  • National Bridge Inventory (NBI) Statistics
  • 65Number of bridges
  • 489ft / 149mTotal length
  • $103,832,000Total costs
  • 561,829Total average daily traffic
  • 103,645Total average daily truck traffic
  • National Bridge Inventory (NBI) Registered Bridges for Lee
  • No street view available for this location

New bridges in Lee, MA - historical statistics
  • New bridges - historical statistics
  • 1Before 1900
  • 11900-1909
  • 11910-1919
  • 11920-1929
  • 91930-1939
  • 11940-1949
  • 431950-1959
  • 31970-1979
  • 11980-1989
  • 11990-1999
  • 12000-2009
  • 12010-2019
  • 12020-2022
Reconstructed bridges in Lee, MA - Historical Statistics
  • Reconstructed bridges - Historical Statistics
  • 11920-1929
  • 11930-1939
  • 01940-1949
  • 11950-1959
  • 11960-1969
  • 01970-1979
  • 171980-1989
  • 51990-1999
  • 02000-2009
  • 12010-2019
Average Bridge Daily Traffic in Lee, MA
Average Bridge Truck Traffic in Lee, MA
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 2.4%Excellent
  • 4.9%Very good
  • 56.1%Good
  • 22.0%Satisfactory
  • 12.2%Fair
  • 2.4%Serious
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 2.4%Excellent
  • 7.3%Very good
  • 26.8%Good
  • 36.6%Satisfactory
  • 17.1%Fair
  • 9.8%Poor
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 2.4%Excellent
  • 2.4%Very good
  • 43.9%Good
  • 34.1%Satisfactory
  • 17.1%Fair
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 3.8%Excellent
  • 7.7%Very good
  • 42.3%Good
  • 26.9%Satisfactory
  • 11.5%Fair
  • 3.8%Poor
  • 3.8%Serious
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 33.3%Good
  • 66.7%Satisfactory
Find on map >>   Show street view

Structure Number: G1103104QDEMNBI,  Location: 500' SOUTH OF LEE T.L. (Lat: 42.256431,  Lng: -73.285825),  Route carried "on" structure: City street ,  Year Built: 1925,  Year Reconstructed: 1960,  Status: Open,  Structure Length: 0.76m (2.49ft),  Average Daily Traffic: 300 (year 2012),  Truck Traffic: 6%,  Average Future Daily Traffic: 158 (year 2031),  Features Intersected: WATER WEST BROOK,  Facility Carried by Structure: HWY BEARTOWN MTN
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: State Park, Forest, or Reservation Agency,  Approaching Roadway Width: 5.2m (17.1ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.2m (20.3ft),  Curb-To-Curb Width: 5.5m (18.0ft),  Out-to-Out Width: 5.5m (18.0ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Good,  Operating Rating: 76.2 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 54.1 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 0.80m (2.62ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $173,000,  Roadway Improvement Cost: $18,000,  Total Project Cost: $260,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: L050010DKDOT634,  Location: 1.2 MI S JCT US20 73.85 (Lat: 42.282908,  Lng: -73.249375),  Route carried "on" structure: State highway 102,  Year Built: 1905,  Year Reconstructed: 1958,  Status: Open,  Structure Length: 1.42m (4.66ft),  Average Daily Traffic: 7,512 (year 2017),  Truck Traffic: 6%,  Average Future Daily Traffic: 10,581 (year 2032),  Design Load: H 20,  Features Intersected: RR HRR
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 18.016,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 13.4m (44.0ft),  Skew: 3 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 12.4m (40.7ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 15.2m (49.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 43.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 25.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.50m (4.92ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021,  Bridge Improvement Cost: $896,000,  Roadway Improvement Cost: $90,000,  Total Project Cost: $1,345,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>   Show street view

Structure Number: L05002057MUNNBI,  Location: AT ROUTE 102 INT. (Lat: 42.276206,  Lng: -73.285122),  Route carried "on" structure: City street ,  Year Built: 1951,  Status: Open,  Structure Length: 3.81m (12.50ft),  Average Daily Traffic: 300 (year 2021),  Truck Traffic: 50%,  Average Future Daily Traffic: 411 (year 2031),  Design Load: H 20,  Features Intersected: WATER HOUSATONIC RIVER,  Facility Carried by Structure: HWY WILLOW ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 37.4m (122.7ft),  Curb or Sidewalk Widths: Left: 0.0m,  Right: 0.4m (1.3ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 9.1m (29.9ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 40.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 24.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 3.90m (12.80ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Critical Feature Inspection Date: July 2021,  Bridge Improvement Cost: $1,395,000,  Roadway Improvement Cost: $140,000,  Total Project Cost: $2,093,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>   Show street view

