Jump to a detailed profile or search site with Google Custom Search

Bridge Statistics for Fort Carson, Colorado (CO)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 53Number of bridges
  • 440ft / 134mTotal length
  • $2,282,000Total costs
  • 330,951Total average daily traffic
  • 22,741Total average daily truck traffic
  • National Bridge Inventory (NBI) Registered Bridges for Fort Carson
  • No street view available for this location

New bridges in Fort Carson, CO - historical statistics
  • New bridges - historical statistics
  • 31940-1949
  • 21960-1969
  • 141970-1979
  • 71980-1989
  • 31990-1999
  • 142000-2009
  • 102010-2019
Reconstructed bridges in Fort Carson, CO - Historical Statistics
  • Reconstructed bridges - Historical Statistics
  • 11970-1979
  • 01980-1989
  • 01990-1999
  • 02000-2009
  • 12010-2019
Average Bridge Daily Traffic in Fort Carson, CO
Average Bridge Truck Traffic in Fort Carson, CO
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 15.8%Very good
  • 52.6%Good
  • 26.3%Satisfactory
  • 5.3%Fair
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 10.5%Very good
  • 57.9%Good
  • 21.1%Satisfactory
  • 5.3%Fair
  • 5.3%Poor
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 68.4%Good
  • 15.8%Satisfactory
  • 10.5%Fair
  • 5.3%Poor
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 2.9%Very good
  • 54.3%Good
  • 25.7%Satisfactory
  • 17.1%Fair
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 55.6%Good
  • 33.3%Satisfactory
  • 11.1%Fair
Find on map >>   Show street view

Structure Number: T85126,  Location: Prussman and Sheridan Ave (Lat: 38.735419,  Lng: -104.791900),  Route carried "on" structure: Other road ,  Year Built: 1992,  Status: Open,  Structure Length: 1.75m (5.74ft),  Average Daily Traffic: 400 (year 2021),  Truck Traffic: 10%,  Average Future Daily Traffic: 480 (year 2043),  Features Intersected: C Ditch,  Facility Carried by Structure: Prussman Blvd.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 3,  Owner: Army,  Approaching Roadway Width: 11.0m (36.1ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 3.0m (9.8ft),  Curb or Sidewalk Widths: Left: 1.7m (5.6ft),  Right: 2.8m (9.2ft),  Curb-To-Curb Width: 15.5m (50.9ft),  Out-to-Out Width: 20.2m (66.3ft)

Condition: Channel: Fair,  Culverts: Fair,  Operating Rating: 54.4 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.45m (8.04ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $14,000,  Roadway Improvement Cost: $10,000,  Total Project Cost: $24,000 ( Estimate for 2021)
Find on map >>   Show street view

Structure Number: T85127,  Location: Prussman and Barkeley Ave (Lat: 38.741219,  Lng: -104.782900),  Route carried "on" structure: Other road ,  Year Built: 1989,  Status: Open,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 500 (year 2015),  Truck Traffic: 10%,  Average Future Daily Traffic: 600 (year 2043),  Features Intersected: Clover Ditch,  Facility Carried by Structure: Prussman Blvd.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Army,  Approaching Roadway Width: 14.0m (45.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 2.2m (7.2ft),  Curb or Sidewalk Widths: Left: 1.7m (5.6ft),  Right: 2.2m (7.2ft),  Curb-To-Curb Width: 14.0m (45.9ft),  Out-to-Out Width: 20.1m (65.9ft)

Condition: Channel: Fair,  Culverts: Good,  Operating Rating: 54.4 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.66m (5.45ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2021)
Find on map >>   Show street view

