location: Denton rd (Lat: 31.261944,  Lng: -85.411944),  Route carried "on" structure: City street ,  Year Built: 2017,  Status: Open,  Structure Length: 2.44m (8.01ft),  Average Daily Traffic: 10,457 (year 2015),  Truck Traffic: 5%,  Average Future Daily Traffic: 15,538 (year 2041),  Design Load: HS 20,  Features Intersected: Rock creek,  Facility Carried by Structure: Denton rd
Minimum Vertical Clearance: 0.00m,  Kilometerpoint: 1.619,  Lanes on structure: 4,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 19.2m (63.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 12.2m (40.0ft),  Curb or Sidewalk Widths: Left: 2.1m (6.9ft),  Right: 2.1m (6.9ft),  Curb-To-Curb Width: 19.2m (63.0ft),  Out-to-Out Width: 19.2m (63.0ft)

Condition: Deck: Excellent,  Superstructure: Excellent,  Substructure: Excellent,  Channel: Excellent,  Operating Rating: 63.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 37.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Superior to present desirable criteria,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 3.31m (10.86ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $1,428,000,  Roadway Improvement Cost: $143,000,  Total Project Cost: $1,571,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete
Find on map >>   Show street view

Structure Number: 20976,  Location: CITY OF DOTHAN (Lat: 31.258100,  Lng: -85.449200),  Route carried "on" structure: City street ,  Year Built: 2019,  Status: Open,  Structure Length: 2.19m (7.19ft),  Average Daily Traffic: 700 (year 2003),  Truck Traffic: 1%,  Average Future Daily Traffic: 1,140 (year 2041),  Design Load: HS 20,  Features Intersected: QUAIL CREEK,  Facility Carried by Structure: BROOKSIDE DRIVE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.520,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Material/Design: Concrete,  Design/Construction: Channel Beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 7.3m (24.0ft),  Curb-To-Curb Width: 11.6m (38.1ft),  Out-to-Out Width: 12.3m (40.4ft)

Condition: Deck: Excellent,  Superstructure: Excellent,  Substructure: Excellent,  Channel: Excellent,  Operating Rating: 57.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 34.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Superior to present desirable criteria,  Deck Geometry: High priority of corrective action,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 3.00m (9.84ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $822,000,  Roadway Improvement Cost: $82,000,  Total Project Cost: $904,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 21505,  Location: _ (Lat: 31.264114,  Lng: -85.543867),  Route carried "on" structure: County highway 560,  Year Built: 2019,  Status: Open,  Structure Length: 3.29m (10.79ft),  Average Daily Traffic: 289 (year 2018),  Average Future Daily Traffic: 352 (year 2028),  Design Load: HS 20,  Features Intersected: DEAN CREEK
Minimum Vertical Clearance: 2.68m (8.79ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 9 degrees,  Material/Design: Concrete,  Design/Construction: Channel Beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 12.2m (40.0ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 8.7m (28.5ft)

Condition: Deck: Excellent,  Superstructure: Excellent,  Substructure: Excellent,  Channel: Excellent,  Operating Rating: 56.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Superior to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Superior to present desirable criteria,  Length Of Structure Improvement: 4.17m (13.68ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $800,000,  Roadway Improvement Cost: $80,000,  Total Project Cost: $880,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels
Find on map >>   Show street view

Structure Number: 6411,  Location: JCT. OF ALA.52 E (Lat: 31.222519,  Lng: -85.360553),  Route carried "under" structure: State highway 52,  Year Built: 1958,  Structure Length: 0. m,  Average Daily Traffic: 7,350 (year 2013),  Truck Traffic: 8%,  Features Intersected: SR 52,C. OF GA. R.R.,  Facility Carried by Structure: SR 210 MP 9.990
Minimum Vertical Clearance: 5.49m (18.01ft),  Kilometerpoint: 106.259,  Lanes on structure: 3,  Lanes under structure: 2,  Material/Design: Concrete continuous,  Design/Construction: Tee Beam,  Length of Maximum Span: 18.9m (62.0ft)

Find on map >>   Show street view

Structure Number: 6412,  Location: JCT. SR. 52 E. (Lat: 31.222508,  Lng: -85.360381),  Route carried "under" structure: State highway 52,  Year Built: 1958,  Structure Length: 0. m,  Average Daily Traffic: 7,350 (year 2013),  Truck Traffic: 8%,  Features Intersected: SR 52,C. OF GA. R.R.,  Facility Carried by Structure: SR 210 MP 9.990
Minimum Vertical Clearance: 5.49m (18.01ft),  Kilometerpoint: 106.259,  Lanes on structure: 2,  Lanes under structure: 2,  Material/Design: Concrete continuous,  Design/Construction: Tee Beam,  Length of Maximum Span: 18.9m (62.0ft)

Find on map >>   Show street view

Structure Number: 11197,  Location: 0.5 MI.E. U.S. 231 (Lat: 31.223067,  Lng: -85.383550),  Route carried "under" structure: Business City street ,  Year Built: 1974,  Structure Length: 0. m,  Average Daily Traffic: 460 (year 2013),  Truck Traffic: 1%,  Features Intersected: RANGE ST C/GA * BAYL R R,  Facility Carried by Structure: US 84 MP 210.502
Minimum Vertical Clearance: 7.06m (23.16ft),  Kilometerpoint: 339.770,  Lanes on structure: 3,  Lanes under structure: 2,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 24.7m (81.0ft)

Find on map >>   Show street view

Structure Number: 11198,  Location: 0.5 MI E. US 231 (Lat: 31.223033,  Lng: -85.383053),  Route carried "under" structure: Business City street ,  Year Built: 1974,  Structure Length: 0. m,  Average Daily Traffic: 460 (year 2013),  Truck Traffic: 1%,  Features Intersected: RANGE ST C/GA * BAYL R R,  Facility Carried by Structure: US 84 MP 210.502
Minimum Vertical Clearance: 7.06m (23.16ft),  Kilometerpoint: 3338.771,  Lanes on structure: 3,  Lanes under structure: 2,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 25.9m (85.0ft)