Structure Number: L05003058MUNNBI,  Location: AT RTE 102 INTERSECTION (Lat: 42.278081,  Lng: -73.275200),  Route carried "on" structure: City street ,  Year Built: 1954,  Status: Posted for load,  Structure Length: 3.82m (12.53ft),  Average Daily Traffic: 5,200 (year 2021),  Truck Traffic: 6%,  Average Future Daily Traffic: 7,896 (year 2031),  Design Load: H 20,  Features Intersected: WATER HOUSATONIC RIVER,  Facility Carried by Structure: HWY MEADOW ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.023,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 37.4m (122.7ft),  Curb or Sidewalk Widths: Left: 0.0m,  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 9.1m (29.9ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 35.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 21.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Meets minimum limits,  Length Of Structure Improvement: 3.90m (12.80ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 36 months,  Inspection Date: July 2021,  Critical Feature Inspection Date: July 2021,  Underwater Inspection Date: September 2020,  Bridge Improvement Cost: $1,395,000,  Roadway Improvement Cost: $140,000,  Total Project Cost: $2,093,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>   Show street view

Structure Number: L05004059MUNNBI,  Location: .5 MI SOUTH OF RTE 102 (Lat: 42.273175,  Lng: -73.269419),  Route carried "on" structure: City street ,  Year Built: 1939,  Status: Temporarily open,  Structure Length: 1.22m (4.00ft),  Average Daily Traffic: 647 (year 2018),  Truck Traffic: 5%,  Average Future Daily Traffic: 474 (year 2033),  Design Load: H 15,  Features Intersected: WATER POWDER MILL BROOK,  Facility Carried by Structure: HWY MEADOW ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 4.2m (13.8ft),  Skew: 3 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 10.4m (34.1ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 6.0m (19.7ft),  Out-to-Out Width: 7.3m (24.0ft)

Condition: Deck: Serious,  Superstructure: Poor,  Substructure: Satisfactory,  Channel: Poor,  Structural Evaluation: High priority of replacement,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 1.90m (6.23ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2021,  Bridge Improvement Cost: $1,344,000,  Roadway Improvement Cost: $135,000,  Total Project Cost: $2,017,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: L05006016MUNNBI,  Location: JUST S OF RTE 102 (Lat: 42.294767,  Lng: -73.238956),  Route carried "on" structure: City street ,  Year Built: 1938,  Year Reconstructed: 1995,  Status: Open,  Structure Length: 1.84m (6.04ft),  Average Daily Traffic: 1,400 (year 2014),  Truck Traffic: 6%,  Average Future Daily Traffic: 2,211 (year 2031),  Design Load: HS 20,  Features Intersected: WATER GOOSE POND BROOK,  Facility Carried by Structure: HWY TYRINGHAM RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Skew: 4 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 8.4m (27.6ft),  Curb or Sidewalk Widths: Left: 0.1m (0.3ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 10.4m (34.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 94.9 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 52.9 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.90m (6.23ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2021,  Bridge Improvement Cost: $986,000,  Roadway Improvement Cost: $99,000,  Total Project Cost: $1,480,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: L0500705AMUNNBI,  Location: 300' S OF INT WITH RT 20 (Lat: 42.294292,  Lng: -73.226053),  Route carried "on" structure: City street ,  Year Built: 1970,  Status: Open,  Structure Length: 1.31m (4.30ft),  Average Daily Traffic: 2,198 (year 2018),  Truck Traffic: 6%,  Average Future Daily Traffic: 158 (year 2033),  Design Load: H 20,  Features Intersected: WATER GREENWATER BROOK,  Facility Carried by Structure: HWY FOREST ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Prestressed concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 12.6m (41.3ft),  Curb or Sidewalk Widths: Left: 1.9m (6.2ft),  Right: 0.5m (1.6ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 12.3m (40.4ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 46.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 26.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.40m (4.59ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2022,  Bridge Improvement Cost: $677,000,  Roadway Improvement Cost: $68,000,  Total Project Cost: $1,016,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: L0500805BMUNNBI,  Location: AT JCT W/ ROUTE 20 (Lat: 42.298828,  Lng: -73.221000),  Route carried "on" structure: City street ,  Year Built: 1939,  Status: Posted for load,  Structure Length: 1.22m (4.00ft),  Average Daily Traffic: 240 (year 2015),  Truck Traffic: 6%,  Average Future Daily Traffic: 158 (year 2032),  Design Load: H 15,  Features Intersected: WATER GREENWATER BROOK,  Facility Carried by Structure: HWY SILVER ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 10.7m (35.1ft),  Curb or Sidewalk Widths: Left: 0.1m (0.3ft),  Right: 0.1m (0.3ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 9.1m (29.9ft)