Structure Number: T85131,  Location: 100 YD E INT W/BARKELEY (Lat: 38.725481,  Lng: -104.756700),  Route carried "on" structure: Other road ,  Year Built: 2008,  Status: Open,  Structure Length: 4.40m (14.44ft),  Average Daily Traffic: 1,000 (year 2015),  Truck Traffic: 10%,  Average Future Daily Traffic: 1,200 (year 2043),  Features Intersected: I Ditch,  Facility Carried by Structure: Specker Ave.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 4,  Owner: Army,  Approaching Roadway Width: 15.6m (51.2ft),  Skew: 3 degrees,  Material/Design: Prestressed concrete continuous,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 14.7m (48.2ft),  Curb or Sidewalk Widths: Left: 2.1m (6.9ft),  Right: 2.1m (6.9ft),  Curb-To-Curb Width: 15.9m (52.2ft),  Out-to-Out Width: 21.9m (71.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 68.0 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 40.8 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 5.38m (17.65ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2021),  Deck Structure Type: Other,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: T85133,  Location: .6 mi East of Specker Ave (Lat: 38.725769,  Lng: -104.746900),  Route carried "on" structure: Other road ,  Year Built: 1988,  Status: Open,  Structure Length: 1.09m (3.58ft),  Average Daily Traffic: 1,000 (year 2015),  Truck Traffic: 10%,  Average Future Daily Traffic: 480 (year 2043),  Features Intersected: Drainage Ditch,  Facility Carried by Structure: McGrath Ave.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 4,  Owner: Army,  Approaching Roadway Width: 14.6m (47.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 2.4m (7.9ft),  Curb-To-Curb Width: 22.2m (72.8ft),  Out-to-Out Width: 25.6m (84.0ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 54.4 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.76m (5.77ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2021)
Find on map >>   Show street view

Structure Number: T85139,  Location: 500 ft SE of Chiles Ave. (Lat: 38.763550,  Lng: -104.802600),  Route carried "on" structure: Other road ,  Year Built: 1942,  Status: Open,  Structure Length: 1.85m (6.07ft),  Average Daily Traffic: 30 (year 2015),  Average Future Daily Traffic: 30 (year 2043),  Features Intersected: B Ditch,  Facility Carried by Structure: Wickersham Blvd.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Army,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 4.6m (15.1ft),  Curb-To-Curb Width: 8.6m (28.2ft),  Out-to-Out Width: 9.5m (31.2ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Poor,  Channel: Fair,  Operating Rating: 34.0 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 26.2 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Meets minimum limits,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.59m (8.50ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2021),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: T8514,  Location: OConnell and Chiles Ave. (Lat: 38.748800,  Lng: -104.801300),  Route carried "on" structure: Other road ,  Year Built: 1988,  Status: Open,  Structure Length: 1.34m (4.40ft),  Average Daily Traffic: 600 (year 2015),  Truck Traffic: 10%,  Average Future Daily Traffic: 700 (year 2043),  Design Load: HS 20,  Features Intersected: I Ditch,  Facility Carried by Structure: OConnell Blvd.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Army,  Approaching Roadway Width: 11.0m (36.1ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 3.0m (9.8ft),  Curb or Sidewalk Widths: Left: 1.8m (5.9ft),  Right: 0.0m,  Curb-To-Curb Width: 16.1m (52.8ft),  Out-to-Out Width: 19.4m (63.6ft)

Condition: Channel: Very good,  Culverts: Satisfactory,  Operating Rating: 45.0 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 34.7 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.05m (6.73ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $1,000,  Roadway Improvement Cost: $1,000,  Total Project Cost: $2,000 ( Estimate for 2021)
Find on map >>   Show street view

Structure Number: EPC4099-00.33L,  Location: 1.5 MI W OF I-25 (Lat: 38.766000,  Lng: -104.804000),  Route carried "under" structure: County highway ,  Year Built: 2008,  Structure Length: 0. m,  Features Intersected: WESTMEADOW DRIVE,  Facility Carried by Structure: ACADEMY BLVD SB
Minimum Vertical Clearance: 5.55m (18.21ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 4,  Material/Design: Prestressed concrete continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 28.3m (92.8ft)