Condition: Deck: Fair,  Superstructure: Poor,  Substructure: Satisfactory,  Channel: Fair,  Operating Rating: 29.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 17.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 0.1 - 9.9% below),  Length Of Structure Improvement: 1.90m (6.23ft),  Designated Inspection Frequency: Every 12 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: August 2021,  Other Special Inspection Date: August 2021,  Bridge Improvement Cost: $1,215,000,  Roadway Improvement Cost: $122,000,  Total Project Cost: $1,823,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: L05010014MUNNBI,  Location: JUST W OF RTE 20 (Lat: 42.303786,  Lng: -73.251100),  Route carried "on" structure: City street ,  Year Built: 1890,  Year Reconstructed: 1932,  Status: Open,  Structure Length: 3.81m (12.50ft),  Average Daily Traffic: 6,200 (year 2014),  Truck Traffic: 4%,  Average Future Daily Traffic: 10,265 (year 2031),  Features Intersected: WATER HOUSATONIC RIVER,  Facility Carried by Structure: HWY W PARK ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 18.7m (61.4ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 13.2m (43.3ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 76.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 45.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 3.90m (12.80ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $2,023,000,  Roadway Improvement Cost: $203,000,  Total Project Cost: $3,035,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>   Show street view

Structure Number: L050110AYDOTNBI,  Location: AT SUMMER ST INTERSECTION (Lat: 42.310625,  Lng: -73.254756),  Route carried "on" structure: US 20,  Year Built: 1985,  Status: Open,  Structure Length: 4.27m (14.01ft),  Average Daily Traffic: 12,893 (year 2014),  Truck Traffic: 9%,  Average Future Daily Traffic: 18,794 (year 2031),  Design Load: HS 20,  Features Intersected: WATER HOUSATONIC RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 28.029,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Skew: 2 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 42.1m (138.1ft),  Curb or Sidewalk Widths: Left: 1.8m (5.9ft),  Right: 1.8m (5.9ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 16.7m (54.8ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 63.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 38.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 4.30m (14.11ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2020,  Bridge Improvement Cost: $487,000,  Roadway Improvement Cost: $49,000,  Total Project Cost: $731,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>   Show street view

Structure Number: L05013015MUNNBI,  Location: .2 MI S OF LENOX TL (Lat: 42.327847,  Lng: -73.241892),  Route carried "on" structure: City street ,  Year Built: 1911,  Year Reconstructed: 1937,  Status: Temporarily open,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 2,172 (year 2018),  Truck Traffic: 6%,  Average Future Daily Traffic: 1,421 (year 2031),  Features Intersected: WATER WASHNGTN MTN BROOK,  Facility Carried by Structure: HWY MILL ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.5m (27.9ft),  Curb-To-Curb Width: 8.1m (26.6ft),  Out-to-Out Width: 9.1m (29.9ft)

Condition: Deck: Fair,  Superstructure: Poor,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 47.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 28.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.70m (5.58ft),  Designated Inspection Frequency: Every 12 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: June 2020,  Other Special Inspection Date: June 2021,  Bridge Improvement Cost: $1,283,000,  Roadway Improvement Cost: $129,000,  Total Project Cost: $1,925,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: L0501405CMUNNBI,  Location: BETW MILL ST&WOODLND RD (Lat: 42.328294,  Lng: -73.240947),  Route carried "on" structure: City street ,  Year Built: 1936,  Status: Posted for load,  Structure Length: 1.10m (3.61ft),  Average Daily Traffic: 388 (year 2019),  Truck Traffic: 6%,  Average Future Daily Traffic: 158 (year 2032),  Features Intersected: WATER WASHNGTN MTN BROOK,  Facility Carried by Structure: HWY WASH MTN RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 6.4m (21.0ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 10.6m (34.8ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 6.4m (21.0ft),  Out-to-Out Width: 6.8m (22.3ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Good,  Operating Rating: 28.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 16.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 10.0 - 19.9% below),  Length Of Structure Improvement: 1.20m (3.94ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021,  Bridge Improvement Cost: $321,000,  Roadway Improvement Cost: $33,000,  Total Project Cost: $482,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: L0501505DMUNNBI,  Location: 500' N. OF WSHGTN MT. RD. (Lat: 42.331650,  Lng: -73.237072),  Route carried "on" structure: City street ,  Year Built: 1935,  Year Reconstructed: 1996,  Status: Open,  Structure Length: 1.57m (5.15ft),  Average Daily Traffic: 388 (year 2018),  Truck Traffic: 6%,  Average Future Daily Traffic: 505 (year 2031),  Design Load: HS 20,  Features Intersected: WATER WASHNGTN MTN BROOK,  Facility Carried by Structure: HWY WOODLAND RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 6.3m (20.7ft),  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 15.2m (49.9ft),  Curb-To-Curb Width: 6.3m (20.7ft),  Out-to-Out Width: 7.3m (24.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Fair,  Operating Rating: 66.4 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 33.4 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.60m (5.25ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2022,  Bridge Improvement Cost: $710,000,  Roadway Improvement Cost: $72,000,  Total Project Cost: $1,066,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: L0501605EMUNNBI,  Location: .25 M EAST OF WOODLAND RD (Lat: 42.332947,  Lng: -73.230347),  Route carried "on" structure: City street ,  Year Built: 1938,  Year Reconstructed: 1988,  Status: Open,  Structure Length: 1.02m (3.35ft),  Average Daily Traffic: 160 (year 2018),  Truck Traffic: 6%,  Average Future Daily Traffic: 158 (year 2031),  Design Load: H 20,  Features Intersected: WATER WASHNGTN MTN BROOK,  Facility Carried by Structure: HWY WASH MTN RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Skew: 3 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.8m (28.9ft),  Curb-To-Curb Width: 5.5m (18.0ft),  Out-to-Out Width: 6.1m (20.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 68.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 40.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.10m (3.61ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $571,000,  Roadway Improvement Cost: $58,000,  Total Project Cost: $857,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>   Show street view

Structure Number: L05019AXYMUNNBI,  Location: NEAR INT. W/ BRADLEY ST. (Lat: 42.321831,  Lng: -73.242061),  Route carried "on" structure: City street ,  Year Built: 2005,  Status: Open,  Structure Length: 3.17m (10.40ft),  Average Daily Traffic: 120 (year 2016),  Truck Traffic: 6%,  Average Future Daily Traffic: 158 (year 2031),  Design Load: HS 25 or greater,  Features Intersected: WATER HOUSATONIC RIVER,  Facility Carried by Structure: HWY GOLDEN HILL
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 6.2m (20.3ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 30.5m (100.1ft),  Curb-To-Curb Width: 6.2m (20.3ft),  Out-to-Out Width: 7.2m (23.6ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Good,  Channel: Good,  Operating Rating: 43.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 25.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Meets minimum limits,  Length Of Structure Improvement: 3.20m (10.50ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Critical Feature Inspection Date: May 2020,  Bridge Improvement Cost: $906,000,  Roadway Improvement Cost: $91,000,  Total Project Cost: $1,360,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: L05020BUUMUNNBI,  Location: OFF CRYSTAL @ WOODS POND (Lat: 42.343733,  Lng: -73.245217),  Route carried "on" structure: City street ,  Year Built: 2020,  Status: Open,  Structure Length: 3.38m (11.09ft),  Average Daily Traffic: 650 (year 2016),  Truck Traffic: 20%,  Design Load: HL 93,  Features Intersected: WATER HOUSATONIC RIVER,  Facility Carried by Structure: HWY VALLEY ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 6.5m (21.3ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 32.0m (105.0ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 7.6m (24.9ft)

Condition: Deck: Excellent,  Superstructure: Excellent,  Substructure: Excellent,  Channel: Excellent,  Operating Rating: 45.4 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 35.6 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Superior to present desirable criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Critical Feature Inspection Date: May 2020,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Epoxy,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: L050236J0DOTNBI,  Location: 0.1 MI W OF ST 102 (Lat: 42.293694,  Lng: -73.241494),  Route carried "on" structure: Other road ,  Year Built: 2011,  Status: Open,  Structure Length: 3.16m (10.37ft),  Average Daily Traffic: 1,200 (year 2017),  Truck Traffic: 1%,  Average Future Daily Traffic: 474 (year 2032),  Design Load: HS 25 or greater,  Features Intersected: WATER HOUSATONIC RIVER,  Facility Carried by Structure: HWY OLD PLEASANT
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Skew: 1 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Single/Spread,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 30.4m (99.7ft),  Curb or Sidewalk Widths: Left: 1.8m (5.9ft),  Right: 0.0m,  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 10.7m (35.1ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 75.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 46.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.20m (10.50ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2021,  Bridge Improvement Cost: $1,660,000,  Roadway Improvement Cost: $167,000,  Total Project Cost: $2,491,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: L050240AXDOTNBI,  Location: 0.3 MI. E. OF MAPLE ST. (Lat: 42.299697,  Lng: -73.214681),  Route carried "on" structure: US 20,  Year Built: 1939,  Year Reconstructed: 1992,  Status: Open,  Structure Length: 1.16m (3.81ft),  Average Daily Traffic: 4,745 (year 2018),  Truck Traffic: 9%,  Average Future Daily Traffic: 6,475 (year 2032),  Features Intersected: WATER GREENWATER BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 32.680,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 10.7m (35.1ft),  Curb or Sidewalk Widths: Left: 2.0m (6.6ft),  Right: 2.0m (6.6ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 17.0m (55.8ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 40.9 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 23.9 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.20m (3.94ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021,  Bridge Improvement Cost: $802,000,  Roadway Improvement Cost: $81,000,  Total Project Cost: $1,204,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: L050270AWDOTNBI,  Location: 0.1 MI W OF BR OVER I-90 (Lat: 42.296822,  Lng: -73.187444),  Route carried "on" structure: US 20,  Year Built: 1956,  Status: Open,  Structure Length: 0.68m (2.23ft),  Average Daily Traffic: 4,745 (year 2018),  Truck Traffic: 9%,  Average Future Daily Traffic: 6,475 (year 2032),  Design Load: H 20,  Features Intersected: WATER GREENWATER BROOK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 35.051,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Skew: 1 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.8m (22.3ft)