Find on map >>   Show street view

Structure Number: EPC4099-00.33R,  Location: 1.5 MI W. OF I25 (Lat: 38.765703,  Lng: -104.804003),  Route carried "under" structure: County highway ,  Year Built: 1979,  Structure Length: 0. m,  Average Daily Traffic: 5,000 (year 2008),  Features Intersected: WESTMEADOW DRIVE,  Facility Carried by Structure: ACADEMY BLVD NB
Minimum Vertical Clearance: 5.64m (18.50ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 4,  Material/Design: Prestressed concrete continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 28.2m (92.5ft)

Find on map >>   Show street view

Structure Number: EPC4099-00.67L,  Location: 1.2 MI W OF I-25 (Lat: 38.765917,  Lng: -104.798278),  Route carried "under" structure: County highway ,  Year Built: 2010,  Structure Length: 0. m,  Features Intersected: B ST, US ARMY RR,  Facility Carried by Structure: ACADEMY BLVD SB
Minimum Vertical Clearance: 7.16m (23.49ft),  Kilometerpoint: 0.000,  Lanes on structure: 3,  Lanes under structure: 4,  Material/Design: Prestressed concrete continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 34.5m (113.2ft)

Find on map >>   Show street view

Structure Number: EPC4099-00.67R,  Location: 1.2 MI W OF I25 (Lat: 38.765833,  Lng: -104.798333),  Route carried "under" structure: County highway ,  Year Built: 1978,  Structure Length: 0. m,  Average Daily Traffic: 10,000 (year 2008),  Features Intersected: B ST, US ARMY RR,  Facility Carried by Structure: NB ACADEMY BLVD
Minimum Vertical Clearance: 9.51m (31.20ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 4,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 38.4m (126.0ft)

Find on map >>   Show street view

Structure Number: I-17-GR,  Location: S. INT. OF ACADEMY & (Lat: 38.764603,  Lng: -104.775556),  Route carried "under" structure: City street ,  Year Built: 1971,  Structure Length: 0. m,  Average Daily Traffic: 36,400 (year 2005),  Truck Traffic: 9%,  Features Intersected: ACADEMY BLVD,  Facility Carried by Structure: I 25 ML SBND
Minimum Vertical Clearance: 6.40m (21.00ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 7,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 45.9m (150.6ft)

Find on map >>   Show street view

Structure Number: J-17-D,  Location: 1.1 MI S/SH 83 ACADMY BLV (Lat: 38.749389,  Lng: -104.811428),  Route carried "under" structure: State highway 115A,  Year Built: 1964,  Structure Length: 0. m,  Average Daily Traffic: 2,600 (year 2018),  Truck Traffic: 5%,  Features Intersected: SH 115 ML,  Facility Carried by Structure: FORT CARSON+NORAD
Minimum Vertical Clearance: 5.06m (16.60ft),  Kilometerpoint: 0.251,  Lanes on structure: 3,  Lanes under structure: 6,  Material/Design: Concrete continuous,  Design/Construction: Tee Beam,  Length of Maximum Span: 19.0m (62.3ft)

Find on map >>   Show street view

Structure Number: J-18-BM,  Location: SECURITY JCT I-25 A (Lat: 38.724689,  Lng: -104.733189),  Route carried "under" structure: Interstate 25A,  Year Built: 2009,  Structure Length: 0. m,  Average Daily Traffic: 39,000 (year 2011),  Truck Traffic: 11%,  Features Intersected: I 25 ML,  Facility Carried by Structure: SH 16A ML
Minimum Vertical Clearance: 5.33m (17.49ft),  Kilometerpoint: 211.809,  Lanes on structure: 7,  Lanes under structure: 5,  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 33.2m (108.9ft)

Discuss Fort Carson, Colorado (CO) on our hugely popular Colorado forum.


City-data.com does not guarantee the accuracy or timeliness of any information on this site.  Use at your own risk.
Some parts © 2024 Advameg, Inc.