Condition: Channel: Fair,  Culverts: Satisfactory,  Operating Rating: 77.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 46.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.40m (1.31ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021,  Bridge Improvement Cost: $250,000,  Roadway Improvement Cost: $26,000,  Total Project Cost: $376,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: L0503005JMUNNBI,  Location: 500' N OF ROUTE 20 (Lat: 42.300208,  Lng: -73.203875),  Route carried "on" structure: City street ,  Year Built: 1970,  Status: Open,  Structure Length: 1.16m (3.81ft),  Average Daily Traffic: 129 (year 2018),  Truck Traffic: 6%,  Average Future Daily Traffic: 158 (year 2033),  Design Load: H 20,  Features Intersected: WATER GREENWATER BROOK,  Facility Carried by Structure: HWY CHESTNUT ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 11.1m (36.4ft),  Curb or Sidewalk Widths: Left: 0.5m (1.6ft),  Right: 1.8m (5.9ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 9.9m (32.5ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Good,  Operating Rating: 82.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 46.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.20m (3.94ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2022,  Bridge Improvement Cost: $487,000,  Roadway Improvement Cost: $49,000,  Total Project Cost: $731,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>   Show street view

Structure Number: L0503305LMUNNBI,  Location: 0.9MI FROM JCT W/ROUTE 20 (Lat: 42.307722,  Lng: -73.194494),  Route carried "on" structure: City street ,  Year Built: 1939,  Status: Open,  Structure Length: 0.61m (2.00ft),  Average Daily Traffic: 129 (year 2019),  Truck Traffic: 2%,  Average Future Daily Traffic: 16 (year 2031),  Design Load: H 15,  Features Intersected: WATER DAVIS BROOK,  Facility Carried by Structure: HWY CHESTNUT ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 2.4m (7.9ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.1m (20.0ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 47.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 28.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Meets minimum limits,  Length Of Structure Improvement: 1.60m (5.25ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $532,000,  Roadway Improvement Cost: $54,000,  Total Project Cost: $799,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: L0503405KMUNNBI,  Location: OFF 20 BTWN FORST&SLVR ST (Lat: 42.297869,  Lng: -73.222906),  Route carried "on" structure: City street ,  Year Built: 1939,  Year Reconstructed: 2018,  Status: Open,  Structure Length: 1.16m (3.81ft),  Average Daily Traffic: 129 (year 2019),  Truck Traffic: 6%,  Average Future Daily Traffic: 158 (year 2032),  Design Load: HL 93,  Features Intersected: WATER GREENWATER BROOK,  Facility Carried by Structure: HWY CHAPEL ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.7m (31.8ft),  Curb-To-Curb Width: 6.1m (20.0ft),  Out-to-Out Width: 7.0m (23.0ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Good,  Channel: Very good,  Operating Rating: 51.8 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 42.1 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Deck Structure Type: Other,  Wearing Surface/Protective System: Wearing Surface: Epoxy Overlay
Find on map >>   Show street view

Structure Number: L050400DLDOT634,  Location: 0.4 MI N OF US20 76.34 (Lat: 42.315711,  Lng: -73.246594),  Route carried "on" structure: City street ,  Year Built: 1943,  Year Reconstructed: 1987,  Status: Open,  Structure Length: 1.37m (4.49ft),  Average Daily Traffic: 129 (year 2017),  Truck Traffic: 6%,  Average Future Daily Traffic: 474 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: RR HRR,  Facility Carried by Structure: HWY CLM ST TO ML
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 11.9m (39.0ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 7.9m (25.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 70.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 50.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.40m (4.59ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021,  Bridge Improvement Cost: $568,000,  Roadway Improvement Cost: $57,000,  Total Project Cost: $853,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: L050414GPDOTNBI,  Location: .5 MI SOUTH OF SPRING ST (Lat: 42.297272,  Lng: -73.269097),  Route carried "on" structure: City street ,  Year Built: 1957,  Year Reconstructed: 1995,  Status: Open,  Structure Length: 6.40m (21.00ft),  Average Daily Traffic: 5,050 (year 2010),  Truck Traffic: 6%,  Average Future Daily Traffic: 3,001 (year 2031),  Design Load: H 20,  Features Intersected: I 90,  Facility Carried by Structure: HWY STOCKBRDG RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 14.162,  Lanes on structure: 2,  Lanes under structure: 4,  Toll: On toll road,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Skew: 2 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 17.4m (57.1ft),  Curb or Sidewalk Widths: Left: 0.8m (2.6ft),  Right: 1.2m (3.9ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 12.0m (39.4ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Operating Rating: 61.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 36.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.50m (21.33ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Bridge Improvement Cost: $2,636,000,  Roadway Improvement Cost: $264,000,  Total Project Cost: $3,955,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: L050424GKDOTNBI,  Location: .2 MI E. FAIRVIEW ST A13 (Lat: 42.296594,  Lng: -73.251786),  Route carried "on" structure: Interstate 90,  Year Built: 1957,  Year Reconstructed: 1993,  Status: Open,  Structure Length: 5.20m (17.06ft),  Average Daily Traffic: 29,932 (year 2016),  Truck Traffic: 22%,  Average Future Daily Traffic: 36,087 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: COMB QUARRY RD & HRR
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 15.610,  Lanes on structure: 2,  Lanes under structure: 2,  Base Highway Network: Yes,  Toll: On toll road,  Owner: State Highway Agency,  Approaching Roadway Width: 12.7m (41.7ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 16.1m (52.8ft),  Curb-To-Curb Width: 12.7m (41.7ft),  Out-to-Out Width: 13.6m (44.6ft)

Condition: Deck: Good,  Superstructure: Fair,  Substructure: Satisfactory,  Operating Rating: 55.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Better than present minimum criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 5.20m (17.06ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $2,778,000,  Roadway Improvement Cost: $278,000,  Total Project Cost: $4,168,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: L050424GLDOTNBI,  Location: .2 MI E. FAIRVIEW ST A13 (Lat: 42.296756,  Lng: -73.251803),  Route carried "on" structure: Interstate 90,  Year Built: 1957,  Year Reconstructed: 1993,  Status: Open,  Structure Length: 5.20m (17.06ft),  Average Daily Traffic: 29,932 (year 2016),  Truck Traffic: 22%,  Average Future Daily Traffic: 36,087 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: COMB QUARRY RD & HRR
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 15.610,  Lanes on structure: 2,  Lanes under structure: 2,  Base Highway Network: Yes,  Toll: On toll road,  Owner: State Highway Agency,  Approaching Roadway Width: 12.7m (41.7ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 16.1m (52.8ft),  Curb-To-Curb Width: 12.7m (41.7ft),  Out-to-Out Width: 13.6m (44.6ft)

Condition: Deck: Good,  Superstructure: Fair,  Substructure: Satisfactory,  Operating Rating: 55.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Better than present minimum criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 5.20m (17.06ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $2,778,000,  Roadway Improvement Cost: $278,000,  Total Project Cost: $4,168,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: L050434GJDOTNBI,  Location: @ CLARK CT INT. A14 (Lat: 42.297022,  Lng: -73.248567),  Route carried "on" structure: City street ,  Year Built: 1957,  Year Reconstructed: 1994,  Status: Open,  Structure Length: 4.94m (16.21ft),  Average Daily Traffic: 3,362 (year 2017),  Truck Traffic: 5%,  Average Future Daily Traffic: 474 (year 2031),  Design Load: HS 20,  Features Intersected: I 90,  Facility Carried by Structure: HWY MARBLE ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 15.932,  Lanes on structure: 2,  Lanes under structure: 4,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 15.8m (51.8ft),  Curb or Sidewalk Widths: Left: 0.8m (2.6ft),  Right: 1.2m (3.9ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 11.6m (38.1ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Fair,  Operating Rating: 62.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 37.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 5.00m (16.40ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Bridge Improvement Cost: $2,279,000,  Roadway Improvement Cost: $228,000,  Total Project Cost: $3,419,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: L050444GGDOTNBI,  Location: AT MILE MARKER 10.3 A15 (Lat: 42.297833,  Lng: -73.240656),  Route carried "on" structure: Interstate 90,  Year Built: 1957,  Year Reconstructed: 1990,  Status: Open,  Structure Length: 11.90m (39.04ft),  Average Daily Traffic: 29,932 (year 2016),  Truck Traffic: 22%,  Average Future Daily Traffic: 36,087 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: COMB US20 & HOUSATNC R
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 16.576,  Lanes on structure: 2,  Lanes under structure: 4,  Base Highway Network: Yes,  Toll: On toll road,  Owner: State Highway Agency,  Approaching Roadway Width: 12.6m (41.3ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 6,  Length of Maximum Span: 29.1m (95.5ft),  Curb-To-Curb Width: 12.6m (41.3ft),  Out-to-Out Width: 13.6m (44.6ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 53.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 31.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Underclear: Equal to present minimum criteria,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 12.00m (39.37ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 36 months,  Inspection Date: April 2021,  Underwater Inspection Date: April 2020,  Bridge Improvement Cost: $6,411,000,  Roadway Improvement Cost: $642,000,  Total Project Cost: $9,617,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: L050444GHDOTNBI,  Location: AT INT. 2 A15 (Lat: 42.297981,  Lng: -73.240692),  Route carried "on" structure: Interstate 90,  Year Built: 1957,  Year Reconstructed: 1991,  Status: Open,  Structure Length: 11.21m (36.78ft),  Average Daily Traffic: 29,932 (year 2016),  Truck Traffic: 22%,  Average Future Daily Traffic: 36,087 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: COMB US20 & HOUSATNC R
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 16.576,  Lanes on structure: 2,  Lanes under structure: 4,  Base Highway Network: Yes,  Toll: On toll road,  Owner: State Highway Agency,  Approaching Roadway Width: 12.6m (41.3ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 6,  Length of Maximum Span: 29.1m (95.5ft),  Curb-To-Curb Width: 12.6m (41.3ft),  Out-to-Out Width: 13.6m (44.6ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Good,  Operating Rating: 53.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Underclear: High priority of corrective action,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 11.30m (37.07ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 36 months,  Inspection Date: April 2021,  Underwater Inspection Date: April 2020,  Bridge Improvement Cost: $6,037,000,  Roadway Improvement Cost: $604,000,  Total Project Cost: $9,056,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: L050450BYDOTNBI,  Location: 0.3 MI W OF US 20 (Lat: 42.292819,  Lng: -73.240758),  Route carried "on" structure: State highway 102,  Year Built: 1958,  Status: Open,  Structure Length: 5.59m (18.34ft),  Average Daily Traffic: 12,284 (year 2018),  Truck Traffic: 11%,  Average Future Daily Traffic: 21,636 (year 2031),  Design Load: HS 20,  Features Intersected: WATER HOUSATONIC RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 19.341,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 13.4m (44.0ft),  Skew: 3 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 31.1m (102.0ft),  Curb or Sidewalk Widths: Left: 0.7m (2.3ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 15.2m (49.9ft)

Condition: Deck: Satisfactory,  Superstructure: Poor,  Substructure: Good,  Channel: Good,  Operating Rating: 42.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 18.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.70m (21.98ft),  Designated Inspection Frequency: Every 12 months,  Underwater Inspection Frequency: Every 36 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: May 2020,  Underwater Inspection Date: August 2021,  Other Special Inspection Date: May 2021,  Bridge Improvement Cost: $5,756,000,  Roadway Improvement Cost: $576,000,  Total Project Cost: $8,635,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>   Show street view

Structure Number: L050464GQDOTNBI,  Location: .2 MI S.DEVON RD A10 (Lat: 42.297464,  Lng: -73.280214),  Route carried "on" structure: Interstate 90,  Year Built: 1957,  Year Reconstructed: 1993,  Status: Open,  Structure Length: 2.99m (9.81ft),  Average Daily Traffic: 29,932 (year 2016),  Truck Traffic: 22%,  Average Future Daily Traffic: 36,087 (year 2031),  Design Load: HS 20,  Features Intersected: HWY WEST RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 13.357,  Lanes on structure: 2,  Lanes under structure: 2,  Base Highway Network: Yes,  Toll: On toll road,  Owner: State Highway Agency,  Approaching Roadway Width: 12.8m (42.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 10.8m (35.4ft),  Curb-To-Curb Width: 12.8m (42.0ft),  Out-to-Out Width: 13.7m (44.9ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Fair,  Operating Rating: 61.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 36.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present desirable criteria,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.00m (9.84ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $1,615,000,  Roadway Improvement Cost: $162,000,  Total Project Cost: $2,423,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: L050464GRDOTNBI,  Location: .2 MI S. DEVON RD A10 (Lat: 42.297772,  Lng: -73.280197),  Route carried "on" structure: Interstate 90,  Year Built: 1957,  Year Reconstructed: 1993,  Status: Open,  Structure Length: 2.93m (9.61ft),  Average Daily Traffic: 29,932 (year 2016),  Truck Traffic: 22%,  Average Future Daily Traffic: 36,087 (year 2031),  Design Load: HS 20,  Features Intersected: HWY WEST RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 13.357,  Lanes on structure: 2,  Lanes under structure: 2,  Base Highway Network: Yes,  Toll: On toll road,  Owner: State Highway Agency,  Approaching Roadway Width: 12.8m (42.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 10.8m (35.4ft),  Curb-To-Curb Width: 12.8m (42.0ft),  Out-to-Out Width: 13.7m (44.9ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Fair,  Operating Rating: 61.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 36.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present desirable criteria,  Underclear: Meets minimum limits,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 3.00m (9.84ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $1,615,000,  Roadway Improvement Cost: $162,000,  Total Project Cost: $2,423,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: L050474GMDOTNBI,  Location: AT MM 9.4 A12 (Lat: 42.296053,  Lng: -73.257700),  Route carried "on" structure: Interstate 90,  Year Built: 1957,  Year Reconstructed: 1993,  Status: Open,  Structure Length: 3.26m (10.70ft),  Average Daily Traffic: 12,308 (year 2017),  Truck Traffic: 20%,  Average Future Daily Traffic: 36,087 (year 2031),  Design Load: HS 20,  Features Intersected: HWY FAIRVIEW ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 15.127,  Lanes on structure: 2,  Lanes under structure: 2,  Base Highway Network: Yes,  Toll: On toll road,  Owner: State Highway Agency,  Approaching Roadway Width: 12.8m (42.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 10.1m (33.1ft),  Curb-To-Curb Width: 12.8m (42.0ft),  Out-to-Out Width: 13.7m (44.9ft)

Condition: Deck: Good,  Superstructure: Fair,  Substructure: Satisfactory,  Operating Rating: 57.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 34.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present desirable criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.30m (10.83ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Bridge Improvement Cost: $1,776,000,  Roadway Improvement Cost: $178,000,  Total Project Cost: $2,665,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: L050474GNDOTNBI,  Location: AT MM 9.4 A12 (Lat: 42.296225,  Lng: -73.257708),  Route carried "on" structure: Interstate 90,  Year Built: 1957,  Year Reconstructed: 1993,  Status: Open,  Structure Length: 3.26m (10.70ft),  Average Daily Traffic: 12,181 (year 2017),  Truck Traffic: 22%,  Average Future Daily Traffic: 36,087 (year 2031),  Design Load: HS 20,  Features Intersected: HWY FAIRVIEW ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 15.127,  Lanes on structure: 2,  Lanes under structure: 2,  Base Highway Network: Yes,  Toll: On toll road,  Owner: State Highway Agency,  Approaching Roadway Width: 12.8m (42.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 10.1m (33.1ft),  Curb-To-Curb Width: 12.8m (42.0ft),  Out-to-Out Width: 13.7m (44.9ft)

Condition: Deck: Good,  Superstructure: Fair,  Substructure: Satisfactory,  Operating Rating: 57.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 34.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present desirable criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.30m (10.83ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Bridge Improvement Cost: $1,776,000,  Roadway Improvement Cost: $178,000,  Total Project Cost: $2,665,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: L050484GFDOTNBI,  Location: INT. OF ROUTES 20 & 102 (Lat: 42.296881,  Lng: -73.238961),  Route carried "on" structure: Ramp Interstate 20,  Year Built: 1957,  Year Reconstructed: 1992,  Status: Open,  Structure Length: 4.15m (13.62ft),  Average Daily Traffic: 5,431 (year 2018),  Truck Traffic: 13%,  Average Future Daily Traffic: 4,106 (year 2031),  Design Load: HS 20+Mod,  Features Intersected: US 20 HOUSATONIC ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 30.223,  Lanes on structure: 1,  Lanes under structure: 4,  Base Highway Network: Yes,  Toll: On toll road,  Owner: State Highway Agency,  Approaching Roadway Width: 7.6m (24.9ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 18.7m (61.4ft),  Curb-To-Curb Width: 7.6m (24.9ft),  Out-to-Out Width: 8.5m (27.9ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Good,  Operating Rating: 60.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 36.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.20m (13.78ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Bridge Improvement Cost: $111,000,  Roadway Improvement Cost: $12,000,  Total Project Cost: $167,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: L050494GDDOTNBI,  Location: .7 MI W. MAPLE ST A16 (Lat: 42.298483,  Lng: -73.234947),  Route carried "on" structure: Interstate 90,  Year Built: 1957,  Year Reconstructed: 1990,  Status: Open,  Structure Length: 3.82m (12.53ft),  Average Daily Traffic: 12,308 (year 2017),  Truck Traffic: 22%,  Average Future Daily Traffic: 31,902 (year 2031),  Design Load: HS 20,  Features Intersected: I 90 RAMPS INT 2
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 17.059,  Lanes on structure: 2,  Lanes under structure: 4,  Base Highway Network: Yes,  Toll: On toll road,  Owner: State Highway Agency,  Approaching Roadway Width: 12.6m (41.3ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 17.2m (56.4ft),  Curb-To-Curb Width: 12.6m (41.3ft),  Out-to-Out Width: 13.6m (44.6ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Fair,  Operating Rating: 51.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 30.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Better than present minimum criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.90m (12.80ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Bridge Improvement Cost: $2,084,000,  Roadway Improvement Cost: $209,000,  Total Project Cost: $3,127,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up,  Deck Protection: Epoxy Coated Reinforcing